| Sl. No. | Item Description |
| 1 | Supply, laying, jointing,testing and commissioning LT underground cables, 1100 volts grade, cross-sectional area 70 sq. mm 3.5 core XLPE Insulated and PVC sheathed, heavy duty armoured, with multistranded aluminium conductors, IS-7098 marked, laid in trenches / ducts / fixed on poles / walls / laid under roads / paths / drain / culverts or encased in GI pipe, complete all as specified and as directed. Note : Rate quoted includes terminal lugs / road cutting / wall cutting / floor cutting and making good damaged portion matching with existing surface with all existing finishes. |
| 2 | All as per item No 01 above, but for sectional area 50 sq.mm 3.5 core. |
| 3 | All as per item No 01 here-in-before, but for sectional area 25 sq.mm 4 core. |
| 4 | All as per item No 01 here-in-before, but for sectional area 16 sq.mm 4 core. |
| 5 | Supply, laying, jointing, testing and commissioning HT underground cables, 11000 volts earthed, grade cross-sectional area 150 sq. mm 3 core XLPE Insulated, screened, PVC bedded, galvanised steel strip or wire armoured, electric power cables (heavy duty) with aluminium conductor, IS-7098 marked, laid in trenches / ducts / fixed on poles / walls / laid under roads / paths / drain / culverts or encased in GI pipe, complete all as specified and as directed. Note : Rate quoted includes terminal lugs / road cutting / wall cutting / floor cutting and making good damaged portion matching with existing surface with all existing finishes. |
| 6 | Taking out old unserviceable LT under ground cable from , in trenches / ducts / on poles / walls / under roads / paths / drain / culverts or encased in GI pipe, complete all as specified and as directed.Note : Rate quoted includes road cutting / wall cutting / floor cutting and making good damaged portion matching with existing surface with all existing finishes. |
| 7 | Taking out old unserviceable HT under ground cable from , in trenches / ducts / on poles / walls / under roads / paths / drain / culverts or encased in GI pipe, complete all as specified and as directed.Note : Rate quoted includes road cutting / wall cutting / floor cutting and making good damaged portion matching with existing surface with all existing finishes. |
| 8 | Excavation in trenches not exceeding 1.5 mtr deep and 1.5 mtr width as in soft/loose soil complete all as specified and as directed. |
| 9 | Returning, filling in, including spreading, levelling,watering and well ramming in layers not exceeding 25 cm thick complete all as specified and as directed. |
| 10 | Removal of surface soil to a distance n.exc 50 m and deposited where directed at a level n. exc 1.5 m above the starting point complete all as specified and as directed. |
| 11 | Supplying and Laying sand forcushioning for cable protection in trenches 8 cm before laying cable and 15 cm deep over the cable, complete all as specified and as directed.( Note: Punned thickness shall be taken for measurement) |
| 12 | Supplying and Laying for un-reinforced precast concrete cable cover, (ISI Marked) class LV, Type I, flat, size 250mm x 150mm x 40mm, complete all as specified and as directed. |
| 13 | Supplying and Laying for un-reinforced precast concrete cable cover, (ISI Marked) class HV, Type I, flat, size 300mm x 180mm x 40mm, complete all as specified and as directed. |
| 14 | Material and Labour for straight through heat shrinkable joints 1100 Volts,PVC / XLPE insulated armoured Heavy duty LT UG cables with aluminium conductor including joint kitsfor cable size 3.5 core 70 sq.mm, complete all as specified and as directed. |
| 15 | Material and Labour for indoor termination heat shrinkable joints 1100 Volts, XLPE insulated armoured Heavy duty LT UG cables with aluminium conductor including joint kits for cable size 3.5 core 70sq.mm, complete all as specified and as directed. |
| 16 | Material and Labour for straight through heat shrinkable joints 1100 Volts, XLPE insulated armoured Heavy duty LT UG cables with aluminium conductor including joint kits for cable size 3.5 core 50sq.mm, complete all as specified and as directed. |
| 17 | Material and Labour for indoor termination heat shrinkable joints 1100 Volts, XLPE insulated armoured Heavy duty LT UG cables with aluminium conductor including joint kits for cable size 3.5 core 50sq.mm, complete all as specified and as directed. |
| 18 | Material and Labour for 11KV (earthed ) cable jointing kit out door end termination heat shrinkable type with jointing material and accessories suitable for 3 core XLPE armoured aluminium cable of size 150sqmm, complete all as sepcified and as directed. |
| 19 | Supply, installing, testing and commissioning, factory made and tested LT feeder pillar box (KIOSK) 1200mm x 900mm x 500mm size, outdoor type, platform mounted suitable for 415 volts 3 phase 4 wire, 50 HZ AC supply system, having bus bar chamber with insulated aluminium bus bars 250 Amps rating installed on porcelain insulators. The panel shall be dust and vermin proof, IP 65 class protection and made of 3.15mm thick CRCA MS sheet and 40x40x4mm thick angle iron frame work, powder coated finish over one coat of red oxide primer outside and two coats of red oxide primer on inside, front opening type, with aprons for for cable entry, and fixing danger notice plate made of 1.6 mm thick mild steel sheet, vitreous enameled white, of size20 x 15cm with letter, figures and conventional skull bones in signal red colour and fixed front & back door |
| 20 | LTpanel etc with voltage and danger indicated in Hindi and English with double door shutter and locking arrangement (including provision of 65mm Godrej (freedom) stranded lock with 2 keys, internal wiring with PVC insulated, stranded copper conductor, FRLS cables, IS-694 marked of adequate size but not less than 2.5 Sq.mm. The platform shall be such that it is of a height 30 cm above the nearest road level, including connections of all out going / in coming existing cables by drawing / digging out cable from loops in trenches out side the Bldg inclusive of necessary excavation and earth work as required and relaying the cables with retrieved bricks and providing new sand cushioning and crimping suitable size copper lugs for terminal connections of cables, necessary brick foundation with plastering to the panel board,the various feeders shall be indicated |
| 21 | by 50 mm size letters in synthetic enamel white paint including taking out of old unserviceable skeleton type panel with control switches complete all as specified and as directed. The scope of work includes the following :-(a) 3 Nos for phase (R,Y,B) rating 250 amp and 1No for neutral rating 240 Amp, Mounted on DMC support with heat shrink sleeve - 1 Set(b) Manual changeover160A- 1 No(c) MCCB 4P 160 Amps 25 KA 415 V 50 Hz – 1 No (I/C)(d) MCCB 4P 100 Amps 25 KA 415 v 50 Hz - 2 No(e) Panel socket 32A, 3P+N+E-- 1 No(f) Time switch 24 Hr Digital-- 1 No(g) MCB DP 32 Amps 10 KA 415 v 50 Hz - 2 Nos |
| 22 | (h) Multifunction meter,Class 1, three phase, digital type, with parameters like voltage, ampere, frequency, PF etc, and with suitable rated CT’s complete including selector switch for three phase etc(j) Indication Lamp (R,Y,B), LED Type, With toggle switches – 1 Set of Three |
| 23 | Material and Labour for fixing standalone bus bar panel for XLPE cable termination of size minimum 50 sqmm including Aluminium bus bar of 200 Amps with provision for cable entry and earth termination including taking down old unserviceable Bus bar anytype and size. The panel shall be fixed at least 30 CM above the ground with panel stand firmly grouted to the ground and necessary PCC and excavation shall be deemed to be included in the rate. The Bus bar shall be of Aluminium of 200 Amps and max of length 80CM and of size 20x5mm . R, Y, B and Neutral shall have bus bars of same size and length etc., complete all as specified and as directed. |
| 24 | Dismantling ofACSR or AAC conductor squirrel type from poles of any size & capacity and unserviceable materials removing from the site complete all as specified and as directed. |
| 25 | Material and Labour forArial Bunched Cable (ABC), 5 core,( 3 phase, 1 Neutral, 1 Messenger, 1 Street light) of size 70 Sqmm (3x70+1x70+1x50+1x16), 1100 Volt grade, confirming to IS 1455. All as specified and as directed.Note: (i) The three phase cables, Neutral , and street light conductor shall be twisted around messenger to form cable assy.(ii) The phase and neutral conductors shall be insulated with XLPE.(iii) The quoted rate shall also include necessary fixing arrangement in the existing poles and conenction to street lights. |
| 26 | Material and Labour for surface dressing once in every 2 monthsto E/Minstallations /1.5 Mtrs from out side of fencing ,E/M store yardsof Tech area main incomer substation 100 sqm areanot exceeding 15 cm deepgetting out soft / loose soilremovingshrubs, small trees height up to 1.0 Mtrs, removing the grass from route and cleaning the fencing by removing small treees /Vegetation on fencing complete all as specified and as directed. Note : (i) Rate includesremoving all waste material and grass exceeding 500 Mtrs distance from installation ,depositing where directed at a level not exceeding 1.5 Mtrs above the starting pointand cleaning of yard , Complete all as specified and as directed. |
| 27 | All as per item No 23 above, but for Non tech area pump house 80 Sqm. |
| 28 | Material and Labour for road cutting / removing the hard Standing / Cutting floor inside the Substation / E/M Installations / Path for laying of cables of any size complete all as specified and as directed. Note : quoted rate shall include cutting of road, and necessary PCC for making good . |
| 29 | Supply and fixing in repair Onload Change over switch of capacity 125 A, 4 Pole, 415 Volts, 50 Hz, with Panel Mounted rotating handle, including dismantling old unserviceable change over switch by disconnection all incoming and outgoing electrical connection from existing indoor LT Panel complete all as specified and as directed. |
| 30 | Material and labour for laying 40 mm stones in the substation yard to reduce touch potential. Using hard stones, broken and sized up to 63 mm, complete all as specified and as directed. |
| 31 | Material and labour for repairing/servicing calibrating testing and recommissioning ACB, upto 1.1 KV, out door/indoor type, including replacement of gasket set, adjusting reconditioning stationery moving contact, adujsting link mechanism within limit, nut, bolt and washer including replacement of damage thimbles of required size complete all as specified and as directed. |
| 32 | Supply and Fix for medium grade GI pipe 40mm dia for cable protection, complete all as specified and as directed . |
| 33 | Supply and fix breather for transformer oil conservator tankincluding filled with silica gelfor transformer of ratings 160 KVA complete all as specified and as directed. |
| 34 | Material and Labour for filtrationof transformer oil of different capacity / Rating to remove moisture, sludge, carbon particles and to acheivethe dielectric strength / rupturing capacity of oil not less than 50 KV/ minute with 2.5mm gap and topping up of oil to the required level of transformer indicator level, complete all as specified andas directed . Note: (a)Topping up of transformer oil shall be measured and paid separately(b) Contractor has to make his own arrangement for oil filtration plant. |
| 35 | Material and Labour for topping up/ change oil for transformer of 11KV/433 Volt of different capacity/HT oil switch of 11 KV of different capacity of any rating of dielectric strength / rupturingcapacity of oil not less than 50 KV ( tested at site with testing kit with2.5 mm gap ) and test the the dielectric strength of transformer oilbefore and after the topping up and makeoil to the required level of transformer indicator level, complete all as specified andas directed .Note: (a) The transformer oil container shall be ISI marked and brought at site in sealed container only.(b) The Material and Labour fornecessary T & P forcollection of transformer oil samples , testing kitand filteration plant is inclusive in rate quoted. |
| 36 | Supply, installing, testing and commissioning, factory made and tested LT feeder pillar box (KIOSK) 1000mm x 900mm x 500mm size, outdoor type, platform mounted, suitable for 415 volts 3 phase 4 wire, 50 HZ AC supply system, having bus bar chamber with insulated aluminium bus bars 300 Amps rating installed on porcelain insulators. The panel shall be dust and vermin proof, IP 65 class protection and made of 3.15mm thick CRCA MS sheet and 40x40x4mm thick angle iron frame work, powder coated finish over one coat of red oxide primer outside and two coats of red oxide primer on inside, front opening type, with aprons for for cable entry, and fixing danger notice plate made of 1.6 mm thick mild steel sheet, vitreous enameled white, of size20 x 15cm with letter, figures and conventional skull bones in signal red colour and fixed |
| 37 | front & back door. LTpanel etc with voltage and danger indicated in Hindi and English with double door shutter and locking arrangement (including provision of 65mm Godrej (freedom) stranded lock with 2 keys, internal wiring with PVC insulated, stranded copper conductor, FRLS cables, IS-694 marked of adequate size but not less than 2.5 Sq.mm. The platform shall be such that it is of a height 30 cm above the nearest road level, including connections of all out going / in coming existing cables by drawing / digging out cable from loops in trenches out side the Bldg inclusive of necessary excavation and earth work as required and relaying the cables with retrieved bricks and providing new sand cushioning and crimping suitable size copper lugs for terminal connections of cables, necessary brick foundation with plastering to the panel board,the |
| 38 | various feeders shall be indicated by 50 mm size letters in synthetic enamel white paint including taking out of old unserviceable skeleton type panel with control switches complete all as specified and as directed. The scope of work includes the following :-(a) 3 Nos for phase (R,Y,B) rating 300 amp and 1No for neutral rating 300 Amp, Mounted on DMC support with heat shrink sleeve - 1 Set(b) MCCB 4P 63 Amps 16/18 KA 415 V 50 Hz – 4 No (c) MCCB 4P 200 Amps 25 KA 415 v 50 Hz - 1 No (I/C)(d) MCB DP 32 Amps 10 KA 415 V 50 Hz-4 Nos |
| 39 | (e) Multifunction meter, class 1, three phase, digital type, with parameters like voltage, ampere, frequency, PF etc, and with suitable rated CT\"s complete including selctor switch for three phase etc. (f) Indication Lamp (R, Y, B), LED Type, with toggle switches - 1 Set of Three |
| 40 | Supply and Fix in repiars 4 pole, MCCB, 630A, adjustable thermal magnetic , 50KA breaking capacity, complete all as specified and as directed. |
| 41 | Supply and Fix in replacement of MCCB 4 Pole 100-125 Amps 415V 25 KA, complete all as specified and as directed. |
| 42 | Supply and Fix in replacement of MCCB 4 Pole 400 Amps 415V 36 KA, complete all as specified and as directed. |
| 43 | Supply and fix in replacement MCB of 63 Amp , 50 Hz AC Supply 10 KA with necessary aluminiumlugs up to 16 Sq mm, complete allas specified and as directed . |
| 44 | Supply and fix in replacement MCB DP 32-40 Amp 240 V 50 Hz AC 10 KA ,with necessarylugs for incomming and outgong connectionsfixed onDB / Enclosure /Panel Boards after taking down the existing MCB etc., complete all as specified and as directed. |
| 45 | All as per item No 38 above, but for MCB SP 6 to 32 Amp, \"C\" Curve. |
| 46 | Cutting the tree branches at a distance not exceeding 2.0 Mtrs way fromroof top of E/M Installation of G+0 Building oftree branch sizeup to 50mm dia and deposited the removing branches at a distance not exceeding 100 Mtrs from Road /Path, complete all as specified and as directed. Note: Branch cutting around 2.0 Mtrs area to a 3 Nos street light pole is considered as one Job. |
| 47 | Supply and Fix in replacement of galvanised iron strip 32 x 6 mm buried in ground with saddles and fixing screwes etc for roof conductors and down conductors including removing and replacement of deteriorated SS bolts, nuts and washers as required at site etc in the existing GI strip of any size from the starting point to upto the end connected points, complete all as specified and as directed . |
| 48 | Dismantling HT/ LT stay assembly complete including MS clamps with bolts, nuts & washers etc along with necessary excavation and earth work, demolition of cement concrete and removing from the site, complete all as specified and as directed. |
| 49 | Material and Labour for stay assembly complete with accessories such as mild steel glavanised flat iron stay clamp, 7/3.15 mild steel galvanised stay strand/wire, one loop type porcelain vitreous insulator (white , brown or green) over all dimensions 65X90 mm & clearing hole 16 mm, stay grips, mild steel galvinsed stay bow, thimbles, 16 mm diameter of stay rod shown in electrical plate No 1 of MES SSR Part- Icomplete all as specified and as directed. Note : Excavation & earthwork, cement concrete concrete measured and paid separately under relevant items of this schedule. |
| 50 | Dismantling cross arms, MS channel or angle sections etc. complete and unserviceable removing from the site complete all as specified and as directed . |
| 51 | Material and Labour for providing cross arms, bracings, support clamps and back plates fabricated from structural steel section including nut bolts washer, welding, bending cold or hot drilling holes for bolts in any shape or size as indicated or directed including two coats of aluminium paint over a coatof read oxide zinc chrome primer including preparation of surfaces complete all as specified and as directed. |
| 52 | Supply and Fix in repair switches air break Gang operated, triple pole , mechanically operated, 11 KV, mounted on insulator and steel frame, with opearting mechanism worked from ground level for a current rating up to 200A, complete all as specified and as directed. |
| 53 | Supply and Fix in repair 33KV lightning arresters expulsion type complete with all fittings, transmission class, with discharge capacity 65 Kilo Amps, complete all as specified and as directed. |
| 54 | Supply, installing, testing and commissioning, factory made and tested LT feeder pillar box (KIOSK) 1000mm x 900mm x 500mm size, outdoor type, platform mounted, suitable for 415 volts 3 phase 4 wire, 50 HZ AC supply system, having bus bar chamber with insulated aluminium bus bars 250 Amps rating installed on porcelain insulators. The panel shall be dust and vermin proof, IP 65 class protection and made of 3.15mm thick CRCA MS sheet and 40x40x4mm thick angle iron frame work, powder coated finish over one coat of red oxide primer outside and two coats of red oxide primer on inside, front opening type, with aprons for for cable entry, and fixing danger notice plate made of 1.6 mm thick mild steel sheet, vitreous enameled white, of size 20 x 15cm with letter, figures and conventional skull bones in signal red colour and fixed |
| 55 | front & back door. LTpanel etc with voltage and danger indicated in Hindi and English with double door shutter and locking arrangement (including provision of 65mm Godrej (freedom) stranded lock with 2 keys, internal wiring with PVC insulated, stranded copper conductor, FRLS cables, IS-694 marked of adequate size but not less than 2.5 Sq.mm. The platform shall be such that it is of a height 30 cm above the nearest road level, including connections of all out going / in coming existing cables by drawing / digging out cable from loops in trenches out side the Bldg inclusive of necessary excavation and earth work as required and relaying the cables with retrieved bricks and providing new sand cushioning and crimping suitable size copper lugs for terminal connections of cables, necessary brick foundation with plastering to the panel board,the |
| 56 | various feeders shall be indicated by 50 mm size letters in synthetic enamel white paint including taking out of old unserviceable skeleton type panel with control switches complete all as specified and as directed. The scope of work includes the following :-(a) 3 Nos for phase (R,Y,B) rating 300 amp and 1No for neutral rating 300 Amp, Mounted on DMC support with heat shrink sleeve - 1 Set(b) MCCB 4P 63 Amps 16/18 KA 415 V 50 Hz – 2 No (c) MCCB 4P 160 Amps 25 KA 415 v 50 Hz - 1 No (I/C)(d) MCB DP 32 Amps 10 KA 415 V 50 Hz-4 Nos |
| 57 | (e) Multifunction meter, class 1, three phase, digital type, with parameters like voltage, ampere, frequency, PF etc, and with suitable rated CT\"s complete including selector switch for three phase etc. (f) Indication Lamp (R, Y, B), LED type, with toggle switches- 1 set of Three.Note :(i) Necessary PCC and coping work for fixing the panel is inclusive in the quoted amount.(ii) Drawings shall be pre approved from Engineer-in-Charge before making order. |
| 58 | Material and Labour for dismantling the burnt winding (Primary/Secondary) and rewinding the distribution transformer (oil-cooled, copper-wound, 160 KVA capacity) from its installed position on the existing platform . This includes:(a) Disconnecting the electric supply from HV and LV sides.(b) Removing the transformer from its installed position and transporting it to the workshop. (c) Conducting a preliminary inspection and diagnosing faults.(d) Performing service tasks such as oil draining, removing the transformer top cover, dismantling the bush stem, removing the core coil assembly (CCA), and cleaning job components.(e) Dismantling the CCA and performing coil winding and refixing.(f) Conducting terminal gear cutting and rejoining, tanking, and all associated jobs. |
| 59 | (g) Replacing washers, sleeves, taps, kerb tapes, and cork sheets as necessary (h) Refilling the transformer oil after checking and ensuring the functionality of the Winding Temperature Indicator (WTI) and Oil Temperature Indicator (OTI), including the replacement of unserviceable items if required.(i) Refilling the transformer oil after checking and ensuring the functionality of the Winding Temperature Indicator (WTI) and Oil Temperature Indicator (OTI), including the replacement of unserviceable items if required.(j) Reinstalling the transformer in its original position and making all electrical connections with thimbles and PG clamps. |
| 60 | (k) Commissioning the transformer, which includes refilling transformer oil after dehydration with dielectric strength (minimum 60 KV) and conducting thorough testing to ensure proper operation and functionality. |
| 61 | Material and labour for providing a transformer of the same rating on a rental basis on the same day, including installation to replace the burnt transformer, making the necessary connections to continue the supply at the site, and dismantling the temporary transformer after repairing the faulty one. It also includes the cost of transporting the transformer from the workshop to the site, complete all as specified and as directed. |
| 62 | Material and Labour for Earthing complete with galvanized steel earth plate electrode 600x600x6.0mm thick buried directly in ground (earth pit not less than 2.25 meters deep below ground level) with top edge of the plate not less than 1.5 meters below normal ground level connected to galvanized iron strip 32x6 mm as earthing by means of bolts nuts and washers of galvanized iron including excavation and earth work and disposal of surplus soil including 40 mm GI tubing light grade and necessary fittings for protection of GI strip including laying of charcoal , dust and common slat , PCC 1:2: 4 type B 1 using 320 mm graded aggregate with earth pit with 40 X 40 X 6.0 mm MS angle iron frame RCC cover 40 mm thick (1:2: 4) type C1 using 20 mm graded stone aggregate reinforced with 8 mm dia round bar @ |
| 63 | 75 mm C/C both way with MS handle 20 mm dia, plastering 15 mm thick CM ( 1: 6) internally and up to 150 mm below ground level externally . PGI funnel with wire mesh 20 mm dia GI pipe for watering complete all as shown on electrical plate No : 03 of SSR part -I 2009 and connected to earth test point including testing, complete all specified and as directed. |
| 64 | Material and Labour for removing of dirt by using sand paper completely and preparation of old painted steel surface of Transformer and any gauge/size with applying two coats of primer with red oxide Zinc chrome and a final coat of Japan paint as existing colour of paint by spray paint (Using Machine) at four sides, top and bottom of transformer capacity ofrating160 KVA , complete painting of the transformer to match the existing color, with the MES number neatly displayed,all as specified and as directed by Engineer in charge. |
| 65 | Note: (i) Contractor has to take the shutdown of Transformer 11/0.433 KV from substation before starting the execution of work and switch ON/OFF on the Transformer after completion of work all as directed.(ii) Cost of T & P also included in quoted rate. (iii) The contractor should be deployed the skilled electrician for handling the HT & LT installation smoothly without damaging/disturbing the existing installations. |
| 66 | Supply and Fixfor load line vertical MCCB DB, 4 Way, Double door with 125 A MCCB incomer and three/single phase outgoing. The DB should be fitted with suitably rated bus bar, neutral links, blanking plates etc. |
| 67 | Repair to street light/flood light of any type,any description mounted on pole/ Roof/ wall ,disconnecting electrically, testing of all components to ascertain defective parts of the fitting and testing the conductivity of electric cable of internal wiring of the fittings, dismantling of defective componentsand testing the fitting after replacement of defective components and cable of internal wiring and making the fitting fully functional testing complete all as specified and as directed. |
| 68 | All as pe Ser item No 54 above but post top / Bollard light |
| 69 | Repairto high mast light fitting mounted on up to 16 mtr height structure of qty 09 to 12 light fitting, lowering disconnecting electrically, testing of all components to ascertain defective part of the fitting and testing the conductivity of electric cable of internal wiring of the fittings, dismantling of defective components, testing the fitting after replacement of defective componentsand making the fitting fully functional finally entire unit to be raised upto its original level complete all as specified and as directed. Note : The necessary components should be measured and paid separately. |
| 70 | All as per item No 56 above, but 300W, with 10KV SPD to be fixed on High mast of height up to 12m, complete all as specified and as directed. |
| 71 | Supply and Fix in repair LED street light luminaires 60 W, IP-66 with pressure die cast aluminium housing , Heat resistant toughened glass with frame, including taking down existing unserviceble HPSV/MH/LED fitting fromSteel /PCC pole up to 9.00 Mtrs height or from wallcompleteall as specified and as directed. Note:Height of new fitting should adjusted to achieve better illumination level so as to match with LED fittings as directed. |
| 72 | Supply and Fix in repair LEDflood light fitting 150W, 110 L/Watt efficacy with 10KV SPD andhigh pressure die cast housing IP 66 protection for area lighting with necessary fixing arrangment on pole/Wall with suitable size MS clamp , nuts & bolts for lightscompleteincluding taking down old unserviceble fitting of any type and depositing to storefor credit all as specified and as directed by Engineer-in-Charge. |
| 73 | Supply and Fix in repair of post top luminaire die cast housing and clear acrylic and spun aluminium reflectorof IP 65 protection , resistanceto corrsion of 40 Watt with LED lamp with all fixing arrangementsfixedto post top complete including taking down old unserviceable fitting of any type and depositing to storefor creditall as specified and as directed . |
| 74 | Supply and Fix in repair of Bollard luminaire die cast housing and clear acrylic of IP 65 protection Inverted Tripod type , resistanceto corrosion of 10 Watt with LED lamp with all fixing arrangementsfixedwith soft 360 deg light distributioncomplete including taking down old unserviceable fitting of any type and depositing to storefor creditall as specified and as directed . |
| 75 | Supply and fix, testing and commissioning of17W hybrid All in One Solar street light with not less than 3000 Lumens light output and more than 180 Lumens per watt system efficiency. 50,000 burning hours as per L70. Built in maintenance free Lithium Ferro Phosphate Battery(Life Po4) with >256Wh capacity, 35 wp solar panel module. The housing shall be made of Single piece Pressure diecast Aluminium Housing in non corrosive 500 hours NSS Salt spray tested finish and UV stabilised polycarbonate cover with embeded lens for each LED\"s. 3 step Adjustable Arm tilting option to adjust the light distribution with no additional pole support suitable for mounting on arm bracketdirectly on pole top. |
| 76 | Hybrid type MPPT Charge controller and driver efficency shall be greater than 90%.all including octogonal pole of 5m with FDN bolt andbase plate size of 200x200x12mm and sheet thickness 3 mm fixed including RCC , complete all as specified and as directed. |
| 77 | Supply and Fix passing through pole cable 3 core PVC insulated unsheathed multistranded copper conductor of size 2.5 Sqmm from junction box to fitting,complete all as specified and as directed . |
| 78 | Material and Labour for cleaning of feeder piller/ panel after dismantling the Incomming and outgoing connections from MCBs and replacing the old unserviceable Gland, lugs, nuts & bolts, push buttons, indicating lamps, supporting insulators etc., and checking the serviceability of MCBs, cables and earth continuity conductor including replacement of worn out and unserviceable minor accessories, complete all as specified and as directed .Note: Spares / materials charge for repair/replacement of wornout parts shall be measured and paid seperatley under relevant items |
| 79 | Supply and Fix junction box transparent type ready made of size 133x205x95 mm with aluminium bus bar of 50Amp capacity for RYB andhalf for neutral made in suitablesize fixed inside the junction box with necessary supporting insulators fixed on hylem sheet ,MS sheet steel fixed inside the bottom portion of box to connect the cable gland complete , entire assemblyfixed to pole /Wall with MS clamp 25 X 5 mm and nuts & bolts, or inside the Copping of pole /Post top including MCB SP 6 Amp 10 KA 240 V - 1 No, with necessary sizecopper lugs for connecting cables from junction box to fittings, complete all as specified and as directed. |
| 80 | Material and Labour for painting of PCC pole with cement base paint one coat suitable for outdoor including cleaning of poles removing creeper etc from pole, complete all as specified and as directed . |
| 81 | Material and labour for painting Steel Tubular Poles (Swaged Type) For Street Lightingof height maximum up to15 Mtr single dome typeup to light fitting complete including two coat of synthetic enamel paint over one coat of red oxide primer complete all as specified and as directed . |
| 82 | Cutting the tree branches at a distance not exceeding 3.0 Mtrs away fromStreet light poles /fitting including removing the creeper which surrounded the poles and street lights ,oftree branch sizeup to 50mm dia as directed and deposited the removing branches at a distance not exceeding 100 Mtrs from Road /Path. Complete all as specified and as directed. |
| 83 | Material and Labour for PCC 1:4:8 type D2 40 mm graded stone aggregateCompletefor foundations for post top lantern /PCC at road crossing etc,complete all as specified and as directed. |
| 84 | Material and Labour for PCC 1:3:6 type C120 mm graded aggregate in coping of pole for post top lantern complete all as specified and as directed by. |
| 85 | Dismantling of Unserviceable Pre-stressed concrete poles/ steel poles of any size & shape including necessary excavation and earth work, taking out of embedded portion of poles from concrete after necessary demolition of cement concrete foundation and disposal of same complete all as specified and as directed.Note :Excavation & earth work, returning filling removing of surplus soil and demolition of concrete and disposed of the demolished concrete shall deemed to be included in the unit rate quoted by the tenderer. |
| 86 | Supply,erecting & fixing steel tubular swaged poles complete with cast iron base plate, final taper plug, bolts, nuts & screws as specified type 410 SP - 31 ( 9.00 metres long), complete all as specified and as directed. Note: (i) Earthwork, cement concrete, etc. will be measured and paid separately under relevant items of this schedule. (ii) Excavation & earth work shall only be measured in case location is other than item No.71 above. |
| 87 | Supply onlyLED driver 10 Watt as per sample for out door type LED fitting,complete all as specified and as directed. |
| 88 | All as per item No 73 above, but for LEDdriver 40/45 Watt |
| 89 | All as per item No 73 here-in-before, but for LEDdriver 150 Watt |
| 90 | All as per item No 73 here-in-before, but for LEDdriver 300 Watt |
| 91 | Supply, installation, testing and commissioning of street light timer control panel, frame size suitable for upto6 Kw loadon pole/wall/floor mounting made out of CRCA steel sheet duly powder coated with locking arrangement, including internal wiring complete with bypass arrangements as per manufactures recommendation and design complete all as specified and as directed. |
| 92 | Supply andfix in replacement power contactors 3 pole, 65 Amps,for street light after dismantling existing contactors from panel and connecting new contactors and making connection withincoming and outgoing MCCB/MCB complete all as specified and as directed . |
| SR No | FileName | File Description |
| 1 | Click here to download tender document | Tender Documents |
| 2 | Click here to download tender document | Tender Documents |
| 3 | Click here to download tender document | Tender Documents |
| 4 | Click here to download tender document | Tender Documents |
Copyright © 2026 · All Rights Reserved. Terms of Usage | Privacy Policy
For Tender Information Services Visit : TenderDetail