| 1 | Earth work in excavatin in foundation in odinary soil i/clift up to 1.5 mt and lead up to 50 mt and i/c filling, watering and ramming of excavated earth into the trenches or into the spece between thebuilding and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth etc all complete work. as per S.I. No. 251 |
| 2 | Earth work in embankment in ordinary soil incuding useual lead lift and compected to desired density etc all complete work i/c cartage up to 3 K.M. as per S.I. No. 253 |
| 3 | Laying of Coarse sand in Blanket coat I/C Supply of all materials labour T&P |
| 4 | Concrete with 4 cm gaugestone ballast , Coarse sand of 1.25 F M and cement in propotion of 12:6:1 in foundation under floors, including supply of all meterials, labour and T&p etc. required for proper completion of work. As per S.I. No. 273 |
| 5 | Cement concrete with 2 cm guage approved stone ballast, approved coarse sand, cement in the proportion 1:1.5:3 including supply of all materials, labour and tools and plants etc. required for proper completion of work. As per S.I. No. 279 (b) |
| 6 | 1st class brick M-I50 in 1:4 cement & fine sand FM 1.25 mortar in foundation and plinth I/C cost of materials, labour and T&P required for proper completion of work as per S.I. No. 305. |
| 7 | Making construction joint with maxphalt sectboard including all material, labour and T&P etc. |
| 8 | Supplying and laying of 125 micron polythenincluding all material, labour and T&P etc. as per Material Rate Ch-1 S.No. 42 |
| 9 | Supplying and Mixng of admixture in Top Coat 1;1/2;3 including all material, labour and T&P etc. |
| 10 | 12 mm thick plaster with cement and fine sand FM 1.25 in 1:4 over brick work minimum thickness not to be less than 10 mm thick including all cost of material, labour allround. as per S.I. No. 584 |
| 11 | Cement concrete with 2 cm guage approved stone ballast, approved coarse sand, cement in the proportion 4:2:1 including supply of all materials, labour and tools and plants etc. required for proper completion of work. As per S.I. No. 279 (a) |
| 12 | R.C.C work with cement approved coares sand and 20 mm gauge apprved stone ballast in slab excluding supply of reinforcement and its bending but including its fixing and bending the same with 24BWGGI. binding wire and including nesessary centering and shuttering etc and also including supply of all material, labour and T&P etc, required for proper completion of work. Bending wire cost being included in the item. as per S.I. No. 283 |
| 13 | Mild steel or iron in plain work such as reinfoced concrete or reinforce brick work (when not included in an over all rates) wrougrt to required shap as necessasy including benefit for proper completion to the work and including supply of steel and wastage and over lapping and hooks. as per S.I. No. 504 |
| 14 | Supply of sign board./ Graynite Stone with Piller including all material, labour and T&P etc. Please Enable Macros to View BoQ information |