| 1 | S&F single pole and neutralsheet metal enclosure with a two pin and earth plug and socket complete with one single pole 20 ampsMCB complete all as spec ified and directed by Engineer-In-Charge. |
| 2 | M&L for submain wiring with 2X4.0 SQMM+1X4 SQMM Earth Wire single core PVC insulated FRLSHsheathed copper cableconnecting to common earth dolly in and including heavy duty PVC Casing and Caping with all accessories complete all as specified and directed. |
| 3 | S&F VTPN 4 way double door prewired distribution board TPN-DPX 125 MCCB including one No MCCB 100 Amps, 25 kA, 4 pole as incomer and suitable SPN/TP MCBs as outgoing double door type sheet metal enclosure 415V with 200 Amps rated standard busbar of suitable size plate and common neutral link without MCBs with blank plate suitable for 4 way completeall as specified and all as directed by Engineer-in-Charge.Note : Rates of MCCB and MCB SPN/SP/TP shall deemed to be included in the quoted rates. |
| 4 | Supplying transporting to site, erecting and fixingin position, steel tubularswaged and weldedHT poles of under mentioned height and type 410 SP 55, IS 2713 maked with mild steelbase of 11 mtrs height ( Fillet welded to poles), pole cap/ finialtaper plug, bolts, mnuts, wahsers etc, including painting on the outsidewith two coats of aluminium paint over a coat of red oxide primeron exposed surfaces and black bituminous paint on steelsurface embeded in concrete and painting03 nos band/ strips with fluorescent, PO box red synthetic enamel paint (30 cm wide each) at a distance of 30 cm from plinthblock and numbering of poles, complete all as specifiedand directed by Engineer-in-Charge. |
| 5 | M&L for cross arms bracings supports, clamps and back plates fabricated from structural steel section including nuts bolts, washers, welding bending cold or hot, drilling holes for boltsin anyshape or sizeas indicated or directed and inclusive of one primer coat one under coat and one finishing coat of paint etc complete all as specifiedand directed by Engineer-in-Charge. |
| 6 | Supplying installing, testing and commissioning of air break, gang operated, triple pole switch, outdoor, vertical mounting type of capacity 400 amps, ISI marked, mechanically operated on insulators and frame work with operating mechanism workedfrom ground lwvel, with locking arrange4ments including 65mm pad lockes with two keys, complete with fuse mounts, fusecarriers and HT fuse elements having 11000 amp rating suitable for HT KV, 50 Hz Ac supply incl necessary electric connections complete all as specifiedand directed by Engineer-in-Charge. |
| 7 | Excavation in trenches in soft/loose soil not exceeding 1.5 Mtr wide and not exceeding 1.5 Mtr depth for laying of cables/poles or foundation etc and getting out all as specified and directed by Engineer-In-Charge. |
| 8 | Complete all as per iten No 7.00 herein before but exceeding 1.5 mtr deep but not exc 3.0mtr deep all as specified and directed by Engineer-In-Charge. |
| 9 | Removing of surplus excavated soil to a distance not exceeding 50 Mtr from starting point and depositing where directed at a level not exceeding 1.5 Mtr above the starting point all as specified and directed by Engineer-In-Charge. |
| 10 | M&L for PCC 1:4:8 type D-2 using 40mm graded aggregate, mechanically crushed stone in wall, reataining wall any thickness, size, shape,base of pole in polepit and foundation etc all as specified and directed by Engineer-In-Charge. |
| 11 | M&L for cement concrete (1:3:6) type C-1using 20mm graded stone aggregate cast-in-situas mass filling and coping of pole and strut, stayaround the poleetc all as specified and directed. |
| 12 | Returning, filling, including spreading levelling and well ramming in layers not exceeding 25cm apart all as specified and directed by Engineer-In-Charge. |
| 13 | M&L for sand cushoning with a layer of sand 80mm thick before laying of cable and 150mm thick after laying of cable to trenches complete all as specified and directed by Engineer-In-Charge.Note : Compacted Thickness shall be 18 cm considered for measurement and payment purpose. |
| 14 | M&L for sub class `B` bricks for cable protection all as specified and directed by Engineer-In-Charge. |
| 15 | Supply, laying, testing and connecting HT cable under ground XLPE insulated screened PVC bedded, galvanised strip or wire armoured, electricpower cables (heavy duty) 95 Sqmm 3 core 11 KV grade with strandard aluminium conductor as specified and directed laid in trenches/ on poles/ road crossing or passing through existing/new pipe under road crossing, clamping on walletc all as specified and directed by Engineer-In-Charge.. Note:(i) Cost of laying electrical cable through new/existing pipe under road, buildings, railway tracks, highwaysand Aluminium thimbles/lugs are incl in the quoted rates. (ii) All equipments , machinery or toolsif required for laying electrical cable through new/existing pipes are provided by the contractor without any extra cost. |
| 16 | Supply & fix cable end jointing kit for 11KV grade cable for outdoor type termination cold shrinkable joint complete with jointing material and accessories suitable for 3 Core 95 Sqmm core XLPE armoured aluminium conductor cable of size 95 Sqmm complete all as specified and directed. |
| 17 | Supply, installation, testing and commissioning transformer of capacity 400 KVAstep down , outdoordouble wound with copperwindingcomplete filled with oil with standard fittings, HT 11 /0.433 KV, 3phase50Hz AC oil innersed with IS :335 ISI mark filtered & dehydrated transformer oil with ONAN type cooling with external cooling tubes/radiators having nolaod voltage ratio 11/0.433KV (corresponding to princial tapping) delta connection on primery side (HV connection) Star connection on secondary side(Secondary outgoing) inaccordance with vector group symbol (DYN-11) confirming to IS :1180 Part-I (2021) EEL-2 as per GOI Gazette Notification No CG-DL-E-08042021-226437 dt 8th Apr 2021 and having off circuit tap changer in steps of 2.5% on HV side to take care ofvoltage from (+)7.5%to (-7.5%) to give output on 433V secondary sideand including initial oil filling to approprite level ,control cable and following standard fittings complete all asspecified and directed including following(a)Oil conservator with oil filling hole cap and drain plug(b)01 No prismatic oil level gauge mounted on conservator wall with first fill of charge up to maximum level(c) Silica gel dehydration breather with oil seal and first fill of charge(d)Pressure release valve with automatic resetting arrangement after relaese of pressure-01 set(e)Adequate number of thermometer pocket including one thermometer (f) Top oil filter valve(g) Botom oil filter cum drain valve(h) Rating diagram and terminal markingplate(i) Earthing terminal 04 Nos (j) Lifting lug - 02 set(k)Jacking pads 01 Set(l) Under carriaige with 04 Nos plain roller(m) Air release plug on main transformer tank |
| 18 | (n) Adequate No of cooling radiatores (o) 100mm dial type oil tramperature indicator with maximumread pointer and reseting device(p) Air insulated cable box on HV and LV side(q) Buchholz Relay (having Contacts for Alam & Trip)(r)OTI (Heving Contacts for Alam & Trip)(s) WTI (having Contacts for Alam & Trip)(t)Marshalling Box (Having TTB Only)Note : (i) Routine test shall be carried out as per IS 1180. (ii) Pre-dispatch inspection at OEM factory premises shall be carried out by Rep of Accepting officer.(iii) Prior to manufacturethe contractor shall get the general errangement , drawing and design details of the transformer approved from GE(iv) After installation of Transformer at site, the pre-commissioning test shall be carried out by SEI/EI/ESO/Rep of Accepting Offr, cost of all tests such as factory test, pre commissioning tests are deemed to be included in quoted rates. (v) Necessary foundation for the transformer shall be as per OEM recommendations and cost of the same shall deemed to be included in the quoted rates |
| 19 | Supply, installation, commissioning and testingof LTPaneloutdoor type factory made out of CRCAsheet 3.15 mm thick dust & vermin proof , frontand rear openingshutters having locking arrangementtotally enclosed weather proof, antirusted powder coated including aluminium Bus Barof 800 Ampsrating of suitable length, 440 volts, 3 Phase 4 wire50 Hz mountedon suitable type ofinsulators. complete withbottom removable gland plates, as required, all internalconnection wiring bymin. 2.5 Sqmm. copper wires, Panel shall be comprising ofseperate chambers / modules / compartment to accomodate incomer MCCB, outgoing MCCB andinstrument chamber comprise of digital Ammeter & voltmeter flush mounted, selector switches, RYB indicator ,CT\"s,etc complete mounted on suitable size of MS angle framestandof minimum 450 cmheight from ground l;evelinclPCCand earhwork required to fix the stand , The panel board shall be comprising of the following :-(a) Incommer - MCCB 4 POLE 415 V ,500 A (50 kA)- 01 NosOutgoing :-(a)MCCB 4 POLE 415 V100 A (25 kA)- 06Nos(b ) MCCB 4 POLE 415 V63 A (25 kA) - 03 Nos(c)Blank chamber - 01 Nos with din rail sutable for fixing04 Nos TP/TPN MCBs(d) Digital ammeter 0-500 A flush type square with selector switch & CTs -01 No(e) Digital voltmeter 0-500 V flush type square with selectorswitch-01 No |
| 20 | Supply,andfixingbus bar chamber 4 Wayoutdoor type factory made out of CRCA sheet dust & vermin proof , frontopeningdoor having locking arrangementtotally enclosed weather proof, antirusted powder coatedpaintedincludingaluminium Bus Bar of 1000 Amps rating bus size 45 cmlong x 50mm wide x 15mm thick, 440 volts, 3 Phase 4 wire having suitable gap to connect the cables of size 95 Sqmm 3.5 coreand bus mountedon suitable type ofinsulators incl coloured insulating sleeve on each complete withbottom removable gland plates for inccomming and out going cables,bus chamber mounted onMS angle stand made of MS angle 50mm x 50 mm x 5 mm and should having minimium 45 Cm gap below bus chamber incl necessaryPCC foundation work complete all as specified and directed. |
| 21 | M & L for Earthing complete with galvanised steel earth plate electrode 60×60cm.× 6mm thick, buried directly in ground (earth pit not less than 2.25 metres deep below ground level) with top edge of the plate not less\"than 1.5 metres below normal ground level, connected to galvanisedusing galvanised iron strip 32×6mm dia by means of bolts, nuts, check nuts and washers of galvanised iron or steel all as shown in electrical plate No. 3 connected to earthing test point all as specified or indicated including testing on completion complete all as specified and directed. |
| 22 | Supply, laying and testing cable XLPE insulated, armoured heavy duty electric cable with aluminium conductor, 1100 volts grade, cross-sectional area 185 sq mm 3½ corelaid in trenches/ on poles/ road crossing or passing through existing/new pipe under road crossing, clamping on walletc. Note:(i) Cost of laying electrical cable through new/existing pipe under road, buildings, railway tracks, highwaysand Aluminium thimbles/lugs are incl in the quoted rates. (ii) All equipments , machinery or toolsif required for laying electrical cable through new/existing pipes are provided by the contractor without any extra cost.complete all as specified and directed by Engr -in- charge. |
| 23 | Supply, laying, testing and connectingcable under ground XLPE insulated screened PVC bedded, galvanised strip or wire armoured, electricpower cables (heavy duty) with 1100 Volts grade with starndedard aluminium conductor inclusive connected with thimbles, nutt bolt by crimping tool etc complete of size 70 sq mm 3.5 core laid in trenches/ on poles/ road crossing or passing through existing/new pipe under road crossing, clamping on walletc. Note:(i) Cost of laying electrical cable through new/existing pipe under road, buildings, railway tracks, highwaysand Aluminium thimbles/lugs are incl in the quoted rates. (ii) All equipments , machinery or toolsif required for laying electrical cable through new/existing pipes are provided by the contractor without any extra cost. |
| 24 | Supply, laying, testing and connectingcable under ground XLPE insulated screened PVC bedded, galvanised strip or wire armoured, electricpower cables (heavy duty) with 1100 Volts grade with starndedard aluminium conductor inclusive connected with thimbles, nutt bolt by crimping tool etc complete of size 50 sq mm 3.5 corelaid in trenches/ on poles/ road crossing or passing through existing/new pipe under road crossing, clamping on walletc. Note:(i) Cost of laying electrical cable through new/existing pipe under road, buildings, railway tracks, highwaysand Aluminium thimbles/lugs are incl in the quoted rates. (ii) All equipments , machinery or toolsif required for laying electrical cable through new/existing pipes are provided by the contractor without any extra cost. |
| 25 | Supply, laying, testing and connectingcable under ground XLPE insulated screened PVC bedded, galvanised strip or wire armoured, electricpower cables ( heavy duty) with 1100 Volts grade with starndedard aluminium conductor inclusive connected with thimbles, nutt bolt by crimping tool etc complete of size 35 sq mm 3.5 corelaid in trenches/ on poles/ road crossing or passing through existing/new pipe under road crossing, clamping on walletc. Note:(i) Cost of laying electrical cable through new/existing pipe under road, buildings, railway tracks, highwaysand Aluminium thimbles/lugs are incl in the quoted rates. (ii) All equipments , machinery or toolsif required for laying electrical cable through new/existing pipes are provided by the contractor without any extra cost. |
| 26 | Supply, laying, testing and connectingcable under ground XLPE insulated screened PVC bedded, galvanised strip or wire armoured, electricpower cables (heavy duty) with 1100 Volts grade with starndedard aluminium conductor inclusive connected with thimbles, nutt bolt by crimping tool etc complete of size 25 sq mm 4 corelaid in trenches/ on poles/ road crossing or passing through existing/new pipe under road crossing, clamping on walletc. Note:(i) Cost of laying electrical cable through new/existing pipe under road, buildings, railway tracks, highwaysand Aluminium thimbles/lugs are incl in the quoted rates. (ii) All equipments , machinery or toolsif required for laying electrical cable through new/existing pipes are provided by the contractor without any extra cost. |
| 27 | Supply, laying, testing and connectingcable under ground XLPE insulated screened PVC bedded, galvanised strip or wire armoured, electricpower cables (heavy duty) with 1100 Volts grade with starndedard aluminium conductor inclusive connected with thimbles, nutt bolt by crimping tool etc complete of size 16sq mm 4 corelaid in trenches/ on poles/ road crossing or passing through existing/new pipe under road crossing, clamping on walletc. Note:(i) Cost of laying electrical cable through new/existing pipe under road, buildings, railway tracks, highwaysand Aluminium thimbles/lugs are incl in the quoted rates. (ii) All equipments, machinery or toolsif required for laying electrical cable through new/existing pipes are provided by the contractor without any extra cost. |