|
| 1 | (4.10.1)Earth work in excavation in foundation,trenches etc. including dressing of sides and ramming of bottoms, including getting out the excavated material, refilling after laying pipe/ foundation and disposal of surplus excavated material at a lead upto 50m suitable site as per direction of Engineer for following depths, below natural ground / Road top level.In all types soils/ saturated soil such as moorum, sand, sandy silt,clay, black cotton soil, kankar,etc.Depth upto 1.5 m. |
| 2 | (4.2.1)Earth work in excavation for roadway, including trimming bottom and side slopes in accordance with requirement of line, grades and cross sections, including disposal of surplus material with all lift and lead upto 1000 metre as per MoRT&H specification clause 301. |
| 3 | (1.1.3)Carriage of Materials by mechanical transport including loading,unloading and stacking::Stone,boulders,gravelly material Lead upto 5Km. |
| 4 | (21.1.8)Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering - All work upto plinth level :1:5:10 (1 cement : 5 fine/ coarse sand : 10 graded stone aggregate 40 mm nominal size) |
| 5 | (9.1)Providing and laying lean cement concrete 1:4:8 in Sub- base over a prepared sub-grade with coarse and fine aggregate conforming to IS: 383, the size of coarse aggregate not exceeding 25 mm, aggregate cement ratio not to exceed 15:1, aggregate gradation after blending to be as per table 600-1, cement content not to be less than 150 kg/ cum, optimum moisture content to be determined during trial length construction, concrete strength not to be less than 10 Mpa at 7 days, mixed in concrete mixer, laid manually, compacted with surface vibrator, finishing and curing complete as per clause 601, 112 of MoRT&H specification including all material, labour, machinery, lighting, guarding and maintenance of diversion. |
| 6 | (25.1.2)Random rubble masonry with hard stone in foundation and plinth :Cement mortar 1:4 (1 cement : 4 coarse sand) |
| 7 | (25.2)Add Extra for random rubble masonry with hard stone in superstructure above plinth level and upto two stories. |
| 8 | (32.3.3)Cement plastering including T&P, scaffolding, material and complete labour, including cost of water, curing, racking of joints etc. with 20 mm cement plaster of mix : including Providing /mixing of synthetic fibers compulsorily complying with IS 16481:2022 of 06 mm/12 mm length to be mixed @ 0.25% by weight of Cement i.e. 125 gms per 50 kg Cement up to 900 gms per cum of Concrete/ mortar 1:6 (1 cement : 6 fine/ coarse sand) |
| 9 | (26.23)Providing & fixing precast cement concrete coping 1 : 2 :4 mix 50mm thick complete as per specification |
| 10 | (29.26.2)Steel work welded in built up sections/ framed work including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works. |
| 11 | (32.35.1)Finishing walls with Acrylic Smooth exterior paint of required shade New work (Two or more coat applied @ 1.67 ltr/10 sqm over and including base coat of water proofing cement paint applied @ 2.20 kg/ 10 sqm). |
| 12 | (32.50.1)Painting with synthetic enamel paint of approved brand and manufacture to give an even shade Two or more coats on new work. |
| 13 | (4.4)Construction of embankment with approved material obtained from borrow pit with all lifts and leads, transporting to site, spreading, grading to required slope and compacting by vibratory roller 8-10 tonne to meet requirement of table 300-2 including cost of compensation for earth taken from private land complete as per MoRT&H specification clause 305. (Lead taken upto 5 km) |
| 14 | (9.11)Providing and fixing of 60mm thick precast cement concrete interlocking paver block casted with rubber moulds in approved reflective colour and design having minimum compressive strength of 300 kg/ sq cm. The CC paving blocks be laid on average 50mm thick bed of coarse sand and the joint is to be filled with fine sand. Laying procedure on compacted sub-base as defined. Complete job is to be executed as per the instruction of Engineer in-charge. The rates to be inclusive of all lead & Lifts etc. complete as per specifications. |
| 15 | (10.1)Providing and fixing precast cement concrete M-20 grade (Using mechanical Concrete Mixer) kerb stone top and bottom width 115 and 165 mm respectively, 250 mm high on 150 mm thick PCC M-10 grade foundation as per design, including fixing at site as per clause 408 of MoRT&H Specification including all material, labour, machinery, lighting, guarding and maintenance of diversion. Please Enable Macros to View BoQ information |