| 1 | Carriage of following material from store center to site of work including loading & unloading at both ends maximum distance up to 100 Km. :- |
| 2 | STP Pole 13 mtr long |
| 3 | PCC Pole 8.5 mtr long |
| 4 | ACSR Weasal Conductor |
| 5 | 11 KV Pin Insulator with nut and bolt |
| 6 | 11 KV Disc Insulator with nut and bolt |
| 7 | ACSR RABBIT CONDUCTOR |
| 8 | 11 KV CROSS ARM |
| 9 | Guarding ANGLE 65*65*6*1600 MM |
| 10 | LT ABC 3*95 SQMM |
| 11 | 11 KV XLPE CABLE 3*120 SQMM |
| 12 | 11 KV XLPE CABLE 3*185 SQMM |
| 13 | Joint Kit 11 KV XPLE Cable 3*120 sqmm |
| 14 | Joint Kit 11 KV XPLE Cable 3*185 sqmm |
| 15 | Stay set |
| 16 | MS CHANNEL 125*65*2240 MM |
| 17 | M.S. ANGLE 75*75*6 MM |
| 18 | T-off channel |
| 19 | MS Angle 65x65x6 mm BRACING |
| 20 | Earthing rod |
| 21 | Guarding Wire 6/8 SWG |
| 22 | LT ABC 3*50 SQMM |
| 23 | Errection STP Pole 13 mtr long/PCC pole 8.5 mtr long after digging a pit of size 1.6 mtr deep in all type of Soil including grouting ratio (1:4:8) of the pole with proper ramming after completion of work (as per UPPCL Respo). |
| 24 | Errection of Double PCC Pole 8.5 mtr long after digging a pit of size 1.20x0.60x1.6 mtr in all type of Soil for each pole including grouting ratio (1:4:8) of the pole with proper ramming after completion of work (as per UPPCL Respo). |
| 25 | Laying, lifting, Stringing & Proper sagging of ACSR RABBIT CONDUCTOR For HT/LT Line including binding & junpering properly. (as per UPPCL Respo) |
| 26 | Laying, lifting, Stringing & Proper sagging of ACSR WEASAL CONDUCTOR For HT/LT Line including binding & junpering properly. (as per UPPCL Respo) |
| 27 | Fixing of Stay rod complete as per norms (as per UPPCL Respo). |
| 28 | Fixing of MS Earthing of each 11 KV line and pole after drive of electrodes if size 20mm x 250 mm and connection the earthing point with GI wire. (as per UPPCL Respo). |
| 29 | Febrication and Fixing of MS Channel 125*65*2240 mm fixing all HT/LT assesories Fues Set HT/LT Pin Insulator on D/P Pole.(as per UPPCL Respo) |
| 30 | Febrication and Fixing of MS Angle 75*75*6 mm fixing all HT/LT assesories Fues Set HT/LT Pin Insulator on D/P Pole.(as per UPPCL Respo) |
| 31 | Febrication and Fixing of Guarding Angle 65*65*6*1600 mm fixing all HT/LT assesories Fues Set HT/LT Pin Insulator on D/P Pole.(as per UPPCL Respo) |
| 32 | Febrication and Fixing of MS Angle 65*65*6 bracing fixing all HT/LT assesories Fues Set HT/LT Pin Insulator on D/P Pole.(as per UPPCL Respo) |
| 33 | Fixing of 11 KV Pin Insulator (as per UPPCL Respo). |
| 34 | Fixing of 11 KV Disc Insulator (as per UPPCL Respo). |
| 35 | Fixing of T-off channel (as per UPPCL Respo). |
| 36 | Fixing of 11 KV X-ARM (as per UPPCL Respo). |
| 37 | Fixing of guarding wire (as per UPPCL Respo). |
| 38 | Excatvation of Trunch (Kaccha Road) for Cable (as per UPPCL Respo). |
| 39 | Laying of 11 KV XPLE Cable 3*120 sqmm pit of the size 1.5 in the trunch and roas crossing in the air. (as per UPPCL Respo) |
| 40 | Laying of 11 KV XPLE Cable 3*185 sqmm pit of the size 1.5 in the trunch and roas crossing in the air. (as per UPPCL Respo) |
| 41 | Filling of Joint Kit 11 KV XPLE Cable 3*120 sqmm (as per UPPCL Respo). |
| 42 | Filling of Joint Kit 11 KV XPLE Cable 3*185 sqmm (as per UPPCL Respo). |
| 43 | Laying of LT ABC 3*95 sqmm including fixing of all LT ABC assesories on support (as per UPPCL Respo) |
| 44 | Laying of LT ABC 3*50 sqmm including fixing of all LT ABC assesories on support (as per UPPCL Respo) |
| 45 | Providing and Fixing of MS Nut and Bolts. (as per Direction of supervixing Engineer) |
| 46 | Providing and Fixing Clamp with nut and bolt (as per Direction of supervixing Engineer) |
| 47 | Providing and Fixing Danger Board with clamp (as per Direction of supervixing Engineer) |
| 48 | Providing and Fixing LT Clamp For PCC/STP Pole (as per Direction of supervixing Engineer) |
| 49 | Providing and Fixing of ABC Suspension Clamp (as per Direction of supervixing Engineer) |
| 50 | Providing and Fixing of ABC Dead & Clamp (as per Direction of supervixing Engineer) |
| 51 | Providing and Fixing of ABC Huck for PCC Pole (as per Direction of supervixing Engineer) |
| 52 | Providing and Fixing of ABC Peircing Clamp (as per Direction of supervixing Engineer) |
| 53 | Providing and Fixing of LT Sackle Insulator (as per Direction of supervixing Engineer) |
| 54 | Providing and Fixing of G.I. Pipe 6 Fitt ( as per Direction of supervixing Engineer) |
| 55 | Provding and Fixing of HDPE Pipe 6\" inch ( as per Direction of supervixing Engineer) |
| 56 | MS iron Scrap small material (such as clamp, channel, angle, cross arms, nut bolts etc.) (as per Direction of supervixing Engineer) |
| 57 | Recived back STP Pole 11 Mtr long Scrap(35Nos.) from site to store. (as per Direction of supervixing Engineer) Please Enable Macros to View BoQ information |