| 1 | Fitting and erecting one HT DP using A type pole in position incl. fitting 2 channel cross arms, digging & back filling pit, drawing earth leads. |
| 2 | Drilling hole of various sizes on existing Channel/Cross Arm. |
| 3 | Loading HT A type pole from the stacking place and unloading the same at work site (transport by vehicle). |
| 4 | Erecting one 100kVA Transformer to existing DP and giving connections, incl. loading & unloading, excluding transportation. |
| 5 | Transporting Transformers by hired vehicle upto 5km and upto 2 No. of 63 to 250kVA Transformers / RMUs excluding loading & unloading. |
| 6 | Stringing of 1.1 kV Aerial bunched cable of size 3 x 70 + 1 x 16+1x 50 sqmm with bare/insulated Messenger through existing poles |
| 7 | Installing One No. Insulation piercing connector of size Main :16 to 95 ,Tap:1.5 to 16 Sq.mm |
| 8 | Installation of Insulation piercing connector for main to service line main :16-95 sqmm, Tap 16-95 sqmm |
| 9 | Erection of Anchor clamp / dead end clamp for LT ABC of any size |
| 10 | Erection of suspension clamp for LT ABC of any size |
| 11 | Installation of Pre-insulated lugs for 70sqmm |
| 12 | Installation of Pre-insulated lugs for 50sqmm |
| 13 | Providing End Caps |
| 14 | Stringing of 11 kV Aerial bunched cable of size 3 x 120 + 1 x 95 sqmm with bare/insulated Messenger through existing poles |
| 15 | Erection of Anchor clamp / dead end clamp for 11kV ABC of any size |
| 16 | Erection of suspension clamp for 11KV ABC of any size |
| 17 | Providing Cable Tie |
| 18 | Fiting One no MVT on existing cross arm including 2 nos end termination (for One phase) of any rating for 11 kV AB Cable |
| 19 | Loading HT PSC pole from the stacking place and unloading the same at work site (transport by vehicle). |
| 20 | Transporting poles by hired vehicle to a distance upto 5km and carrying upto 4 poles excluding loading & unloading. |
| 21 | Transporting Transformers by hired vehicle to a distance beyond 5km and upto 2 No. of 63 to 250kVA Transformers / RMUs (Running km). |
| 22 | Dismantling (without damage) one LT PSC/RCC pole after disconnecting stays, strut etc. and stacking the same. |
| 23 | Dismantling (without damage) one km LT Sph 2 wire OH line, cross arms, insulators and stacking the conductors in rolls. |
| 24 | Transferring LT 3ph 4/5 wire OH line to newly erected HT/LT pole and refitting all items to the new pole. |
| 25 | Additional rate for refitting/redoing one Shackle set and reshackling one span while renewing any type of pole. |
| 26 | Renewal of existing damaged/broken old LT stay with existing stay rod. |
| 27 | Straightening one Slanted LT pole after unbinding the line and rebinding the line after work. |
| 28 | Fitting one No. Section fuse on LT line with dropping cables, crimping sockets, connecting with bolt&nut etc. |
| 29 | Providing concrete muffing (0.45x0.45x1.5m) inclusive of cost of all material (as per specification). |
| 30 | Pole numbering using printed Aluminium sheets / Painting the surface of pole with anti algal yellow paint and painting Letters with black paint as specified incl. cost of paint. |
| 31 | Providing Transformer fencing , using 50x50x6mm Angle iron, 40 x 6 mm MS flat and 8 mm MS rod as specified, incl cost of transportation & foundation |
| 32 | Providing yard metalling with 6mm & 40mm thick blue metal as specified after constructing a curb wall. |
| 33 | Fitting 6 channel cross arms, AB switch, DO fuse, LA, HT & LT connections on existing DP, 3 LT fuses. |
| 34 | Fitting and providing one HT Stay for 11kV pole incl. digging & back filling pit. |
| 35 | Fitting one additional Fuse unit and giving connection from Transformer to fuse and DB to LT OH line. |
| 36 | Installing one DTR Meter with box on existing poles and giving the complete connections incl. conveyance of materials. |
| 37 | Erecting one LT PSC Pole in position incl. digging & back filling pit. |
| 38 | Providing one Coil Earth using GI earth wire, digging separate pit at standard distance away from the pole/structure & backfilling. |
| 39 | Fitting one Additional 75x40mm, 1.8m Channel cross arm in existing single pole incl. conveyance of materials. |
| 40 | Providing Strut using LT PSC pole incl. digging & back filling pit. |
| 41 | Fitting and providing one Strut using HT PSC pole incl. digging & back filling pit. |
| 42 | Dismantling and reconnecting Sph service connection from the OH line incl. lowering down the WP portion. |
| 43 | Dismantling and reconnecting 3ph service connection from the OH line incl. lowering down the WP portion. |
| 44 | Providing Stay for LT poles incl. digging & back filling pit. |
| 45 | Fitting and providing one HT Fly stay for 11kV pole using HT PSC pole incl. digging & back filling pits. |
| 46 | Renewal of existing damaged/old LT PSC/RCC (Sph line) pole with new PSC pole in place and refitting of all items incl. conveyance (except pole). |
| 47 | Erecting 9m PSC pole as support pole for ABC stringing work-New |
| 48 | Erecting HT A-Type pole as support pole for ABC stringing work -New |
| 49 | Dismantling (without damage) one 11kV PSC/RCC pole after disconnecting stays, strut etc. and stacking the same. |
| 50 | Fitting and erecting one HT A type Pole in position incl. fitting cross arm, digging & back filling pit, drawing earth leads. |
| 51 | Insertion of one LT PSC pole in existing Sph OH line incl. digging & back filling pit, fitting cross arm, insulator, binding etc. |
| 52 | Additional rate for excavation of one Pit for Coil Earthing in Hard Laterite. |
| 53 | Additional rate for excavation of Pit for A type pole in Laterite. |
| 54 | Additional rate for excavation of one Earth Pit (2.5m depth) in Hard Laterite. |
| 55 | Additional rate for excavation of one Pit for HT Pole/HT Stay in Hard Laterite. |
| 56 | Errection and commissioning of street light metering with timer |
| 57 | Insertion of one LT PSC pole in existing 3ph OH line incl. digging & back filling pit, fitting cross arm, insulator, binding etc. |
| 58 | Providing one Earth using earth pipe incl. digging separate pit at standard distance away from the pole/structure & backfilling. |
| 59 | Providing WP support with PSC pole incl. digging & back filling pit. Please Enable Macros to View BoQ information |