| 1 | Drain Size (1000x1000 mm.) (600X600) (450X300) |
| 2 | Excavation in foundation in B.C soil including lift up to 15 meter and lead upto 30 m (100 ft) and including filling, watering & ramming of excavated earth into the trenches or into the space between the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth as directed by the Engineer-in-charge upto a distance of 30 M from the foundation trenches.(S.I.No. 251) |
| 3 | Sand filling in plinth including supply of necessary quantity of sand from a distance not exceeding 8km (5 miles) from the side of work & including watering ,dressing etc. Rate to include cost of all materials,labour and tools & plants,etc. required for proper completion of the work. |
| 4 | Cement concrete with 4cm (1/2\"\") gauge approved stone ballast, approved coarse sand. cement in the proportion 1 : 4 : 8 including supply of all materials,labour and tools and plants etc. required for proper completion of the work. As per S.I. No.-281 |
| 5 | RCC work with cement approved coarse sand and 2cm. (3/4\"\") gauge approved stone ballast in the proportion 1:2:4 in lintels of doors and windows, excluding supply of reinforcement and its binding but including its fixing and binding the same with 24 B.W.G.I wire.and including necessary cantering and suttering etc and also including supply of all materials,labour and tools and plants etc. required for proper completion of the work. binding wire to be supplied by the contractor free of cost. As in Item (283) above but in RCC 1:1.5:3 As Per SI No. 288 |
| 6 | Mild steel of iron in plain work such as reinforced concrete/ brick work (when not included in over all rates) wrought to required shape as necessary including bending for proper completion of the work and including supply of steel, its wastage and hooks and authorised over lapping shall be measured. |
| 7 | Excavation in foundation in B.C soil including lift up to 15 meter and lead upto 30 m (100 ft) and including filling, watering & ramming of excavated earth into the trenches or into the space between the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth as directed by the Engineer-in-charge upto a distance of 30 M from the foundation trenches.(S.I.No. 251) |
| 8 | Sand filling in plinth including supply of necessary quantity of sand from a distance not exceeding 8km (5 miles) from the side of work & including watering ,dressing etc. Rate to include cost of all materials,labour and tools & plants,etc. required for proper completion of the work. |
| 9 | Cement concrete with 4cm (1/2\"\") gauge approved stone ballast, approved coarse sand. cement in the proportion 1 : 4 : 8 including supply of all materials,labour and tools and plants etc. required for proper completion of the work. As per S.I. No.-281 |
| 10 | RCC work with cement approved coarse sand and 2cm. (3/4\"\") gauge approved stone ballast in the proportion 1:2:4 in lintels of doors and windows, excluding supply of reinforcement and its binding but including its fixing and binding the same with 24 B.W.G.I wire.and including necessary cantering and suttering etc and also including supply of all materials,labour and tools and plants etc. required for proper completion of the work. binding wire to be supplied by the contractor free of cost. As in Item (283) above but in RCC 1:1.5:3 As Per SI No. 288 |
| 11 | Mild steel of iron in plain work such as reinforced concrete/ brick work (when not included in over all rates) wrought to required shape as necessary including bending for proper completion of the work and including supply of steel, its wastage and hooks and authorised over lapping shall be measured. |
| 12 | Excavation in foundation in B.C soil including lift up to 15 meter and lead upto 30 m (100 ft) and including filling, watering & ramming of excavated earth into the trenches or into the space between the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth as directed by the Engineer-in-charge upto a distance of 30 M from the foundation trenches.(S.I.No. 251) |
| 13 | Sand filling in plinth including supply of necessary quantity of sand from a distance not exceeding 8km (5 miles) from the side of work & including watering ,dressing etc. Rate to include cost of all materials,labour and tools & plants,etc. required for proper completion of the work. |
| 14 | Cement concrete with 4cm (1/2\"\") gauge approved stone ballast, approved coarse sand. cement in the proportion 1 : 4 : 8 including supply of all materials,labour and tools and plants etc. required for proper completion of the work. As per S.I. No.-281 |
| 15 | RCC work with cement approved coarse sand and 2cm. (3/4\"\") gauge approved stone ballast in the proportion 1:2:4 in lintels of doors and windows, excluding supply of reinforcement and its binding but including its fixing and binding the same with 24 B.W.G.I wire.and including necessary cantering and suttering etc and also including supply of all materials,labour and tools and plants etc. required for proper completion of the work. binding wire to be supplied by the contractor free of cost. As in Item (283) above but in RCC 1:1.5:3 As Per SI No. 288 |
| 16 | Mild steel of iron in plain work such as reinforced concrete/ brick work (when not included in over all rates) wrought to required shape as necessary including bending for proper completion of the work and including supply of steel, its wastage and hooks and authorised over lapping shall be measured. |
| 17 | Path-Way |
| 18 | Construction of granular sub-base by providing close Graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with front end loader at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401 |
| 19 | Cost of local sand for locking of C.C. Block. (PWD-255) |
| 20 | Providing and laying of rubble moulded zig zag interlocking concrete block Pavements having thickness 80 mm as per drawings and technical Specification Clause 1504. (PWD-PAGE NO. 87 - 6.7, 1) |
| 21 | Providing and laying at or near ground level factory made kerb stone of M-25 grade cement concrete in position to the required line, level and curvature, jointed with cement mortar 1:3 (1 cement: 3 coarse sand), including making joints with or without grooves (thickness of joints except at sharp curve shall not to more than 5 mm), including making drainage opening wherever required complete etc. as per direction of Engineer in-charge (length of finished kerb edging shall be measured to calculate volume for payment). (Precast C.C. kerb stone shall be approved by Engineer-in-charge). (DSR-16.69) |
| 22 | Painting Ist coat over priming coat (butexcluding cost of priming coat) on steeland other metal surfaces up to 10 cm.width or girth or small articles notexceeding 0.10sqm in area white superiorsynthetic enamel such as LUXOL3,Hi-glossapcolite superlac, DULUX specifiedbrushing to give an even shade andincluding cleaning the surface of alldirt,dust and other foreign matter sandpapering and stoping including cost ofall materials, labour tools and plantsetc. required for proper completion ofthe work. (PWD-641+642) Please Enable Macros to View BoQ information |