| 1 | Dismantling brick work or stone work in lime or cement mortar and including stacking of materials as directed by Engineer-in-charge within a distance of 60 meter (200 feet). (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 2 | Dismantling reinforced cement concrete or reinforced brick work including stacking of dismantled materials as directed by Engineer-in-charge within a distance of 60 meter (200 feet). (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 3 | Excavation for roadwork in soil with hydraulic excavator including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000m(Grabage) (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 4 | Construction of embankment with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacting to meet requirement of table 300-2. (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 5 | Construction of granular sub-base by providing close graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with front end loader at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401 (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 6 | Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with grader in sub-base/base course on well prepared surface and compacting with vibratory roller to achieve the desired density. (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 7 | Providing and applying primer coat with SS grade bitumen emulsion on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.70 kg/sqm using mechanical means. (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 8 | Providing and applying tack coat with bitumen VG-10 using bitumen pressure distributor at the rate of 0.25 kg per sqm on the prepared bituminous surface cleaned with mechanical broom. (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 9 | Providing and laying dense graded(GRDAE-1) bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder @ 4 per cent by weight of total mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification clause No. 505 complete in all respects. (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 10 | Providing and laying dense graded(GRDAE-2) bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder @ 4.5 per cent by weight of total mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification clause No. 505 complete in all respects. (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 11 | Providing and laying bituminous concrete with higher capacity hot mix plant using crushed aggregates of specified grading, premixed with bituminous binder @ 5.4 per cent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 507 complete in all respects (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 12 | Providing and applying tack coat with bitumen VG-10 using bitumen pressure distributor at the rate of 0.20 kg per sqm on the prepared bituminous surface cleaned with mechanical broom. (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 13 | Providing and laying bituminous concrete with higher capacity hot mix plant using crushed aggregates of specified grading, premixed with bituminous binder @ 5.4 per cent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 507 complete in all respects (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 14 | Construction of cement concrete kerb with top and bottom width 115 and 165 mm respectively, 250 mm high in M 20 grade on M-15 grade foundation 150 mm thick, foundation having 50 mm projection beyond kerb stone, kerb stone laid with kerb laying machine, foundation concrete laid manually, all complete as per clause 409 i/c all material labour, T&P, labour cess, all taxes etc (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 15 | Construction of median and island above road level with approved material brought from borrow pits, spread, sloped and compacted as per Clause 408 (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 16 | Providing plantation of center median of road i/c all material labour etc. comeplete as per direction of e/i(spacing@5 c/c) (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 17 | Providing and laying of hot applied thermoplastic compound 2.5 mm thick including reflectorising glass beads @ 250 gms per som area, thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC 35-2015 The finished surface to be level, uniform and free from streaks and holes. (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 18 | Retro Reflectorised Signs (Stainless steel Frame and Post with one side sings) Supply & fixing of reflective sign board (Single side) of size 1.50x1.20 m retro reflective sheeting of HIP grade type-IV, the board shall be fixed on 50mm SS 304 grade pipe and reflective sheet on 4 mm thick, ACM sheet of standard make as per MORTH specificaton. The Board shall be fixed using 2 man post 45x45x60 cm cement concrete foundation. The stainless steel joint welding of SS pipe work shall be band and grinder property including bufting so an to give uniform shining at weded joints. The Retro reflective sheeting shall be tested for a certificate of having the sheeting tested for coefficient of retro reflection, daytime colour and luminance, shrinkage, flexibility, liner removal, adhesion, impact resistance, specular gloss and fungus resistance, 3 years outdoor weathering and its having passed these tests shall be obtained from International/Government Laboratory/ Institute by the manufacturer of the sheeting and in case the certificate is obtained from international condition, it should also be obtained from Indian condition within 3 years of launching of product by the manufacture in abroad. Alternatively, a certificate conforming to ASTM Specification (D 4956-09) on artificial accelerated weathering requirements from a reputed laboratory in India can be accepted provisionally. In such a situation, the Employer / Client, if so desires, could seek for a performance guarantee which would be released after receipt of certificate meeting the requirement of three years outdoor weathering of the sheeting as per IRC 67:2012. Legends , letters , numerals and borders etc should be as per MoRTH specification No- 801.3.7 . Proof of the same in form of government report shall be uploaded while quoting tender as per SOR Ch. No. 26 Item No 25 (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 19 | Reinforced cement concrete M15grade Hectometer stone of standarddesign as per IRC:8, fixing in position including painting and printing etc (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 20 | Reinforced cement concrete M15grade kilometre stone of standard design as per IRC:8, fixing in position including painting and printing etc (Ordinary kilometer stone (precast) (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 21 | Providing and fixing of retro-reflectorised cautionary, mandatory and informatory sign as per IRC :67 upto date made of high intensity grade sheeting type-IV vide clause 801.3, fixed over aluminium sheeting 1.5 mm thick supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the ground by means of properly designed foundation with PCC M-25 grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm below ground level as per approved drawing. The Retro reflective sheeting shall be tested for a certificate of having the sheeting tested for coefficient of retro reflection, daytime colour and luminance, shrinkage, flexibility, liner removal, adhesion, impact resistance, specular gloss and fungus resistance, 3 years outdoor weathering and its having passed these tests shall be obtained from International/Government Laboratory/ Institute by the manufacturer of the sheeting and in case the certificate is obtained from international condition, it should also be obtained from Indian condition within 3 years of launching of product by the manufacture in abroad. Alternatively, a certificate conforming to ASTM Specification (D 4956- 09) on artificial accelerated weathering requirements from a reputed laboratory in India can be accepted provisionally. In such a situation, the Employer / Client, if so desires, could seek for a performance guarantee which would be released after receipt of certificate meeting the requirement of three years outdoor weathering of the sheeting as per IRC 67 upto date. Legends , letters , numerals and borders etc should be as per MoRTH specification No-801.3.7 . Proof of the same in form of government report shall be uploaded while quoting tender.As per SOR ch-26 SI no.-18 Cautionary Signs (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 22 | Supply & Erection of built up overhead structure 12.00 M to 15.00M span comprising of three vertical post of 6.00 M high made up of 350 mm N.B. havey class M.S. pipe as vertical member welded with 10mm M.S. plate at top & bottom for bearing of horizantal frame comprising of 65 mm . N.B. made havey class main pipe as of 42 mm class medium N.B. pipe bracing as per approved designed drawing with one coat of steel primer and two coats of synthetic enamle paint complate the work includes construction of RCC fundation of size 0.90x0.90M & 1.5 M deep for built up Overhead Structure including earth work in excavation , 100 mm thick Lean Concrete in 1:4:8 cement , course sand and 40 mm gauge stone balllast , RCC with 1:2:4 cement , Course sand and 20 mm stone grit including supply of grouting of 25 mm dia foundation bolts (600mm long) as per provision of structure including cost of reinforcement & shutting as per direction of Engineer in Charge . (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 23 | Providing and erecting direction and Hazard Marker (LEFT) indentification retro-reflectorised sign as per IRC-67 made of high inlensity grade sheeting vide clause 801.3 fixed over aluminium sheeting, 2mm thick with area not exceeding 0.9 sqm. Supported on a miled steel single angle iron post 75x75x6 mm firmly fixed to the ground by means of property designed foundation with M-15 grade cement concrete 45x45x60 cm. below ground level as per approved drawing, complete. (90x90 cm) (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 24 | Providing and erecting direction and Hazard Marker (Rught Side) indentification retro-reflectorised sign as per IRC-67 made of high inlensity grade sheeting vide clause 801.3 fixed over aluminium sheeting, 2mm thick with area not exceeding 0.9 sqm. Supported on a miled steel single angle iron post 75x75x6 mm firmly fixed to the ground by means of property designed foundation with M-15 grade cement concrete 45x45x60 cm. below ground level as per approved drawing, complete. (90x90 cm) SI.No. 13 (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 25 | Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days. (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 26 | Furnishing and plaching reinforced/ prestressed cement concrete M-20 grade in foundation as per drawing and Technical Specification i/c all material, labour, T&P labour cess all taxes etc. (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 27 | Supplying, Fitting and Placing un-coated HYSD bar Reinforcement in Foundation complete as per Drawing and Technical Specifications. (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 28 | Providnf weep hole with 150 mm dia PVC pipe i/c all material, labour T&P, labour cess all taxes etc. (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 29 | RCC Grade M25 using batching plant transit mixer & Concrete pump (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 30 | Supplying, Fitting and Placing un-coated HYSD bar Reinforcement in Foundation complete as per Drawing and Technical Specifications. (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 31 | Painting or varnishing new work with one coat (upto one sq. mt.) of ready mixed priming paint and one coat of approved superior quality ready mixed paint or varnish including supply of all materials, labour and tools and plants etc. required for proper completion of the work. Paint to be used should confirm the I.S.I. No. 103-1950. As per PWDSOR 641+642 (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 32 | Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days. (for culvert) (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 33 | Brick Masonry Work in Cement Mortar 1:3 in Foundation complete excluding Pointing and Plastering, as per Drawing and Technical Specifications. (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 34 | RCC Grade M25 using batching plant transit mixer & Concrete pump (for culvert) (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 35 | Supplying, Fitting and Placing un-coated HYSD bar Reinforcement in Foundation complete as per Drawing and Technical Specifications. (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 36 | Back filling behind abutment, wing wall and return wall complete as per drawing and Technical Specification (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 37 | Pointing with cement mortar (1:3 ) on brick work in substructure as per Technical Specifications (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 38 | Running of 5HP pump for dewatering including arrangement of pump suction and delivery pipes and other accessories at site including cost of POL As Per SOR NS (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) Please Enable Macros to View BoQ information |