| 1 | Cleaning the vegetation growth over the boundary for 5m width for execution of the work, collecting, conveying the debris to a far off place etc., complete. |
| 2 | Dismantling barbed wire or flexible wire rope in fencing including making rolls and stacking within 50mtrs lead. |
| 3 | Dismantling and stacking within 50mtrs lead, fencing posts or struts including all earthwork and dismantling of concrete etc. In base of: |
| 4 | Earthwork excavation in hard soil for laying foundation concrete including necessary lead and lift for conveying the excess earth to far away from the monument premises etc., complete. |
| 5 | Laying plain cement concrete using 40mm stone jelly in ratio 1:4:8, properly consolidating, curing etc., complete.(Stone 40mm – 25.91m3, Stone 20mm – 9.57m3 and Sand – 18.73m3 are available at site and Cement 6.776 tonnes will be supplied Departmentally) |
| 6 | Construction of random rubble stone masonry footings/ dwarf wall with new RR stones and cement mortar 1:6, curing etc., complete (Sand – 96.88m3, stone size of 24x24x24cm – 274.36m3 and Bond stone size of 24x24x39cm– 1920.52Nos available at Site and 22.63 tonnes cement will be supplies departmentally) |
| 7 | Construction of dwarf wall above ground level withCoarse Rubble masonry (First sort) with new stones in cement mortar 1:6 curing etc., complete (Sand – 33.87m3,stone size of 24x24x24cm – 127.68m3 and Bond stone size of 24x24x39cm– 738.64 Nos available at site and 7.91 tonnes of cement will be supplied Departmentally) |
| 8 | Providing stone coping above the dwarf wall with similar stone slab of CR stone set properly in cement mortar, curing etc., complete (Flooring stone – 211m2, chisel rod – 211rft, charcoal – 211kgs, Sand – 7.81m3, lime – 5.23m3, Grease – 0.78kgs, Galnut – 7.8kgs, Jaggary – 7.8kgs will be provided by the Department) |
| 9 | Making, supplying and fixing of steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc., as required. In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works (469Rmt x 1.20mt height = 562.80m2) |
| 10 | Pointing the stone joints with lime surki mortar 1:1:1, curing, colour matching etc complete (Surki – 0.67m3, Sand – 0.69m3, Lime – 0.70m3, Grease – 0.14kgs, Galnut – 1.40kgs , jaggary – 1.40kgs will be provided by the department). |
| 11 | Painting the surface with two coats of enamel paint including cost of all materials and labour cost etc., complete. |