| 1 | Cartage of 8.5 M PCC Pole/11 M STP/13 M STP Poles From Store lalitpur or From any other place to the respective site of work through the Kachha Pacca road including at the respective ends also including etc and also inlcuding the cost of labour T&P carrier etc required for proper completion of work. |
| 2 | Cartage of line material viz stone pad top channel Dropper channel Disc Insulator and other line material from ESC/ASK Store lalitpur or any other place to the respective site of work through the kachha pacca road including the work of its loading & unloading at the respective ends including the work of its dragging etc and also including the cost of labour T&P and carrier etc required for proper completion of Work. |
| 3 | Erection of 8.5 M PCC Pole/11 M STP/ 13 M STP Pole Double pole Support of poles including complete HT/LT Fitting as per RESSPO manual and as per direction of Engineer in charge the cost of labour T&P and Carrier etc required for proper completion of work. |
| 4 | Erection of 8.5 M PCC Pole/11 M STP/ 13 M STP Pole Single Support of poles including complete HT/LT Fitting as per RESSPO manual and as per direction of Engineer in charge the cost of labour T&P and Carrier etc required for proper completion of work. |
| 5 | Grouting of 8.5 M PCC Pole/11 M STP/13 M STP Pole as per RESSPO Manual and as per direction of Engineer incharge including the cost of Labour T&P and Carrier etc required for proper completion of work. The support shall be grouted with cement sand & Bricks/stone ballast in ration 1:4:8 including the cost of arrangement of cement sand brick ballast/stone ballast stone pad etc as per actual site required. |
| 6 | Erection & Grouting of Stay Set as per RESSPO manual and also inlcuding the cost of all grouting material labour T&P etc required for proper completion of work. |
| 7 | Erection of Earthing Complete as per direction of supervising engineer. Its including the cost of labour T&P carrier etc required for proper completion of work. |
| 8 | Laying, Sagging, Stringing, Binding and jumpring etc ACSR Weasel Conductor/ACSR Rabbit Conductor/Old new on the newly erected pole other place as per RESSPO Manual and as per direction of Supervising Engineer. |
| 9 | Laying, Sagging, Stringing, Binding and jumpring etc of ABC cable 3X120+ 1X95+1X16 mm, 3X95+1X70+1X16 mm & 3X50+1X35+1X16 mm new on the newly erected pole other place as per RESSPO Manual and as per direction of Supervising Engineer. |
| 10 | Febrication of 11 Kv V Type X Arm (16 mm Hole 2 No each X Ams) as per RESSPO Drawing with loading, unloading & Cartage all complete Work. |
| 11 | Febrication of 11 Kv Dropper Channel (16 mm Hole 7 No each Dropper Channel) as per RESSPO Drawing with loading, unloading & Cartage all complete Work. |
| 12 | Febrication of 11 Kv Top Channel (16 mm Hole 10 No each Top Channel) as per RESSPO Drawing with loading, unloading & Cartage all complete Work. |
| 13 | Febrication of 11 Kv T off Channel 100X50X1300 (16 mm Hole 8 No each Top Channel) as per RESSPO Drawing with loading, unloading & Cartage all complete Work. |
| 14 | Fixing & Erection of 11 Kv Dropper Channel as per RESSPO Drawing All Complete Work. |
| 15 | Fixing & Erection of 11 Kv Top Channel as per RESSPO Drawing All complete Work. |
| 16 | Erection of 11 Kv T off Channel 100X50X1300 as per RESSPO Manual Drawing All complete Work. |
| 17 | Erection of 11 Kv X Arm as per RESSPO Drawing All Complete Work. |
| 18 | Erection of 3x70 sqmm XLPE 11 kv Cable jointing Outdoor including complete HT/LT Fitting as per RESSPO manual and as per direction of Engineer in charge the cost of labour T&P and Carrier etc required for proper completion of work. |
| 19 | Erection of 3x120 sqmm XLPE 11 kv Cable jointing Outdoor including complete HT/LT Fitting as per RESSPO manual and as per direction of Engineer in charge the cost of labour T&P and Carrier etc required for proper completion of work. |
| 20 | Erection of 11 kv Pilfer Proof metering Cubilcle including complete HT/LT Fitting as per RESSPO manual and as per direction of Engineer in charge the cost of labour T&P and Carrier etc required for proper completion of work. |
| 21 | Erection of CT/PT Pole Mounted Unit including complete HT/LT Fitting as per RESSPO manual and as per direction of Engineer in charge the cost of labour T&P and Carrier etc required for proper completion of work. |
| 22 | Erection of 11/0.4 kv 16 kva /25 kva T/F complete HT/LT Fitting as per RESSPO manual and as per direction of Engineer in charge the cost of labour T&P and Carrier etc required for proper completion of work. |
| 23 | Erection of 11/0.4 kv 63 kva T/F complete HT/LT Fitting as per RESSPO manual and as per direction of Engineer in charge the cost of labour T&P and Carrier etc required for proper completion of work. |
| 24 | Erection of 11/0.4 kv 100 kva T/F complete HT/LT Fitting as per RESSPO manual and as per direction of Engineer in charge the cost of labour T&P and Carrier etc required for proper completion of work. |
| 25 | Erection of 11/0.4 kv 250 kva T/F complete HT/LT Fitting as per RESSPO manual and as per direction of Engineer in charge the cost of labour T&P and Carrier etc required for proper completion of work. |
| 26 | Dismentling of old line material as per site |
| 27 | Carriage of old dismentled item from pit site to store lalipur with loading & unloading Please Enable Macros to View BoQ information |