| 1 | Clearing and grubbing road land including uprooting vegetation, grass, bushes, shrubs, saplings and trees of girth up to 300 mm, removal of existing stumps of trees dead or cut earlier stacking serviceable material for use or auction within the road land & disposal of all unserviceable material including removal top 150mm thick organic soil away from the road land as under Clause no. 201, specification for Road & Bridge work of MORT&H (5th revision) including full compensation all operations, all inclusive costs, contigencies, incidentals involved for finished defect free item of work complete as per specification and direction of the Engineer-in-charge |
| 2 | Excavation for road works in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers ,trimming buttom and side slopes inaccordance with requirements of lines ,grades,and cross sections ,transporting to the embankment location within all lifts and leads upto 1000 mtr. as per Clause 301 of MoRT&H Specifications for Road & Bridge works (5th Revision)and as per direction of Engineer-in-Charge. |
| 3 | Scarifying the existing bituminous road surface to a depth of 50mm. and disposal of scarified materials with in all leads and lifts and lead upto 1000 mtr. etc. complete as per specification and direction of Engineer-in-charge |
| 4 | Reworking the scarified Bituminous surface suitably after supplementing the base materials with sand and compacting the finished surface as per technical specification and as per clause 501.8.3.2 of MORT&H specification for Road & Bridge work (5th Revision) |
| 5 | Loosening, leveling and compacting original ground supporting the embankment to facilitate placement of first layer of embankment, scarified to a depth of 150mm. mixed with water to OMC and then compacted by rolling so as to achieve minimum dry density as given in table 300-2 for embankment construction and clause 305 of MORT&H specification for Road & Bridge works(5th Revision) |
| 6 | Construction of embankment with approved materials deposited at site obtaining from road-way cutting and other structures with all lifts and lead graded and compacted to meet requirement as per approved drawing and technical specifications as per Section 900 and Clause 305 of MoRT&H Specification for Road & Bridge works (5th Revision) and as per direction of Engineer-in-Charge. |
| 7 | Construction of embankment with approved materials obtained from borrow pit and other structures with all lifts and lead graded and compacted to meet requirement as per approved drawing and technical specifications as per Section 900 and Clause 305 of MoRT&H Specification for Road & Bridge works (5th Revision) and as per direction of Engineer-in-Charge. |
| 8 | Providing compacted Sub-base shoulder with granular materials by using moorum and sand admixure (75:25)of approved quality and satisfying the required P.I. value as per approved drawing and technical specifications as per Section 900 and Clause 407of MoRT&H Specifications for Road & Bridge works (5th Revision) and as per direction of Engineer-in-Charge |
| 9 | Construction of granular sub-base by providing close graded Granular sub-base Grading-VI materials including all cost of materials with cost of all labour, T&P etc. as per table 400-2, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density complete as per Clause 401 of MORT&H Specification for Road & Bridge works ( 5th Revision). |
| 10 | Providing, laying, spreading and compacting graded stone aggregate to Wet mix macadam specificationincluding all cost, conveyance of materials with cost of all labour, T&P etc. including premixing the material with water at OMC in mechanical mix plant, carriage of mixed material by tipper to site, laying in uniform layers with paver in sub-base/base course on well prepared surface and compacting with vibratory roller to achieve the desired density as per clause 406 of MORT&H specification for Road and Bridge works(5th Revision). |
| 11 | Providing and applying primer coat with bitumen emulsion using emulsion pressure distributor y @ 0.6kg. per sqm.on prepared surface of granular base cleared busing mechanical broom as per Clause 502 of MORT&H Specification for Road & Bridge works (5th Revision.) |
| 12 | Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor @ 0.2kg. per sqm.on prepared surface of granular surface cleaned with mechanical broom as per Clause 503 of MORT&H Specification for Road & Bridge works (5th Revision.) |
| 13 | Providing & laying 50 mm thick av. compacted Bituminous Macadam (Grading-II) using VG-30 Bitumen with Hot Mix Plant 100-120 TPH using crusher broken hard granite aggregates of specified grading premixed with bituminous binder @ 3.3 % by weight of total mix and filler, transporting the hot mix to works site, lying with Hydrostatic Paver Finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled vibratory and tandem rollers to achieve the desired compacting as per Clause No. 504 and section 900 of specifications for Road and Bridge works of MORT&H (5thRevision) &including cost of all materials, labour, T&P,taxes, royalty etc complete in all respect and as per direction of the Engineer-in-charge. |
| 14 | Providing and laying 25 mm thick av. compacted Semi Dence Bituminous Concrete (Grading-II) using VG-30 grade Bitumen with Hot Mix Plant 100-120 TPH using crusher broken hard granite aggregates of specified grading, premixed with bituminous binder @ 5.0 per cent of mix and filler, transporting the hot mix 100-120 TPH to work site, laying with a hydrostatic paverfinisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per clause No.501, 508 and section 900 of specifications for Road and Bridge works of Ministry of Road Transport & Highways (5th Revision) & including cost of all materials, labour, T&P, taxes, royalty etc complete in all respect and as per direction of the Engineer-in-charge. |
| 15 | Dismantling of Rubble stone masonry in cement mortar including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material with all lifts and lead of 1000 meters etc. complete as per specification and direction of Engineer in charge |
| 16 | Dismantling of Cement Concrete Grade M-15 and M-20 including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material with all lifts and lead of 1000 meters etc. complete as per specification and direction of Engineer in charge |
| 17 | Removing all type of Hume Pipes and stacking within a lead of 1000m including earth work and dismantlling of maosnry works including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material with all lifts etc. complete as per specification and direction of Engineer in charge |
| 18 | Earth work in excavation of foundation of structure as per drawing upto the required depth including dressing, levelling within 50 mtr. initial leads and 1.5m. initial lifts etc, complete as per specification and direction of the Engineer-in–charge |
| 19 | Filling foundation with good quality river sand including watering, levellling, curing with cost, conveyance, royalty, taxes of all materials, labour with T&P required for the work etc complete as per specification and direction of the Engineer-in-charge |
| 20 | PCC M-15 Grade using 40mm and down grade size crushed stone aggregates mixed by concrete mixer, laying in layers and compacting by vibrator & all leads and lifts including frame works including cost, conveyance of all materials, cost of all labour, T&P, cost of all materials etc. complete as per direction and specification of Engineer-in-charge |
| 21 | In Levelling course |
| 22 | In substructure and CD work |
| 23 | RCC M-20 Grade using 20mm and down grade size crushed stone aggregates mixed by concrete mixer, laying in layers and compacting by vibrator with all leads and lifts and frame works including cost, conveyance of all materials, cost of all labour, T&P, cost of all materials etc. complete as per direction and specification of Engineer-in-charge |
| 24 | (a)Drain base slab |
| 25 | (b) Drain wall |
| 26 | (c)Drain cover slab |
| 27 | RCC M-25 Grade using 20mm and down grade size crushed stone aggregates mixed by concrete mixer, laying in layers and compacting by vibrator & all leads and lifts including frame works including cost, conveyance of all materials, cost of all labour, T&P, cost of all materials etc. complete as per direction and specification of Engineer-in-charge |
| 28 | Foundation |
| 29 | In substructure |
| 30 | Providing Fe-500 HYSD reinforcement (SAIL/ RINL/TATA/JINDAL STEEL/ SHYAM STEEL) for RCC works including bending, binding & placing in position as per specification of Drawing & design including cost, conveyance of all materials, all labour and T&P etc. complete as per the specification and direction of the Engineer-in-charge. |
| 31 | Providing and laying of metal spall backing in the rear side of abutment and wing wall using 5cm sizie hard granite metal to a thickness not less than 600mm with smaller size towards the soil and bigger size towards the wall and provding the entire surface etc complete as per specification and direction of Engineer in charge |
| 32 | Filling Foundation & plinth with excavated earth including all cost, conveyance, T&P, labour required for the work etc. complete as per drawing & technical specifications for Road & Bridge works MoRTH (5th revision) and as per direction of the Engineer in charge |
| 33 | Gravel backing to apron and revetment below slope pitching etc. complete including cost, conveyance, royalty, taxes of materials, labour, T&P required for the work etc. complete as per direction of the Engineer-in-charge |
| 34 | Rough stone dry packing in aprons and revetments, stone pitching in slopes and in apron etc with hard stone of size 30 cm and above and weighing not less than 40Kg as per approved drawing and Section 900, 1000 & 2500 of specifications for road and bridge works of Ministry of Road Transport & Highways (5th Revision) & including cost of all materials, labour, T&P, taxes, royalty etc complete in all respect and as per direction of the Engineer-in-charge. |
| 35 | Rough stone dry packing in aprons and revetments, stone pitching in slopes and apron (Reuse from dismantled items) etc with hard stone of size 30 cm not less than 40Kg as per approved drawing and Section 900, 1000 & 2500 of specifications for road and bridge works of Ministry of Road Transport & Highways (5th Revision) & including cost of all materials, labour, T&P, taxes, royalty etc complete in all respect and as per direction of the Engineer-in-charge. |
| 36 | Providing weep holes in Plain/ reinforced concrete abutment, wing wall/ return wall with 100mm dia A.C.Pipe, extending through the full width of the structure with slope of 1V:20H Complete as per drawing and Technical specifications etc. complete with cost, conveyance, taxes, royalties of all materials, cost of all labour,T&P, sundries etc. complete as per specification and direction of the Engineer-in-charge |
| 37 | Finishing wall surface with two coat of Weather Coat over a coat of primer of approved quality, make and shade to give an even surface including the cost of all materials, labour, conveyance, taxes, loading, unloading, scaffolding, T&P, etc. all complete as per the direction of Engineer-in-charge |
| 38 | Providing and laying Filter media with stone crushed aggregate of 45mm size satisfying the requirements laid down in clause 2504.2.2 of MORTH specification to a thickness of not less than 600mm with smaller size towards the soil and bigger size towards the wall and provided over the entire surfacee behind abutment, wing wall and return wall to the full height compacted to a firm condition complete as per drawing and Technical specification |
| 39 | Providing, laying and fixing in position Reinforced Cement concrete 1000mm dia NP4 hume pipes for culverts on first class bedding of granular materials including pointing ends fixing collars with cement mortar 1:3 for finished item of work as per Section 1000 & 2900 of specifications for road and bridge works of Ministry of Road Transport & Highways (5th Revision) & including cost of all materials, labour, T&P, taxes, royalty etc complete in all respect and as per direction of the Engineer-in-charge. |
| 40 | Providing and laying of hot applied thermoplastic compound 2.5mm thick including reflect rising glass beads @ 250gms per sqm area thickness of 2.5mm is exclusive of surface applied glass beads as per IRC-35. The finished surface to be level, uniform and free from streaks and holes etc complete as per specification and direction of Engineer in charge |
| 41 | Providing & fixing RCC M-15 in Hectometer stone, 5th Km. stone and Ordinary Km. stone etc along with reinforcement complete as per drawing as per IRC -25 / 1967 & IRC-8-1980 fixed in position including finishing and ettering, painting and technical specification as per Clause No. 804 & 806 and Section 1000, 1500, 1600, 1700, 2300 of Specification for Road & Bridge works of Ministry of Road Transport & Highways (5th Revision) including cost of all materials, labour, T&P, taxes, royalty etc complete in all respect and as per direction of the Engineer-in-charge.Ordinary Kilometre stone |
| 42 | Providing and fixing of retro-reflectorised cautionary mandatory and informatory sign as per IRC:67 made of high intensity grade sheeting vide Clause No.801.3 of specifications for road and bridge works of Ministry of Road Transport and Highways (5th Revision) fixed over aluminium sheeting, 1.5mm thick supported on a mild steel angle iron post 75mmx75mmx6mm, firmly fixed to the ground by means of properly designed foundation with M-25 grade cement concrete 45cmx45cmx60cm, 60cm below ground level as per approved drawing and including cost of all materials, labour, TandP, taxes, royalty etc complete in all respect and as per direction of the Engineer in charge. |
| 43 | 800mm x 600mm rectanglar |
| 44 | Cautionary sign (900mm triangulaar) |
| 45 | Mandatory sign (600mm Circular) |
| 46 | Chevron sign (600mm x450mm ) |
| 47 | 900 mm high Octagon |
| 48 | Direction and place Identification Signs upto 0.9 sqm. size board - Providing and erecting direction and place identification retro-reflectorised sign as per IRC-67 made of high intensity grade sheeting vide clause 801.3, fixed over aluminum sheeting, 2mm thick with area not exceeding 0.9 sqm. supported on a mild steel single angle iron post 75x75x6 mm firmly fixed to the ground by means of properly designed foundation with M25 grade cement concrete 45x45x60 cm, 60cm below ground level as per approved drawing |
| 49 | Direction and place Identification Signs More 0.9 sqm. size board - Providing and erecting direction and place identification retro-reflectorised sign as per IRC-67 made of high intensity grade sheeting vide clause 801.3, fixed over aluminum sheeting, 2mm thick with area not exceeding 0.9 sqm. supported on a mild steel single angle iron post 75x75x6 mm firmly fixed to the ground by means of properly designed foundation with M25 grade cement concrete 45x45x60 cm, 60cm below ground level as per approved drawing Please Enable Macros to View BoQ information |