| 1 | Dismantling tile work in floors and roofs laid in cement mortar including stacking material within 50 meters lead. For thickness of tiles above 25 mm and upto 40 mm |
| 2 | Demolishing cement concrete manually/by mechanical means including disposal of material within 50 meters lead as per direction of Engineer-incharge:1:3:6 or richer mix (i/c equivalent design mix) |
| 3 | Demolishing R.C.C. work manually/by mechanical means including stacking of steel bars and disposal of unserviceable material within 50 meters lead as per direction of Engineer-in-charge. |
| 4 | Earth work in Excavation by manual means over areas ( exceeding 30cm and up to 1.5 mtr in depth, 1.5 mtr in width as well as 10 sqm on plan) including disposal of excavated earth up to 1 mtr from cutting edge, disposed earth is to be leveled and neatly dressed in All kinds of soils. |
| 5 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with: 1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate 40 mm nominal size) |
| 6 | \"Providing and laying in position cement concrete of specified grade including curing butexcluding the cost of centring and shuttering. All work upto plinth level with: 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size)\". |
| 7 | Providing and laying in position specified grade of reinforced cement concrete including curing but excluding the cost of centering, shuttering, finishing and reinforcement. All works upto plinth level 1:1½:3 (1 cement : 1½ coarse sand : 3 graded stone aggregate 20 mm nominal size) |
| 8 | \"Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing inposition and binding all complete upto plinth level Thermo-Mechanically Treated bars of grade Fe-500Dor more\" |
| 9 | Centering and Shuttering including strutting, propping etc. and removal of Formwork for foundation complete job |
| 10 | Steel work welded in built up sections/framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steelprimer using structural steel etc. as required. In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works. |
| 11 | 12mm thick cement plaster of mix 1:4 |
| 12 | P/F of 60mm thick interlocking paver tile to be laid in cement mortar 1:4 mix & fill joint with C.mortar 1:3 mix complete job |
| 13 | Providing and Fixing of GI Pipes 15mm complete with GI fittings |
| 14 | Providing and fixing on wall face un-plasticized Rigid PVC rain water pipes conforming to IS: 13592 Type A including jointing with seal ring conforming to IS: 5382 leaving 10 mm gap for thermal expansion. Single socketed pipes 75 mm diametre |
| 15 | Providing and fixing on wall face un-plasticized Rigid PVC rain water pipes conforming to IS: 13592 Type A including jointing with seal ring conforming to IS: 5382 leaving 10 mm gap for thermal expansion. Single socketed pipes 110 mm diametre |
| 16 | Providing and fixing on wall face un-plasticized - PVC moulded fittings/accessories for un plasticized Rigid PVC rain water pipes conforming to IS : 13592 Type A including jointing with seal ring conforming to IS : 5382 leaving 10 mm gap for thermal expansion. Bend 87.5° 75 mm beend |
| 17 | Providing and fixing on wall face un-plasticized - PVC moulded fittings/accessories for un plasticized Rigid PVC rain water pipes conforming to IS : 13592 Type A including jointing with seal ring conforming to IS : 5382 leaving 10 mm gap for thermal expansion. Bend 87.5° 110 mm bend |
| 18 | Providing and fixing on wall face un-plasticized - PVC moulded fittings/accessories for un plasticized Rigid PVC rain water pipes conforming to IS : 13592 Type A including jointing with seal ring conforming to IS : 5382 leaving 10 mm gap for thermal expansion. Coupler 75 mm bend |
| 19 | Providing and fixing on wall face un-plasticized - PVC moulded fittings/accessories for un plasticized Rigid PVC rain water pipes conforming to IS : 13592 Type A including jointing with seal ring conforming to IS : 5382 leaving 10 mm gap for thermal expansion. Coupler 110 mm bend |
| 20 | Removal of Excavated Malba dismantled unserviceable material from site of work. |
| 21 | Providing and Laying DPC 50mm thick with cement concrete 1:2:4 |
| 22 | Providing and Fixing of inaguration stone |
| 23 | Carriage of constructed material (sand + Aggregate) Please Enable Macros to View BoQ information |