Name of Work:- Construction Of Farm Approach Gravel Road At Kvk, Sawai Madhopur
Sl. No.
Item Description
1
Farm Approach gravel road
2
Clearing and grubbing road land including uprooting rank vegetation, grass, brush, shrubs, saplings and trees of girth upto 300mm, removal of stumps, disposal of unserviceable Material and stacking of serviceable Material upto 1000m from road boundary. (MoRTH Specification : Clause 201). BY MANUAL MEANS In area of Light Jungle
3
Loosening, levelling and compacting original ground supporting embankment to facilitate placement of first layer of embankment, scarified to a depth of 150mm, mixed with water at OMC and then compacted by vibratory roller 8-10 tonne to achieve minimum dry density as given in table 300-2 for embankment construction as per MoRTH specification : Clause No. 305.
4
Providing, laying and spreading and compacting specified graded crushed stone in sub-base course including premixing the Material at OMC in mechanical mixer (Pug mill), carriage of mixed Material, laying in uniform layers with Motor Grader, F.E. Loader, on a prepared surface and compacting with Vibratory Compactor to achieve the desired density including all Material, labour, machinery, lighting barricading and maintenance of Driversion complete. (MoRTH specification clause 401). with all lead & lift
5
Providing, laying and spreading of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401. By Mix in Place Method Grading-III
6
Providing and Laying cement concrete 1:4:8 in sub-base over a prepared sub-grade with coarse and fine aggregate conforming to IS:383, the size of coarse aggregate not exceeding 25mm, aggregate cement ratio not to exceed 15:1, aggregate gradation after blending to be as per Table 600-1, cement content not to be less than 150 kg/cum, optimum moisture content to be determined during trail length construction, concrete strength not to be less than 10 Mpa at 7 days, mixed in a batching plant, transported to site, laid with a paver with electronic sensor, compacting with 8-10 tonne vibratory roller, finishing and curing as per MoRTH specification : Clause No. 601, 112. Please Enable Macros to View BoQ information
We takes all possible care for accurate & authentic tender information, however Users
are requested to refer Original source of Tender Notice / Tender Document published by
Tender Issuing Agency before taking any call regarding this tender.