| 1 | Section-1: ENGINEERING |
| 2 | Development of CNG Stations- |
| 3 | Preparation of Report on usage of Land / site- Carrying out site visit/s , preparation of report along with required drawing / Plan/Layout for usage of land for DRS / CNG / MRS/LNG, Stoarge space , Decompression unit etc as per the requirement of the project. |
| 4 | Preparation of GAD (General Arrangement Drawing) for CNG Station layout |
| 5 | Preparation of GAD General arrangement Drawing for DRS/MRSlayout |
| 6 | Engineering of Online MotherStation (Greenfield) / On line stations including office building (quantity to be checked) |
| 7 | Engineering of CNG Station on RO / DODO/DBS |
| 8 | Engineering of conversion of DBS to On line CNGstation |
| 9 | Engineering of Decompression Unit |
| 10 | CCOE Layout, Study of Drawings for Facilities for COCO / RO / DODOs / DBS |
| 11 | Engineering for CGS |
| 12 | Development of Steel Pipeline network |
| 13 | Design & Engineering for development of Steel Pipeline network for CGD including Underground pipeline, above ground piping, SV Stations, CP systems, branch / spur pipeline connections to DRS/ MRS/ CNG stations / Consumer terminals includingInstrumentation / electrical / Civil works for completion of the Steel pipeline network in all respect |
| 14 | Development of MDPE & GI Pipeline network |
| 15 | Design & engineering for Development of MDPE network for supplying Gas to Households, Commercial consumers, Industrial consumers etc including Sizing Interconnection among DRS, MRS, compliance of PNGRB regulations and relevent stds. |
| 16 | GI Pipeline network for House hold / Apartments / commercial connections |
| 17 | Common services -Supply Packages |
| 18 | Preparation of Technical specifications & Bid document, Floating of tender /Tender for multiple items and/ for multiple cities Evaluation of Bids, Recommendation for Placement of orders, subsequent release order, dispatch clearnce etc - For Supply package (Tendering would be carried out jointly for both GAs i.e. GA-2 & GA-3) |
| 19 | Closure of supply contract/report including submission of vendor evaluation, Completion certificate / execution certificate, feed back etc |
| 20 | Common services - Works/ServicePackages |
| 21 | Preparation of Technical specifications & Bid document, Floating of tender/Tender for multiple scope and/ for multiple cities/ Locations Evaluation of Bids, Recommendation for Placement of orders, release of subsequent orders etc - For Composite / Construction / works / Service package (Tendering would be carried out jointly for both GAs i.e. GA-2 & GA-3) |
| 22 | Closure of contract/report including submission ofvendor evaluation, Completion certificate/ execution certificate, feed back, etc |
| 23 | Section-2: SITE ACTIVITY |
| 24 | Store Management : |
| 25 | At each GA/City /Location |
| 26 | Preparation of SIV/GRV / MIV/MRN, Management of stores such as receiving & issuing ofthe materials, Managing the stocks, Preservation of materials, Physical verification as per Owner\"s policy, Materialreconcialation statement, Assistance in Lodging of claims as per Owner\"\"s policy |
| 27 | Construction Supervision at site |
| 28 | Deployment of RCM (before start of construction till submission of closure recomendation), at each GA (having the qualification of BE/ BE Tech with 10 years of experience in construction) to look after the progress with over all responsibility of acheieving the targtes,incluiding, Plannig, availability of material, store managemnet, work Scheduling, WO - Closure recommnedation, Billing, recommnedation, Appl, Budgeting/ Cash flow requiremnet, Capitalisation, Liabilities on qtr basis etc. |
| 29 | Carrying out the Site supervision of the work being executed at site for Steel / MDPE/ GI / CNG / De-compression facility etc for CGD project at each GA. |
| 30 | Boarding & Lodging facility including the office stationary. Computer and peripherials, office furniture etc. (Per guest house per month) |
| 31 | Deployment of Vehicle for RCM at each GA (Per vehicle per month, to be paid as per actual deployment). |
| 32 | Deployment of Vehicle for construction and site supervisionat each GA (Per vehicle per month, to be paid as per actual deployment). |
| 33 | Any activity requiring visit to carry out inspection, testing, at vendor/manufacturer locations/ FAT. Issuaance of IC, Dispatch clearance on behalf of PBGPL. (This includes the local transport at place of posting and at visiting places, and other incidental expences.NOTE: Rate must include to and fro journey fare and accomodation charges at places(s) of visit(s) |