| 1 | SECTION-A : SS TUBE LAYING & TESTING Laying, testing and commissioning of SS tubes along with all fittings (ie, unions, reducers, elbows, Tees , front Ferrule, Back Ferrule, NRVetc.) (all free issue items) as per Technical Specification & Typical P & ID for type of CNG station and scope of work including handling, lifting, transportation from Company\"s Stores to CNG Stations. |
| 2 | 1”OD X 0.120” min Wall thk.SS Tube (ReferTS Section III - A) |
| 3 | ¾”OD X 0.095” min Wall thk.SS Tube (ReferTS Section III - A) |
| 4 | ½”OD X 0.083” min Wall thk.SS Tube (ReferTS Section III - A) |
| 5 | Erection rates of following items (ReferTS Section III - A) |
| 6 | Ball Valves ¾” Size |
| 7 | Ball Valves ½” Size(2 way/3 way) |
| 8 | Ferrule Fittings ¾” (if to be changed) |
| 9 | Ferrule Fittings ½” (if to be changed) |
| 10 | Dismantaling of SS tubes along with all fittings (ie, unions, reducers, elbows, Tees , front Ferrule, Back Ferrule, NRV, Valvesetc.)from the existing CNG stationas per Instruction from Engineer In-Charge and scope of work including handling, lifting, transportation and submiting to Company\"s Stores from CNG site. |
| 11 | SS 316 tube of 3/4\" OD/ 1/2\" OD/ SS 304 tube of 1/2\" OD |
| 12 | Supply, laying, testing and commissioning of SS 304 Tubes along with isolation valves, reducers & fittings etc.as per Technical Specification, Typical schematic drg. for Ins. air line of CNG station and scope of workincluding handling, storage,lifting, transportation upto CNG stations. |
| 13 | ½”OD X 0.035” min Wall thk.SS Tube (ReferTS Section III - A) |
| 14 | SS Ball Valves ½” Size |
| 15 | Reducer ½” x 1/4\" Size |
| 16 | Euqal Tee ½\" Size |
| 17 | SECTION-B (i) : ERECTION OF MECH. EQUIPMENT Handling (including lifting and transportation from Company\"s store toCNG stations)and erecting in position, the following equipmenteither on the foundation at Ground level or on roof at 3.5 m above ground level.Contractor\"s scope shall include supply of all material and accessories including but not limited to any fixtures, clamps, gasket, nut bolts, etc. |
| 18 | Cascade 3000 L water capacity. Erection at + 3.5 M level (Refer TS Section III - B) for (0 -50) Km |
| 19 | Cascade 3000 L water capacity. Erection at + 3.5 M level (Refer TS Section III - B) for (51-100) Km |
| 20 | Cascade 3000 L water capacity. Erection at + 3.5 M level (Refer TS Section III - B) for (101-150) Km |
| 21 | Cascade 3000 L water capacity. Erection at + 3.5 M level (Refer TS Section III - B) for (151-200) Km |
| 22 | SECTION-B (ii) :UNLOADING , SHIFITNG & LOADING OF MECHANICAL EQUIPMENT IN STATION PREMISE (CASCADE)Unloading from existing position (including Compressed natural Gas venting from cascade if necessary) at Ground level or on roof at 3.5 m above ground level, lifting & erecting onfoundation atground level in the same CNG stations. Again the same cascade is to be shifted to new foundationwithin the same CNG station. Contractor\"s scope shall include supply of all material and accessories including but not limited to any fixtures, clamps, gasket, nut bolts, etc. |
| 23 | Cascade 3000 WLcapacity. (ReferTS Section III - B) |
| 24 | SECTION-B (iii) : SHIFTINGOF MECHANICAL EQUIPMENT IN STATION PREMISE (CASCADE/ BOOSTER COMPRESSOR)Lifting of Cascade / Booster Compressor (including accessories if applicable) from existing position from ground level and shifting & erecting in the same CNG stationsonfoundation atground level or on roof at 3.5 m above ground level (in case of Cascade if required) .Contractor\"s scope shall include supply of all material and accessories including but not limited to any fixtures, clamps, gasket, nut bolts, etc. |
| 25 | 3000 WL Cascade/ Booster Compressor with accessories. Lifting & Erection at ground /3.5 m level (ReferTS Section III - B) |
| 26 | SECTION-B (iv) :UNLOADING, TRANSPORTAION & LOADING OF BOOSTER COMPRESSORUnloading from existing position (including dismantaling of connection, packaging ofbooster Compressor package), handling including lifting and transportation from CNG stations to Company\"s store / erecting on civil foundation at or above ground level in other CNG station site if necessary. Contractor\"s scope shall include supply of all material and accessories including but not limited to any fixtures, clamps, wire rope, gasket, nut bolts, etc. |
| 27 | 450 SCMH Hydraulic Booster Compressor (Refer TS Section III - B)- (0-50Km) |
| 28 | 450 SCMH Hydraulic Booster Compressor (Refer TS Section III - B)- (51-100Km) |
| 29 | SECTION - C : SUPPLY, ERECTION & COMMISSIONING OF MISCELLANEOUS ITEMSupply, erection & commissioning of following miscellaneous items as per technical specification and at locations (within the stations) as directed by EIC. |
| 30 | Water cooler (ReferTS Section III - C) |
| 31 | Fire fighting Equipments (ReferTS Section III - C) |
| 32 | DCP -9 Kg |
| 33 | DCP -75 Kg |
| 34 | CO2 – 4.5 Kg |
| 35 | Sand Bucket Set (6 Nos. on each strand) |