| 1 | Dismentaling brick work or stone work in lime or cement mortar and including stacking materials as directed by Engineer in harge with in a distance of 60 meters ( 200 feet). PWD-692 |
| 2 | Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material. |
| 3 | Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications. PCC Grade M15 |
| 4 | Brick Masonry Work in Cement Mortar 1:3 in Foundation complete excluding Pointing and Plastering, as per Drawing and Technical Specifications. |
| 5 | Furnishing and Placing Reinforced/ Prestressed cement concrete in super-structure as per drawing and Technical Specification RCC Grade M30 |
| 6 | Providing weep holes in Brick masonry/Plain/ Reinforced concrete abutment, wing wall/ return wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :20H towards drawing foce. Complete as per drawing and Technical Specifications |
| 7 | Supplying, fitting and placing HYSD bar reinforcement in super-structure complete as per drawing and technical specifications |
| 8 | Providing and laying boulder apron for bed protection with stone boulders of minimum size and weight as per Table No 1300.1, No gragment weighing not less than 25 kg, laid dry complete as per drawing and technical specification clause 1301.Pitching |
| 9 | Sand Filling complete as per Drawing and Technical Specifications. |
| 10 | Brick soling with straight overburnt brick laid on edge and dry including preparation of subgrade to prescribed camber and including supply of bricks, filling joints, with local earth spreading blinding coats 1cm. (3/8\") deep of local earth of P.L 5 to 7 or sand over the entire surface & including labour and T&P etc. required for proper completion of work. PWD-762b |
| 11 | Construction of embankment with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacting to meet requirement of table 300-2. [lead upto 2000m] [MORT&H] |
| 12 | Construction of granular sub-base by providing close graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with front end loader at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401 |
| 13 | Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with grader in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density. |
| 14 | Providing and applying primer coat with SS-2 grade bitumen emulsion on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.70 to 1.00 kg/sqm using mechanical means as per clause 502 [MORT&H]. |
| 15 | Providing and laying dense graded bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder @ 4.0 per cent by weight of total mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification clause No. 505 complete in all respects. (Grade-I) |
| 16 | Providing and applying tack coat with bitumen VG_10 using Bitumen pressure distributor at the rate of 0.20 kg per sqm on the prepared bituminous surface cleaned with mechanical broom. |
| 17 | Providing and laying bituminous concrete with higher capacity batch type hot mix plant using crushed aggregates of specified grading, premixed with bituminous binder @ 5.4 per cent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 507 complete in all respects Grade-II |
| 18 | Construction of sub-grade and earthen shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2 [lead upto 2000m] [MORT&H] Please Enable Macros to View BoQ information |