| 1 | Demolishing R.C.C. work manually/by mechanical means includingstacking of steel bars and disposal of unserviceable material within50 meters lead as per direction of Engineer-in-charge. |
| 2 | Demolishing cement concrete manually/by mechanical means includingdisposal of material within 50 meters lead as per direction ofEngineer-in_charge:1:3:6 or richer mix (i/c equivalentdesign mix) |
| 3 | Dismantling manually/ mechanically including stacking of serviceablematerial and disposal of unserviceable material within 50 meters lead asper direction of Engineer-in-charge:Bituminous road. |
| 4 | Dismantling tile work in floors and roofs laid in cement mortar includingstacking material within 50 meters lead.For thickness of tiles above 25 mm and upto 40 mm. |
| 5 | \"Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering.All work upto plinth level with: 1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate 40 mmnominal size) |
| 6 | Providing and laying in position cement concrete of specified grade including curing butexcluding the cost of centring and shuttering. All workupto plinth level with 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) |
| 7 | \"Providing and laying in position specified grade of reinforced cement concrete including curing but excluding the cost of centering,shuttering, finishing and reinforcement. All works upto plinth level 1:1½:3(1 cement : 1½ coarse sand : 3 graded stoneaggregate 20 mm nominal size)\" |
| 8 | \"Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing inposition and binding all complete upto plinth level Thermo-Mechanically Treated bars of grade Fe-500Dor more\" |
| 9 | Centering and Shuttering including strutting, propping etc. and removal of Formwork for foundation complete job |
| 10 | Steel work welded in built up sections/framed work, including cutting, hoisting, fixing in position and applying a priming coat ofapproved steelprimer using structural steel etc. asrequired. In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works. |
| 11 | Removal of Excavated Malba dismantled unserviceable material from site of work. |
| 12 | \"Carriage of materials by mechanical transport including loading / unloading & stacking complete.• Sand/Crusher Dust/stone Aggreagte for an average distance 10 Km by MT.\" |
| 13 | P/F of 60mm thick interlocking paver tile to be laid in cement mortar 1:4 mix & fill joint with C.mortar 1:3 mix complete job |
| 14 | 12mm Cement plaster of mix 1 : 6 ( 1 cement : 6 fine sand) |
| 15 | Providing and laying damp-proof Course 50 mm thick with cement concrete 1:2:4 (1cement:2 coarse sand: 4 graded stone aggregate 20mm nominal size) and curing complete |
| 16 | Providing and fixing of inauguration plate Please Enable Macros to View BoQ information |