| 1 | Carriage of following Centralized Materials from Store Center Kunera Etawah to site of work through the Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work. |
| 2 | PCC Pole 8.5 Mtr. |
| 3 | STP 11 Mtr. |
| 4 | ACSR Dog Conductor |
| 5 | ACSR Weasel Conductor |
| 6 | LT ABC 3.5x70 Sqmm |
| 7 | PVC Cable 3.5x70 Sqmm |
| 8 | 11 Kv Cable XLPE 3x70 Sqmm |
| 9 | 11 Kv Cable XLPE 3x120 Sqmm |
| 10 | 25 KVA New Distribution Transformer |
| 11 | 63 KVA New Distribution Transformer |
| 12 | 100 KVA New Distribution Transformer |
| 13 | 11 Kv CT/ PT Pole Unit Sutaible Size |
| 14 | 11 KV CT/PT Cubical Meter Sutaible Size |
| 15 | Earthing Complete |
| 16 | Stay Set Complete |
| 17 | 11 Kv Disc Insulator with Fitting |
| 18 | 11 Kv Pin Insulator with Pin |
| 19 | 11 Kv 3x70 Sqmm Heat Shrinkable Cable Jointing Kit (Indoor/Outdoor Type) |
| 20 | 11 Kv 3x120 Sqmm Heat Shrinkable Cable Jointing Kit (Indoor/Outdoor Type) |
| 21 | Erection & fabrication of following supports including fitting of all required accessories required for proper completion of work as per RESSPO Schedule. It including the cost of all labour, T&P etc. |
| 22 | Erection of Single support by ST/PCC pole including fixing complete HT/LT fittings as per RESSPO Munual including the cost of labour, T&P and carrier etc. required for proper completion of work. |
| 23 | Grouting of Single support ST/PCC pole as per RESSPO Manual including of the cost of labour, T&P and carrier etc. required for proper completion of work. The support shall be grouted with cement, sand & brick ballast. including the cost of arrangement of cement, sand, brick ballast etc. |
| 24 | Erection & Grouting of Double pole including fixing complete HT/LT fitting as per RESSPO Manual including the cost of labour, T&P and carrier etc. required for proper completion of work. The support shall be grouted with cement, sand & brick ballast. including the cost of arrangement of cement, sand, brick ballast etc. |
| 25 | Laying, sagging, stringing, binding & jumpering of ACSR Weasel Conductor on the newly erected pole as per RESPO manual and as per direction of supervising engineer, including the cost of arrangement of labour, T&P carrier etc. required for proper completion of work. |
| 26 | Laying, sagging, stringing, binding & jumpering of ACSR Dog Conductor on the newly erected pole as per RESPO manual and as per direction of supervising engineer, including the cost of arrangement of labour, T&P carrier etc. required for proper completion of work. |
| 27 | Laying, sagging, stringing, binding & jumpering of 3.5x70 Sqmm LT ABC Cable on the newly erected pole as per RESPO manual and as per direction of supervising engineer, including the cost of arrangement of labour, T&P carrier etc. required for proper completion of work. |
| 28 | Laying, sagging, stringing, binding & jumpering of 3.5x70 Sqmm PVC Cable on the newly erected pole as per RESPO manual and as per direction of supervising engineer, including the cost of arrangement of labour, T&P carrier etc. required for proper completion of work. |
| 29 | Erection and grouting of stay set including the work of nozzling etc. as per RESSPO manual and also including the cost of arrangement of all grouting material, labour, T&P etc. required for proper completion of work. |
| 30 | Fixing & connecting of Earthing Rods as per RESSPO Manual including the cost of labour, T&P etc. required for proper completion of work. |
| 31 | Mounting of 25 KVA Transformer on the Single Pole/Double pole/Plinth structures and connections thereof. |
| 32 | Mounting of 63 KVA Transformer on the Single Pole/Double pole/Plinth structures and connections thereof. |
| 33 | Mounting of 100 KVA Transformer on the Single Pole/Double pole/Plinth structures and connections thereof. |
| 34 | Digging, laying and back filling of 3x70 Sqmm XLPE cable including the cost of Cable hoisting and making loops/ HDPE/GI pipe/clamps as per RESPO manual and as per direction of supervising engineer including the cost of arrangement of brick, sand, labour and T&P etc. required for proper completion of the work. |
| 35 | Digging, laying and back filling of 3x120 Sqmm XLPE cable including the cost of Cable hoisting and making loops/ HDPE/GI pipe/clamps as per RESPO manual and as per direction of supervising engineer including the cost of arrangement of brick, sand, labour and T&P etc. required for proper completion of the work. |
| 36 | Filling Of 11 Kv 3x70 Sqmm Heat Shrinkable Cable Jointing Kit (Indoor/Outdoor Type). (including the cost arrangement of labour, T&P, carrier etc. required for proper completion of work) |
| 37 | Filling Of 11 Kv 3x120 Sqmm Heat Shrinkable Cable Jointing Kit (Indoor/Outdoor Type). (including the cost arrangement of labour, T&P, carrier etc. required for proper completion of work) |
| 38 | Safe carriage of CT/ PT Pole Unit and its proper installation on double poole after fixing of channel with M.S. clamps and nuts & bolts for holding the channel angle etc. The unit body shall be earthed by connecting M.S. Strip of sutaible size finally connected to earthing rod. 11 KV line shall be connected to unit as per instructions of SDO / AE(M). The M.S. Strip & earth rod shall be included in the scope of work. |
| 39 | Safe carriage of 11 KV CT/PT Cubical Meter sutaible size and its proper installation at pit site as per RESSPO Manuals |
| 40 | Construction of plinth for 100 KVA Transformer 2x2x1.5 M 4\" RCC Base Stractures with connections thereof as per Norms. |
| 41 | Chemical Pipe Earthing Body & Neutral Of Transformer and connections as per Norms. |
| 42 | Fencing work of 100 KVA Transformer |
| 43 | Carrage & Fixing of Cross Arm Holding Clamp |
| 44 | Carrage & Fixing of V-type Cross Arm |
| 45 | Carrage & Fixing of Stay Clamp |
| 46 | Carrage & Fixing of Fuse Set |
| 47 | Carrage & Fixing of F Clamp |
| 48 | Carrage & Fixing of DP Clamp |
| 49 | Carrage & Fixing of Stay Wire |
| 50 | Carrage & Fixing of GI Wire |
| 51 | Supply, Installation & Fixing of following De-Centralized Materials/accessories. including the cost of labour, T&P and carrier etc. required for proper completion of work. |
| 52 | T-Off Channel |
| 53 | PG Clamp |
| 54 | Top Channel |
| 55 | Dropper Channel |
| 56 | T/F Base Angle |
| 57 | GI Pipe |
| 58 | LT Clamp |
| 59 | Nut Bolt |
| 60 | Guarding Angle |
| 61 | Carriage of scrap material damaged pole, conducotr\"s Etc. from Pit Site to J.E Store Kunera Etawah including the cost of arrangement of labour, T&P, carrier etc. Please Enable Macros to View BoQ information |