| 1 | Stringing of 1.1 kV Aerial bunched cable of size 3 x 70 + 1 x 16+1x 50 sqmm with bare/insulated Messenger through existing poles |
| 2 | Erection of Anchor clamp /dead end clamp for LT ABC of any size |
| 3 | Erection of suspension clamp for LT ABC of any size |
| 4 | Installation of Insulation piercing connector for main to service line main :25-95 sqmm, Tap : 25-95 sqmm |
| 5 | Dismantling (without damage) one km LT Sph 2 wire OH line, cross arms, insulators and stacking the conductors in rolls. |
| 6 | Dismantling and reconnecting 3ph service connection from the OH line incl. lowering down the WP portion |
| 7 | Dismantling and reconnecting Sph service connection from the OH line incl. lowering down the WP portion. |
| 8 | Erecting one LT PSC Pole in position incl. digging & back filling pit. |
| 9 | Providing one Earth using earth pipe incl. digging separate pit at standard distance away from the pole/structure & backfilling |
| 10 | Providing one Driven Earth using GI earth pipe at standard distance away from the pole/structure in loose soil. |
| 11 | Providing Stay for LT poles incl. digging & back filling pit. |
| 12 | Providing Strut using LT PSC pole incl. digging & back filling pit. |
| 13 | Dismantling one ordinary street light/CFL/LED fitting from existing pole and refitting the same on newly erected pole and reconnecting. |
| 14 | Dismantling one damaged 11kV PSC/RCC pole after disconnecting stays, strut etc. and stacking the same. |
| 15 | Dismantling one damaged HT TW/RSJ/Rail Strut pole incl. removal of clamps and stacking. |
| 16 | Dismantling (without damage) one km 11kV line (3 conductors), cross arm, insulators, disc, rolling the conductor and stacking |
| 17 | RMU foundation suitable for CCT, CCCT types with Elevated Transformer plinth |
| 18 | Fitting and providing one Strut using HT PSC pole incl. digging & back filling pit. |
| 19 | Erection of LT 2 way distribution box on existing cross arm giving connection incl. cable and earth connection (excluding earthing). |
| 20 | Loading LT PSC pole from the stacking place and unloading the same at work site (transport by vehicle). |
| 21 | Transporting poles by hired vehicle to a distance upto 5km and carrying upto 4 poles excluding loading & unloading. |
| 22 | Dismantling of 1.1 kV Aerial bunched cable of size 3 x 70 + 1 x 16 (Street Light) + 1 x 50 Sq.mm. (Insulated Messenger) |
| 23 | Laying HT XLPE UG cable (of sizes beyond 3x185 sqmm and upto and incl. 3x300 sqmm) as per specification excl. excavation and backfilling. |
| 24 | Transporting LT ABC by hired vehicle to a distance up to 5 km and carring up to 2 drum including loading and un loading using crane |
| 25 | Loading HT A type pole from the stacking place and unloading the same at work site (transport by vehicle). |
| 26 | Excavation of cable trench in all classes of soil and backfilling after laying of cable (excluding laying of cable). |
| 27 | Fitting and erecting one HT A type Pole in position incl. fitting cross arm, digging & back filling pit, drawing earth leads. |
| 28 | Providing concrete muffing (0.45x0.45x1.5m) inclusive of cost of all material (as per specification). |
| 29 | Cost of construction of foundation, base plates, fixing anchor bots, loading & unloading, handling, erection, allignment and allied works for the installation of Data Aquisition compatible Extensible type Ring Main Units with terminal protector boots & extension modules, actuators for remote operatios, communicable FPIs, CTs, PTs & relay contacts for SCADA, giving power & control wiring and connections, providing terminal protector, interconnecting RMU bus bar and control cables, providing metered LT supply from nearest LT pole, providing 2 nos pipe earthing, cable mounting & terminations, giving connections after ascertaing proper phase sequence, providing location name & warning boards, burying cables & refilling, conducting all recommissioning tests as required, complete, except cost of conveyance. Additional rate for RMUs with one additional Load Break switch / VCB |
| 30 | Dismantling one damaged LT PSC/RCC pole after disconnecting stays, strut etc. and stacking the same |
| 31 | Cost of construction of foundation, base plates, fixing anchor bots, loading & unloading, handling, erection, allignment and allied works for the installation of Data Aquisition compatible Extensible type Ring Main Units with terminal protector boots & extension modules, actuators for remote operatios, communicable FPIs, CTs, PTs & relay contacts for SCADA, giving power & control wiring and connections, providing terminal protector, interconnecting RMU bus bar and control cables, providing metered LT supply from nearest LT pole, providing 2 nos pipe earthing, cable mounting & terminations, giving connections after ascertaing proper phase sequence, providing location name & warning boards, burying cables & refilling, conducting all precommissioning tests as required, complete, except cost of conveyance. RMUs with two nos load break switches & one VCB |
| 32 | Dismantling of suspension clamp suitable for LT AB cable |
| 33 | Dismantling of Anchor clamp / dead end clamp for LT AB cable |
| 34 | Dismantling one damaged LT TW/RSJ/Rail pole after disconnecting stays, strut etc. and stacking the same. |
| 35 | Cost for 50x25x5cm top RCC protection slabs(6mm MS rods 10cm c/c both ways ) using RCC 1:2:4 using 20mm broken stone in storage yard,etched with letter of size 5cm \"KSEB 11kV & DANGER |
| 36 | Dismantling (without damage) one 11kV PSC/RCC pole after disconnecting stays, strut etc. and stacking the same |
| 37 | Providing End Caps |
| 38 | Installing One No. 4 way Satellite Connector of size Main :16 to 95, Tap:4 to 35 Sq.mm to the LT AB cable of Standard size |
| 39 | Doing outdoor/indoor cable termination of 3x300 mm2 11KV XLPE cable very carefully observing directions of manufactures and departmental staff including crimping of socket (cost index(e) : 1 included in Rate) |
| 40 | Dismantling transformer station in DP structure excluding the rate of dismantling earthing |
| 41 | Erecting one 160kVA Transformer to existing Plinth/Platform and giving connections, incl. loading & unloading, excluding transportation. |
| 42 | Hire charges for mobile crane. |
| 43 | Dismantling (without damage) one km LT 3ph 4 wire OH line, cross arms, insulators and stacking the conductors in rolls. |
| 44 | Dismantling (without damage) one km LT additional conductor line, cross arms, insulators and stacking the conductors in rolls. |
| 45 | Doing straight joint on cables of sizes beyond 3x185 sqmm and upto and incl. 3x300 sq mm using the cable jointing kit supplied departmentally as per specification. |
| 46 | Mounting the cable ends of all sizes upto and incl. 3x300 sq mm with special type cable clamps incl. cost of extra materials if needed and giving necessary connections |
| 47 | Quoted Amount of BOQ1 in figures |
| 48 | GST Rate in percentage |