| 1 | EARTHWORK IN EXCAVATION BYMANUAL MEANS INFOUNDATIONS OF EQUIPMENTS, TANKS, FOOTINGS, COLUMNS, PLINTH BEAMS, WALLSFOUNDATIONSISOLATED PITS, PAVEMENTS, TRENCHES FORPIPELINES / CABLES, DRAINS ETC., TO THE REQUIRED LEVELS AND GRADES IN BOTH DRY AND WET CONDITIONS, RAMMING OF BOTTOMS, GETTING OUT INCLUDING DRESSING OF SIDES ANDEXCAVATED EARTH WITH LIFT UP TO 1.5 M INCLUDING STACKING, LEVELING ANDDRESSING ETC., COMPLETE AS PERDIRECTION OF ENGINEER-IN-CHARGE IN ALL TYPES OF SOILS, SUCH AS EARTH, MARINE CLAY, MARSHY LAND, RUNNING SAND, GARBAGE, SLUSH ETC. INCLUDING PROVIDING TEMPORARYSUPPORTS TO ALL SERVICE LINES SUCH ASOVERHEAD AND UNDERGROUND WATERSEWAGE AND DRAIN PIPES, CABLES ETCAND SHORING AND STRUTTING WHEREVERNECESSARY, COMPLETE IN ALL RESPECTS AS PER DIRECTION OF ENGINEER- IN - CHARGE. THE RATE INCLUDES PUMPING OUT WATER, BACKFILLING, REMOVING THE VEGETATION AND REFILLING / DISPOSAL OF EXCAVATED MATERIALS WITH IN A LEAD OF 03KM AS DIRECTED INCLUDING LEVELING, RAMMING ETC COMPLETE AS DIRECTED. |
| 2 | PROVIDING & LAYING 15-23 CM THICK DRY STONE RUBBLE SOLINGHARD STONE SET IN REGULAR LINES, HANDPACKED AND INTERSTICES THOROUGHLY FILLED WITH SMALL CHIPS INCLUDING FILLING IN WITH GOOD QUALITY MURUM BROUGHT FROM RCF PREMISES, COMPACTING WITH IRON RAMMERS, WATERING, METAL-1 WITH GRITSPREADING 12MM THK. LAYERON TOP ETC COMPLETE AS DIRECTED BY ENGINEER IN CHARGE.COMPLETE AS DIRECTED. |
| 3 | PROVIDING AND LAYING CAST IN SITU/READY MIXCEMENT CONCRETE IN M15 OF TRAP/ GRANITE/QUARTZITE/GNEISS METAL FOR FOUNDATION AND BEDDING / STEPS INCLUDING STEEL CENTERING, FORMWORK, LAYING/PUMPING, COMPACTING,ROUGHENINGTHEMIFSPECIALFINISHISTOBEPROVIDED,FINISHINGUNEVENAND HONEYCOMBED SURFACE AND CURING ETC. COMPLETE. THE CEMENT MORTAR 1:3 PLASTER IS CONSIDERED FOR RENDERING UNEVEN AND HONEYCOMBED SURFACE, ONLY. NEWLY LAID CONCRETE SHALL BE COVERED BYGUNNYBAG,PLASTIC,TARPAULINETC. |
| 4 | PROVIDINGANDLAYINGCASTINSITU/READYMIXCEMENTCONCRETEM-30OFTRAP/GRANITE/QUARTZITE/GNEISSMETALFORR.C.C.WORKINFOUNDATIONSLIKE RAFT,STRIP FOUNDATIONS,GRILLAGE AND FOOTINGS OF R.C.C. COLUMNS AND STEEL STANCHIONS ETC. INCLUDING BAILING OUT WATER,STEEL CENTERING,FORMWORK,COVERBLOCKS,LAYING/PUMPING,COMPACTIONANDCURING ROUGHENING THE SURFACE IF SPECIAL FINISH IS TO BE PROVIDED APPLICATION OF ONE COAT OF BLACKBITUMENT PAINT TO CONCRETE SURFACE (EXCLUDING REINFORCEMENT AND STRUCTURAL STEEL) |
| 5 | PROVIDINGANDLAYINGCASTINSITU/READYMIXCEMENTCONCRETEINM-30OFTRAP/GRANITE/ QUARTZITE/GNEISSMETALFORR.C.C.COLUMN /PARDIOFREQUIREDTHICKNESSINCLUDINGSTEELCENTERING, FORMWORK, COVER BLOCKS, LAYING/PUMPING,COMPACTING AND ROUGHENING THEM IF SPECIAL FINISH ISTOBEPROVIDEDANDCURING INCLUDING APPLICATION OF ONE COAT OF BLACKBITUMENT PAINT TO CONCRETE SURFACEETC. COMPLETE..(EXCLUDINGREINFORCEMENTANDSTRUCTURALSTEEL). |
| 6 | PROVIDING AND FIXING IN POSITION TMT - FE - 500 BAR REINFORCEMENT TATA/SAIL/JSW OR EQUIVALENT MAKE OF VARIOUS DIAMETERS FOR R.C.C.PILECAPS,FOOTINGS,FOUNDATIONS,SLABS,BEAMSCOLUMNS,CANOPIES,STAIRCASE,NEWELS, CHAJJAS,LINTELSPARDIS,COPINGS,FINS,ARCHESETC.ASPERDETAILEDDESIGNS,DRAWINGSAND SCHEDULES. INCLUDING CUTTING, BENDING, HOOKING THE BARS, BINDING WITH WIRES OR TACK WELDING AND SUPPORTING AS REQUIRED COMPLETE. (SAIL,TATA, JSW JINDAL OR EQUAVALENT BRANDS ONLY). |
| 7 | SUPPLYING AND FILLING IN FOUNDATION, TRENCHES, PLINTH, UNDER PAVEMENT FLOORS AND SIDES OF FOUNDATION WITH COARSE SAND OF APPROVED QUALITY AT ALL DEPTHS IN LAYERS NOT EXCEEDING 15CMSIN THICKNESS INCLUDING CONSOLIDATION AND DRESSING LAYER BY RAMMING AND WATERING ETCAS DIRECTED BY EIC ETC. COMPLETE. |
| 8 | PROVIDING SECONDCLASSBURNTBRICKMASONRYWITHCONVENTIONAL/I.S.TYPEBRICKSINCEMENT MORTAR 1:6 IN FOUNDATIONS AND PLINTH OF INNER WALLS/ IN PLINTH EXTERNAL WALLS INCLUDING BAILING OUT WATER MANUALLY , STRIKING JOINTS ON UNEXPOSEDFACES, RAKING OUT JOINTS ON EXPOSEDFACES AND WATERING ETC. COMPLETE. |
| 9 | PROVIDING INTERNAL CEMENT PLASTER 12 MM THICK IN A SINGLE COAT USING READY TO USE WALL PLASTER TO CONCRETE OR BRICK SURFACE IN ALL POSITIONS INCLUDING SCAFFOLDING AND CURING COMPLETE. PROVIDING GROOVE AT JOINT OF B.B. MASONRY AND CONCRETE MEMBERS COMPLETE.A) CEMENT RATIO 1:5 (1 CEMENT : 5 GRADED PACKED GRADED SAND) |
| 10 | PROVIDINGAND APPLYINGTWOCOATSOF EXTERIORACRYLICEMULSION PAINTCONFIRMINGTO CORRESPONDING I.S. OF APPROVED MANUFACTURE AND OF APPROVED COLOUR TO THE PLASTERED SURFACES INCLUDINGCLEANING,PREPARINGTHEPLASTERSURFACE,APPLYINGPRIMERCOAT,SCAFFOLDINGIF NECESSARY , AND WATERING THE SURFACE FOR TWO DAYS ETC COMPLETE. |
| 11 | PROVIDING AND LAYING GP-2 (FOSROC) OR ANY OTHER APPROVED EQUIVALENT ANTI SHRINKAGE GROUTING IN POCKETS/SLEEVES, UNDER BASE PLATES OF STRUCTURAL COLUMN AS SPECIFIED IN THE DRAWING, DYNAMIC MACHINES SUCH AS SMALL PUMPS AND COMPRESSORS AS PER MANUFACTURER\"S SPECIFICATIONS, COMPLETE IN ALL RESPECTS ETC AND AS PER THE DIRECTION OF SITE-IN-CHARGE. (THE PRODUCT LIKE ULTRATECH/RENDROC (RGL) OF FOSROC OR ITS EQUIVALENT) |
| 12 | PROVIDING & MAKING ARRANGEMENTS FOR POCKETS IN R.C.C. WHILE CASTING TO RECEIVE / INSTALL FOUNDATION BOLTS OF REQUIRED DIAMENSIONS AND DEPTH AS PER THE DRAWINGETC. COMPLETEAND AS PER THE DIRECTION OF SITE-IN-CHARGE. |
| 13 | SUPPLYING, FABRICATING AND FIXING INPOSITION M.S. HOLDING DOWN BOLTSASSEMBLY CONSISTING OF BOLTS, HEADSNUTS, WASHERS ETC., AND THE LIKEINCLUDING EMBEDDING IN CEMENTCONCRETE / R.C.C WORKS AS PERAPPROVED DRAWINGS COMPLETE IN ALLRESPECTS INCLUDING ONE COAT OFPRIMER. (ALL MATERIALS SUPPLY ARE INCONTRACTOR\"S SCOPE). |
| 14 | DISMANTLINGBRICKMASONRYINLIMEORCEMENTMORTARANDSTACKINGTHEMATERILSASDIRECTED WITH ALL LEADS, LIFTS ETC. |
| 15 | DISMANTLINGSTONEMASONRYINLIMEORCEMENTMORTARINCLUDINGSTACKINGTHEMATERILSAS DIRECTED WITH ALL LEADS, LIFTS ETC. |
| 16 | REMOVINGLIMEORLEANCEMENTCONCRETEINCLUDINGSTACKINGTHESPOILSASDIRECTEDWITHALL LEADS, LIFTS ETC, COMPLETE. |
| 17 | DISMANTLING THE R.C.C. WORK 1:2:4 AND SORTING OUT THE MATERIALS SUCH AS STEEL ETC. AS DIRECTED AND STACKING THEM WITHIN THE SPECIFIED LEAD AS DIRECTED ETC. COMPLETE. |
| 18 | PROVIDINGFIXING VARIOUS TYPES OF MATERIALS & OTHER FITINGS / ACCESSORIES, ETC. INCLUDING THE CHARGES SUCH AS TRANSPORTATION, HANDLING, STORAGE AND OVERHEADS, PROFITS, ETC. COMPLETE. AS DIRECTED BY ENGINEER-IN-CHARGE AS PER REQUIREMENT OF JOB NOT INCLUDED IN ABOVE ITEMS. PAYMENT SHALL BE MADE ON THE BASIS OF ACTUAL COST OF MATERIAL PER CASH MEMO/RECEIPTS. |
| 19 | DESIGN OFR.C.C. FOUNDATIONS AND ALLIED WORK FOR ERECTION OF SERVICE WATER TANK AND PUMPS ANDIN CONUSLTATION WITH RCF AS PER MODIFICATIONS SUGGESTED, EXISTING SITE/SOIL CONDITIONS ALONG WITH PREPARATION OFPROPOSEDDRAWINGS, SUBMISSION OF DETAILED DESIGN AND RCC/FABRICATION DRAWINGS AND ISSUE OF STABILITY CERTFICATE AFTER COMPLETION OF WORK. |