| 1 | Construction of embankment with approved material obtained from borrow pit with all lift & leads, transporting to site by mechanical means within a lead of 5 Kms,spreading, grading to a required slope & compacting to meet requirement of table 300-2 & clause 305 of MoSRT & H specification for Road & Bridge work (AR - 06, P - 157, item no - 35) |
| 2 | Providing & laying Granular Sub-Base in layers not exceding 225 mm watering and compacting to required density in O.M.C with Vibratory Roller including hire and running charges of VRR etc complete. |
| 3 | Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with three wheeled steel roller8-10 tonnes in stages to proper grade and chamber,applying and brooming requisite type of screening/binding materials to fill up the interstices of coarse aggregate,watering and compacting to the required density as per clause 404 of MoSRT&H specificarions for Road & Bridge works(4th Revision) . |
| 4 | Grading No. -II (53-22.4 mm size) |
| 5 | Grading No. -III (53-22.4 mm size) |
| 6 | Earth work in excavation of fondation in hard soil within the initial lead & lift including dressing & levelling the bed & depositiong the excavated earth away from the site etc. all complete as per the direction of Engineer in Charge. |
| 7 | Filling sand-Supplying & filling good clean river sand of approved quality including watering to complete saturation & ramming complete with all leads & lifts including cost, conveyance, royalty & taxes of all materials & cost of all labour & T&P required for the work etc. complete as per specification & direction of Engineer in charge. |
| 8 | PCC M-15 grade in foundation bed using 40mm to 10 mm size crushed stone aggregates mixed by concrete mixer laying in layers and compacting by vibrator & all leads and lifts as per approved drawing & technical specification and as per section 1700& 2100 of MORTH specification for road and bridge works (latest revision) but excluding the charges of GST including cost conveyance etc required as directed by Engineer-in-charge. |
| 9 | PCC M-15 grade in Sub-Structure bed using 40mm to 10 mm size crushed stone aggregates mixed by concrete mixer laying in layers and compacting by vibrator & all leads and lifts as per approved drawing & technical specification and as per section 1700& 2100 of MORTH specification for road and bridge works (latest revision) but excluding the charges of GST including cost conveyance etc required as directed by Engineer-in-charge. |
| 10 | R.C.C work of M-25 grade with 20mm and down grade black hard granite (crusherbroken) stone chips including cost, conveyance, royalty & taxes of all materials & cost of all labour & T&P required for the work etc. complete as per specification & direction of Engineer in charge. |
| 11 | Deck Slab |
| 12 | Abutmant |
| 13 | Construction of R.C.C. railing of M 25 grade in cast-in-situ with 20 mm nominal size aggregate, true to line and grade, tolerance of vertical railing post not to exceed 1 in 500, centre-to-centre spacing between vertical posts not to exceed 2000 mm as per drawing and technical specifications direction of Engineer in charge. |
| 14 | Proving R.C.C M-30 Casting in Wearing Coat including cost canveyance rayality & taxes of all materials cost of all labour T&P etc, complete. |
| 15 | Supplying, fitting and placing HYSD bar reinforcement complete as per drawings and technical specification Clauses 1000 and 1200 of MoRD and as per direction of the Engineer-in-Charge. |
| 16 | Providing Weep Holes is Brick Masonry/Paln/Rainforced concrete abutment, wing wall / return wall with 100mm dia AC pipe, extending through the full width of the structure wirh slope of IV:20H towards drawing force etc, complete. |
| 17 | Providing and laying of Filter Media with Stone Crushed aggregates of 45mm size satisfying the requirements laid down in clause 2504.2.2. of MORTH Specifications to a thickness of not less than 600mm with smaller size towards the soil and bigger size. |
| 18 | Dismantling of existing structures like culverts, bridges, retaining walls and other sturcture comprising of masonry, cement concrete wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable materials and stacking the serviceable materials with all lifts and lead of 1000m as per Technical Specification Clause 202 Please Enable Macros to View BoQ information |