| 1 | Dewatering By10.00hp deisel oprated pump set including PLO & Pump Oprator complete in all S.I, 109 Chapter 20 |
| 2 | Cleaning Jungle including uprooting of rank vegetation grass, bush, wood trees and saplings of girth upto 30 cm measured at a height of 1 metre above ground level & removal of rubbish upto a distance of 50 metres outside the periphery of area cleared. |
| 3 | cleanning of existing deain sludge garbage etc in foul position complete in all 150+25% Sluge |
| 4 | Disposal of excavated sludge upto 10.00Km distance including loading and unloading complete in all |
| 5 | Excavation in foundation in ordinary soil (loam clay, or sand) including lift upto 1.5 metre and lead upto 30 m & including filling, watering and ramming of excavated earth into the trenches or into the space bwtween the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth as directed by the Engineer in charge of 30 m from the foundation trenches. SI No 251 |
| 6 | Providing and laying base concrete 1:4:8 Cement c/sand and 40mm gauge ston ballast including supply of all material labour T&P etc all complete S.I. 281 |
| 7 | R.C.C. work for coulaman fottings 1:2:4 cement C/ sand and app stone grit including centering shuttering Excluding rein forcemeant supply of all material labour T&P all complete s. I . 283 |
| 8 | R.C.C. work for Column, plinth beams and Tea beams 1:2:4 cement C/ sand and app stone grit including centering shuttering Excluding rein forcemeant supply of all material labour T&P all complete s. I . 283,285&288 |
| 9 | R.C.C. work with cement approved coarse sand and 2 cm. guage approved stone grit in the proportion of 1:1.5:3 in PLINTH /SLAB BEAM excluding its fixing and binding wire and including neccesary centaring and shuttering Including supply of all material, labour, T&P etc. Required for proper completion of the work |
| 10 | R.C.C. work for Waal & drain 1:2:4 cement C/ sand and app stone grit including centering shuttering Excluding rein forcemeant supply of all material labour T&P all complete s. I . 283 |
| 11 | First class brick work in 1:4 cement and C sand mortar in foundation plinth including supply of all materials, labour and T&P etc. required for proper completion of work. S I No 303NS |
| 12 | 12mm thick cement plaster in 1:4 cement and fine sand mortar in single coat on rough face including supply of all materials and labour etc complete in all SI No 13.4 |
| 13 | Cement concrete with 2 cm gauge approved stone ballast approved coarse sand cement in the proportion of 4:2:1 including supply of all material T&P etc. required for proper completion of work. S I No279(a) |
| 14 | M.S. or iron work of small sizes and section such as holding down bolts, hold fast, tieods grading etc. wrought to required from including supply to steel bolt, nuts wastage etc and their fixing required for proper completion of the work. S I No 502 |
| 15 | Mild Steel or iron in plain work such as reinforced concrete or reinforcement brick work (when not included in an over all rates) wrought to required shape as necessary including benefit for proper completion fo the work and including supply of all steel and wastage and over lappign and hooks. S I No.504 |
| 16 | Providing and laying spreading and Compacting to jhansi hard stone Bllast 22.50-53mm Size To WBMspacifcation including spreding in uniform thickness hand Packiung and Manual Compaction by Ramer to proper Blinding with local sand to fill up theinterstces of Ramming and compactkng to the required densityt |
| 17 | Providing and laying 80mm thick ISI Raber mold precat & interlocking cement Concrete pre pavers manufactures By automatic electro Operated pavers strength 400kg/cm2 making machine of appropriate size and shape over 60 mm thick average compacted c/sand joint of 3mm thick filled by fine sand including leveling temping and sweeping etc. all complete |
| 18 | Earth work in embankment in ordinary Soil including lift 1.50m lead 30mwith cartage of earth from 6km to site including loading unloading etc all complete mechanically . 253+231(a) Please Enable Macros to View BoQ information |