| 1 | Dismantling of C.C. Road & sorting out & stacking of serviceable materials including supply of lab, T&P etc complete |
| 2 | Excavation of foundation in ordinary soil including lift up to 1.50 m with supply of lab,T&P etc all complete |
| 3 | Concrete work with 20 gauge brick blast, L.Sand & cement in foundation under floor in prop 1:05:1 including supply of lab, mat,T&P etc complete |
| 4 | Making necessary arrangement of barricading with sal ballies, red flag, lab, T&P etc complete |
| 5 | 1st class brick work with 1:3 cement & coarse sand mortar including supply of lab, mat, T&P etc complete |
| 6 | 12 mm thick plaster with 1:3 cement & L.sand mortar including supply of lab, mat, T&P etc complete |
| 7 | Providing bier to retain sewage water etc complete |
| 8 | RCC work with cement, C.sand & 20 mm gauge appd. stone ballast in prop. 1:1.5:3 including supply of lab, mat, T&P etc complete |
| 9 | Mild steel or iron work in slab including supply of lab, T&P etc complete |
| 10 | Bailing out of water with 5 HP mud pump including accessories & supply of lab,T&P etc complete |
| 11 | Cast cement concrete for seat fixing including supply of lab, mat,T&P etc complete |
| 12 | Supply & laying of RCC pipe 300 mm dia including supply of lab, mat, T&P etc complete |
| 13 | Making sewer line connection with supply of lab, mat, T&P etc complete |
| 14 | Supply of RCC frame of size 650 x 75 mm |
| 15 | Supply of RCC cover on M.H size 650 x 75 mm |
| 16 | Disposal of surplus earth & dismantled malva of excavated earth etc complete |
| 17 | Unforeseen work as cartage of pipe including loading/unloading etc complete Please Enable Macros to View BoQ information |