| 1 | Material and Labour for Scarifying or picking gravelled, macadam or bituminous macadam surfaces in area not exceeding 400 Sqm and depth exc 50mm and n.exc 100 mmand removing materials from site of workcomplete all as specified and as directed. |
| 2 | Material and labour for 150 mm thick Soling or sub base with broken boulders or quarried stones, interstics filled surfaces formedand rolled with power road roller of 8 to 12 ton capacity and consolidated to gradient and camber required complete all as specified and as directed. |
| 3 | Material and Labour for 75 mm thick [compacted thickness] Water Bound Macadam with coarse aggregate of Granite, Trap or Basalt of Grading 2 [63 to 40mm size] or of grading 3 (50 to 20mm size) spread, rolled with power road roller of 8 to 12 ton capacity and consolidated to gradient and camber required complete all as specified and as directed. |
| 4 | Material and labour for preparing WBM surfaces by brushing with wire brushes for removing caked mud etc. sweeping with brooms and finally fanning the cleaned surface with gunny bags to remove all loose dirt etc. and applying evenly a priming/ tack coat with bituminous primer @ 10 Kg per 10Sqm using paving bitumen grade VG-10 complete all as specified and as directed. |
| 5 | Material and labour for preparing Black top surfaces by brushing with wire brushes for removing caked mud etc. sweeping with brooms and finally fanning the cleaned surface with gunny bags to remove all loose dirt etc. and applying evenly a priming/ tack coat with bituminous primer @ 5 Kg per 10Sqm using paving bitumen grade VG-10 complete all as specified and as directed. |
| 6 | Material and labour for premix bituminous macadam (using paving bitumen VG-30)laid / rolled and compacted to required gradient and camber (consolidated thickness 75mm or less), rolled with 8 to 12 tonnevibratory power roller complete all as specified and as directed.Note :-Binder content, paving bitumen VG-30 shall not be less than @ 4.0% by weight of total mix. All materials are prepard by hot mix plant. |
| 7 | Material and labour for applying evenly a priming/tack coat with bituminous primer @ 2.5 Kg per 10Sqm using paving bitumen grade VG-10 over bituminous surfacescomplete all as specified and as directed. |
| 8 | Material and labour for laying Bituminous Premixed Semi Dense Asphaltic Concrete, 40 mm consolidated thickness, using paving bitumen of Grade VG – 30, with 5.5% of binder content by weight of total mix using Hot Mix Plant and Mechanical Paver finisher, rolled and compacted with power road roller of 8 to 12 ton capacity to required camber and gradient complete all as specified.Note: Minimum Bitumen content shall be 5.5% as specified here in above. Please note that if the actual quantity of bitumen to be incorporated on approval of Mix–Design is found more than the minimum bitumen content specified above, No price adjustment shall be made for actual bitumen content of Mix–Design. Bitumen shall be Paving Bitumen of Grade VG–30 and shall be procured by the contractor. Mix-Design shall be approved by GE. |
| 9 | Dismantling of old Bricks edging (laid flat or on edge) laid dry complete all as specified and as directed. |
| 10 | Material and labour for Continuous brick edging with burnt clay bricks With fly ash bricks of sub class \"B\" laid with width equal to the depth of the brick, laid dry on end at the required angle complete all as specified and as directed. |
| 11 | Material and labour for Road Marking Strips, Lines, Dashes, Arrows, Letters etc of 2.5 mm thick [Reflective Type] of approved colour conforming to BS 3262-1989 on roads, pavements and the like not exceeding 10cm wide with Hot Thermo Plast material by fully automatic thermoplastic paint applicator machine, fitted with profile shoe, glass beads dispenser, propane tank heaters and profile shoe heater, driven by skilled operator on road surface complete as per MoRT & H specifications including cleaning the road surface of all dirt, scales, oil grease and foreign materials etc complete all as specified and as directed. |
| 12 | Supply and fixingcat eye solar reflective type of metal body alloy of size 100mm x 100mm x 20mm with PAMA striplens reflector fixed with and incl MS stud of suitable size as per manufactures instructions and including taking down off old cat eye complete all as specified and as directed. |
| 13 | Supply and fix in repair of solar cat eye aluminum alloy shall (100%water proofing design according to 65) of size 125mm x 125mm x 25mm (shank 65mm) of high efficiency Mono rystafie solar panel 2.4V/0.3 watt one NI-ed rechargeable battery (1.2V/1600MA) consisting of super bright LED with 10,000 to 18,000 mcd completed as per manufactures instructions etc. all as specified and directed |
| 14 | Surface dressing in road side berms n.exc. 15cm depthin soft / loose soil, depthand removing rubbish upto a distance n.exc. 50 m all as specified and directed. |
| 15 | Material and labour for Moorum / Red Bajri filling under Floors or in Pavings laid in layers not exceeding 10 cm thick, spread levelled and rammed / rolled with power road roller of 8 to 12 ton capacity including watering to and consolidated to required level, gradient and camber required complete all as specified and as directed. Note:Measurements shall be taken after consolidation of earth and 10% deduction shall be made for payments. |