| 1 | Reconductoring LT line |
| 2 | Dismantling (without damage) one km LT 3ph 4 wire OH line, crossarms, insulators and stacking the conductors in rolls. |
| 3 | Insertion of one HT A type pole in existing line incl. digging & backfilling pit, fitting cross arm, insulators, binding etc |
| 4 | Additional rate for excavation of Pit for A type pole in Hard Laterite. |
| 5 | Providing concrete muffing (0.45x0.45x1.5m) inclusive of cost of allmaterial (as per specification). |
| 6 | Additional rate for excavation of one Pit for HT Pole/HT Stay in Hard Laterite |
| 7 | Providing one Coil Earth using GI earth wire, digging separate pit at standard distance away from the pole/structure & backfilling. |
| 8 | Fitting and providing one HT Stay for 11kV pole incl. digging & back filling pit |
| 9 | Renewal of existing damaged/broken old 11kV Stay to the existing stay rod. |
| 10 | Dismantling (without damage) one km LT additional conductor line, cross arms, insulators and stacking the conductors in rolls. |
| 11 | Dismantling one LT 4 line cross arm from existing pole. |
| 12 | Transporting LT ABC by hired vehicle to a distance up to 5 km andcarring up to 2 drum including loading and un loading using crane |
| 13 | Erection of Anchor clamp / dead end clamp for LT ABC of any size |
| 14 | Erection of suspension clamp for LT ABC of any size |
| 15 | Stringing of 1.1 kV Aerial bunched cable of size 3 x 70 + 1 x 16+1x 50 sqmm with bare/insulated Messenger through existing poles |
| 16 | Installation of Insulation piercing connector for main to service line main:16-95 sqmm, Tap 16-95 sqmm |
| 17 | Installing One No. Insulation piercing connector of size Main :16 to 95 ,Tap:1.5 to 16 Sq.mm |
| 18 | Dismantling and reconnecting Sph service connection from the OH line incl. lowering down the WP portion. |
| 19 | Dismantling and reconnecting 3ph service connection from the OH line incl. lowering down the WP portion. |
| 20 | Providing End Caps |
| 21 | Providing Cable Tie |
| 22 | Reconductoring one km LT Sph 2 wire OH old line with new ACSRRabbit conductor incl. conveyance of materials. |
| 23 | Renewal of existing damaged/old LT TW/RSJ/Rail (Sph line) pole with new PSC pole in place and refitting of all items incl. conveyance (exceptpole). |
| 24 | Erecting one LT PSC Pole in position incl. digging & back filling pit. |
| 25 | Dismantling (without damage) one km LT Sph 2 wire OH line, crossarms, insulators and stacking the conductors in rolls. |
| 26 | Dismantling (without damage) one LT PSC/RCC pole after disconnectingstays, strut etc. and stacking the same. |
| 27 | Dismantling one LT 2 line cross arm from existing pole. |
| 28 | Providing Stay for LT poles incl. digging & back filling pit. |
| 29 | Renewal of existing damaged/broken old LT stay with existing stay rod |
| 30 | Fitting one No. Section fuse on LT line with dropping cables, crimping sockets, connecting with bolt&nut etc. |
| 31 | Cutting Channel/Cross Arm/Angle Iron into two pieces. |
| 32 | Drilling hole of various sizes on existing Channel/Cross Arm. |
| 33 | Insertion of one LT PSC pole in existing Sph OH line incl. digging &back filling pit, fitting cross arm, insulator, binding etc. |
| 34 | Providing Strut using LT PSC pole incl. digging & back filling pit. |
| 35 | Loading LT PSC pole from the stacking place and unloading the same atwork site (transport by vehicle). |
| 36 | Transporting poles by hired vehicle to a distance upto 5km and carryingupto 4 poles excluding loading & unloading. |
| 37 | Loading HT PSC pole from the stacking place and unloading the same atwork site (transport by vehicle) |
| 38 | Loading HT A type pole from the stacking place and unloading the sameat work site (transport by vehicle). Please Enable Macros to View BoQ information |