| 1 | Dismantling birick work or stone work in line or cement mortar and in including stacking or materials as directed by the Engineer- in- charge with in a distance of 60 meter (200 feet) item No. 692 SOR 2022 |
| 2 | Brick recoverd from Dismantling damage park baundry wall |
| 3 | Brick Bats recoverd from Dismantling damage park baundry wall |
| 4 | Earth filling including Cutting. of earth in odinary soil (loam, clay or sand) includy lift 1.5m and lead 50.m. The earth from cutting will be used in making embankment in 20cm layer with a lead of 8km. with ramming dressing the surface to requried level Slope all complete as pes direction of E/Iinculding earth cutting, Cost of earth 8km Cantage cost, louding, unloading. ete all Comp. (PWD SI No-253A+231a)/2022 |
| 5 | Earthwork: Excavation in trenches for foundations,pipes cables etc. in ordinary soil (Loam, Clay or Sand) including lift upto 1.5 m lead upto 50m and drassing of sides and ramming of bottom disposal of surplus excavated earth as directed by Engineer- in- charge with lead of 50 m . S.I. 2.6 DSR 2023 |
| 6 | Cement Concrete with 4cm. Guage brick ballast fine sand of 1:25 F:M and cement in proporation of 8:4:1 in foundation and under floors including supply of all meterials. labour T&P etc all complete. (SI.No-275/2022) |
| 7 | M-150 brick work in 1:4 cement and coarse sand mortar in foundation and plinth in Cement mortar 1:4 (1 cement: 4 coarse sand). including all materials, labour and T&P etc. required for proper completion of work. D.S.R. 2023, 6.1.1 |
| 8 | M-150 brick work in 1:4 cement and coarse sand mortar in super structure including necessary cutting and moulding of brick as required thickness of walls including all materials, labour and T&P etc. required for proper completion of work. D.S.R. 2023, 6.3 5684.24+1522/11= 7206.36 |
| 9 | M-150 brick work in 1:3 cement and coarse sand mortar in super structure including necessary cutting and moulding of brick as required thickness of walls nat to be less than 1/2 brick thick wall including all materials, labour and T&P etc. required for proper completion of work. D.S.R. 2023, 6.13.1 |
| 10 | Dimantling existing plaster including Disposal of refuse as directed by the Engineer in charge with in a distance of 60 meet (200 feet) SOR N0 706/2022 |
| 11 | 12 mm. thick plaster with 1 : 4 (one part cement & Four parts of coarse sand of 2.75 F.M.) over brick work minimum thickness not to be less than 1 cms. Including supply of all material , labour , T & P etc. required for proper completion of the work. 13.4.1.DSR 2023 |
| 12 | Finishing walls with Acrylic Smooth exterior paint of required shade :13.46.1 New work (Two or more coat applied @ 1.67 ltr/10 sqmover and including priming coat of exterior primer applied on previsully paint on old surface.@ 2.20 kg/10 sqm) DSR 13.46.1/2023 |
| 13 | Cement Concrete with 2cm, guage approved blaste ballast coarse sand and cement in proportion of 4:2:1 including supply of all materials, labour and T&P etc. required for proper completion of work. (S.I.No.279A)/2022 S.I. 4.1.4 DSR 2023 |
| 14 | Mild steel or iron work of small size and sections such as holding down bolts, hold fast, tle. roads, gratings etc (when not includied in an over all rates) wrought to reuired form including of supply of steel, bolts, nuts and wastage etc and fixing. required for proper completion of work. (S.I.No.502) |
| 15 | P/L in Cement Concrete 8:4:1 of not less than strength stone ballast (40mm normal size) :4 approved coarse sand:1 cement ) and curing complete including cost of form work supply of all material lab T&P etc all complete.(SI.No-4.1.8/DSR 2023 |
| 16 | Supply & fixing 80mm thick precast cement concrete 1-shape interlocking paver block a with top layer of minimum 8mm thickness having plan dimension 200x(160+120mm) of O.P. cement, shooth high gloss finish, skid reitant, manufacted from rubber moulds through vibro-copression machanism. The compressive strength of concrere paver block shalll not be less than 30MPA(M-30) And wight 5kg per no confirming to IS, 15658-2006 with a 4cm thick layer of fine sand including cost of material, labour, T&P TAXES etc. requried for proper comletion of the work as directed by Engineer in charge. Red colour (High Quality pigment/Lanxess, Bayer chamicals.UPPWD SOR 2022/ Additional No. 5 P-51 S.I. 16.91.2 DSR 2023 |
| 17 | Cement concrete flooring 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate) finished with a floating coat of neat cement, including cement slurry, but excluding the cost of nosing of steps etc. complete. 11.3.1 40 mm thick with 20 mm nominal size stone aggre. S.I. 4.1.4 DSR 2023 |
| 18 | Supply & fixing of RCC benchs Sofa type modledesign approved by E/I Complete in all respect.(Old approed Rate) |
| 19 | Providing and laying S & S centrifugally cast (Spun) iron pipes (Class LA) Conforming to. IS : 1536 200mm dia pipe 18.27.4 DSR 2023 |
| 20 | Providing lead caulked joints to spun iron or C.I. Pipes & specials including testing of joints but excluding the cost of pig lead. 200mm dia mtr. pipe 18.28.4 DSR 2023 |
| 21 | Providing and laying S & S C.I. standard specilas such as tees, bends, collars, tapers, caps etc. (Heavy Class) UP to 300mm dia. 18.25.1 DSR 2023 |
| 22 | HORTICULTURE WORK (B)Uprooting rank vegetation and weeds by digging the area to a depth of 60 cm, removing all weeds and other growth with roots by forking repeatedly, breaking clods, rough dressing, flooding with water, uprooting fresh growths after 10 to 15 days and then fine dressing for planting new grass, including disposal of all rubbish with all leads and lifts. (Item No-2.12 DSR-2020) (A.R) |
| 23 | Supply and stacking at site dump manure from approved source, including carriage upto 5km lead complete (manure measured in stacks will be reduced by 8% for payment) Screened through sieve of I.S designation 20 mm. (item No-2.4.1 DSR-2020) (A.R) |
| 24 | Spreeding of sludge, dump manure and/or good earth in required thickness as per direction of Officer-in-charge (cost of sludge, dump manure and/or good earth to be paid separately). Item No-2.8 DSR-2020 (A.R) |
| 25 | Mixing earth and sludge or manure in the required proportion specified or directed by the Officer-in-Charge. Item No-2.9 DSR-2020 (A.R) |
| 26 | Providing and laying Selection no-1 doob grass turf with earth 50mm to 60mm thickness of existing ground prepared with proper level and ramming with require tools wooden and then rolling the surface with light roller make the surface smoothen and light watering the same and maintenance for 30 days or more till the grass establish properly, as per direction of the Officer in charge. Item No-2.34 DSR-2020 (A.R) |
| 27 | Providing and stacking of Clerodendrum inerme having ht. 25cm to 30 cm multi branched in 20 cm size of Earthen Pot/Plastic Pot & as per direction of the Officer-in-Charge. (Item No-6.6 DSR-2020) A.R. |
| 28 | Providing and stacking of Hibiscus rosasinensis of height 45-60 cm. with 3-4 branches in earthen pots of size 20 cm as per direction of the officer-in-charge. (Item No-8.35 DSR-2020) |
| 29 | Providing and stacking of Tabernaemontana coronaria (chandni variegated) of height 45-60 cm. with 3-4 branches earthen pots of size 20 cm as per direction of the officer-in-charge. (Item No-8.61 DSR-2020) |
| 30 | Providing and stacking of Hamelia patens of height 60-75 cm. with 6-8 branches in poly bags of size 25 cm as per direction of the officer-in-charge (Item No.8.32 DSR-2020) |
| 31 | Providing and stacking of Tecoma gaudichaudi of height 90-105 cm.,bushy in big size HDPE bag as per direction of the officer-in-charge (Item No-8.69 DSR-2020) |
| 32 | Providing and stacking of Ficus panda of height 45-60 cm. with 6-7 branches and healthy foliage in bag of size 25 cm as per direction of the officer-in-charge. (Item No-8.26 DSR-2020) |
| 33 | Providing and stacking of Tabernaemontana coronaria (chandni variegated) of height 45-60 cm. with 3-4 branches earthen pots of size 20 cm as per direction of the officer-in-charge. (Item No-8.61 DSR-2020) |
| 34 | Planting of topiary plants(i) Digging holes in ordinary soil and refilling the same with the excavated earth mixed with manure or sludge in the ratio of 2:1 by volume (2 parts of stacked volume of earth after reduction by 20% 1 part of stacked volume of manure after reduction by 8%) flooding with water dressing including removal of rubbish and surplus earth if any with all leads and lifts cost of manure, sludge or extra good earth if needed paid separately): holes 45 cm dia and 45 cm deep (2.14.4 DSR 2016)(ii) Plantation of Tree shrubs, and hedge at site i/c 306 watering and removal of unserviceable material s as per direction of officer in charge (excluding cast of plant & water) 2.57.1 Trees Plant (2.57 DSR 2016)(iii) Using Antitarmite 20 gm per pit as a medicine for the plant.(iv) Vermicampost 0.5kg per pit as a Fertilizer for the growth of plant etc. all complete As per analysis attached |
| 35 | Plantation of Trees, Shrubs, and Hedge at site i/c watering and removal of unserveiceable material’s as per direction of officer in charge (excluding cast of plant & water) 2.57.3 Hedge Plant /Ground cover (item No- 2.57.3 DSR-2020) Please Enable Macros to View BoQ information |