| 1 | Decentralized Material (Provided by Contractor) |
| 2 | 33 kv3x300mm² Cable jointing kit Outdoor |
| 3 | Cross arm clamp for PCC 9/STP 11mtr. |
| 4 | F-bracket for 33 KV |
| 5 | Number Plate with clamp and Nut & Bolt |
| 6 | Danger Board with clamp and Nut & Bolt |
| 7 | G I Barbed Wire |
| 8 | Nut Bolt and washer all sizes |
| 9 | ‘E’ Bracket for 33 KV |
| 10 | 33 kvTop Channel 125x65x6 mm, 3200 mm long with clamp |
| 11 | PG Clamp for Dog Conducter |
| 12 | 33 kvBracing angle 65x65x6 mm-2400 mm with 4 clamp |
| 13 | Dropper angle 100x50x2028 mm |
| 14 | Guarding Angle clamp for STP/PCC pole |
| 15 | GI Wire 4mm for guarding |
| 16 | Alluminium Paint |
| 17 | Red Oxide Paint |
| 18 | Guarding angle 65x65x6 mm – 3600mm |
| 19 | Stone pad |
| 20 | G.I. pipe 160mm (Internal dia) including cost of pipe union connecter for Railway Crossing (30x2=60mtr.) |
| 21 | 33KV \"V\" type X-Arm |
| 22 | CompleteStay ( GI stay rod 20X1800mm , stay wire 7/8 SWG 10 kg, stay clamp,bolt, nut& washer with concrete grouting) |
| 23 | MS Earthing Rod 20 x 2500 mm and 6 SWG earthing wire |
| 24 | Earth wire clamp with nut & bolts |
| 25 | ERECTION OF WORK(Shifting, Loading Carriage & Unloading of following materials from store centre‘Azamgarh’ to work site) |
| 26 | 33 KV ‘XLPE’ Cable 3x300mm² |
| 27 | ACSR Dog Conductor |
| 28 | PCC Pole 9 Mtr Long |
| 29 | 33kv Composite Polymer Disc Insulator 70 KN |
| 30 | 33kv Disc Fitting 70 KN |
| 31 | 33kv Composite Polymer Pin Insulater |
| 32 | Making plinth for ealreadyerected poles, grouting in the ratio 1:4:8 (cement, sand, 40mm brick ballast), back filling of earth, proper ramming & fitting of all accessories (‘V\" type cross arm 100 x 50 x 6 mm, clamps with bolts and nut, composite polymer pin insulators, danger board with clamp, barbed wire, earthing etc. complete in all respect, excluding erection work of 9 mtr single PCC pole& excavation of pit. |
| 33 | Erection work of 9 mtr single PCC pole& excavation of pit, making plinth for erected poles, grouting in the ratio 1:4:8 (cement, sand, 40mm brick ballast), back filling of earth, proper ramming & fitting of all accessories (‘V\" type cross arm 100 x 50 x 6 mm, clamps with bolts and nut, composite polymer pin insulators, danger board with clamp, barbed wire, earthing etc. complete in all respect. |
| 34 | Erection of Double pole structure on 9 Mtr PCC Pole including all works of excvation of pit, pole erection, making plinth for poles, grouting in the ratio 1:4:8 (cement, sand, 40 mm brick ballast), back filling of earth, proper ramming & fitting of all accessories (M.S. angle iron 65 x 65 x 6 mm bracing with clamps, top channel 125 x 65 x 3200 mm with clamps, danger board with clamp, barbed wire earthing, etc. complete). |
| 35 | Making plinth foralready erected double pole, grouting in the ratio 1:4:8 (cement, sand, 40 mm brick ballast), back filling of earth, proper ramming & fitting of all accessories (M.S. angle iron 65 x 65 x 6 mm bracing with clamps, top channel 125 x 65 x 3200 mm with clamps, danger board with clamp, barbed wire earthing, etc. complete in all respect excluding erection work of double pole structure of 9 mtr PCCPole&excvation of pit. |
| 36 | Making plinth foralready erected 11mtr. Single STP poles 30 cm above, grouting in the ratio 1:4:8 (cement, sand, 40mm brick ballast), back filling of earth, proper ramming & fitting of all accessories (clamps with bolt and nut, Aluminium paint, red oxide paint etc.) complete in all respect excluding erection work of single polestructure of 11mtr STP Poleexcvation of pit. |
| 37 | Making plinth for already erected 11mtr. STP double pole, grouting in the ratio 1:4:8 (cement, sand, 40 mm brick ballast), back filling of earth, proper ramming & fitting of all accessories (M.S. angle iron 65 x 65 x 6 mm bracing with clamps, top channel 125 x 65 x 3200 mm with clamps, danger board with clamp, barbed wire earthing, etc. complete in all respect excluding erection work of double pole structure of 11mtrSTPPole&excvation of pit. |
| 38 | Erection of Double pole structure on 9 mtr PCC Pole for One side O/H and One sideCable Rising including all works of excvation of pit, pole erection, making plinth for poles 30 cm above, grouting in the ratio 1:4:8 (cement, sand, 40 mm brick ballast), back filling of earth, proper ramming & fitting of all accessories (M.S. angle iron 65 x 65 x 6 mm bracing with clamps, top channel 125 x 65 x 3200 mm with clamps, danger board with clamp, barbed wire earthing, etc. complete) . |
| 39 | Erection of Four pole structure on 9 Mtr PCC Pole including all works of evocation of pit, pole erection, making plinth for poles, grouting in the ratio 1:4:8 (cement, sand, 40 mm brick ballast), back filling of earth, proper ramming & fitting of all accessories (M.S. angle iron 65 x 65 x 6 mm bracing with clamps, top channel 125 x 65 x 3200 mm with clamps, danger board with clamp, barbed wire earthing, etc. complete). |
| 40 | Grouting of stay rods (20 x 1800) mm including all work of excavation, cement concrete in size (0.60 x 0.60 x 0.30) m in ratio 1:4:8 cement, sand, 40mm brick ballast) as per drg including back filling, proper ramming etc. Fixing tightening &nozzling of stay wire with stay rod with the poles of required tension. |
| 41 | Guarding between two poles like single poles, double poles, four poles, etc. to guard LT, 11 KV Line telephone and river crossing, road crossing etc. with G.I. wire 4 mm, cutting, fabrication and fixing of guarding channel 65 x 65 x 6 mm - 3600 mm with clamps nut & bolts etc. |
| 42 | Laying of 33KV, 3x300Sq.mm, XLPE Cable with HDD (trenchless) method. |
| 43 | Charge of 33 kv 3x300 mm² cable jointing kit outdoor |
| 44 | Tree Cutting Compensation |
| 45 | Laying, spreading, lifting and final sagging of 3 phases of ACSR Dog conductor in accordance with profile and sag chart including binding, Jumpering and fixing of P.G. Clamp as per requirement in 03 Nos. conductor in parallel. Please Enable Macros to View BoQ information |