| 1 | STATION :IBBALURU |
| 2 | SOIL INVESTIGATION (IBBALURU) |
| 3 | (i) Mobilization of tools and equipment from laboratory to site and back for conducting soil investigation work at site. |
| 4 | (ii) Shifting of machine from one bore hole to another including clearing and removing of all vegetation, obstructions, bushes, shrubs etc |
| 5 | (iii) Making 100mm dia bore in any soil strata upto 8m depth or refusal whichever is met earlier, collecting / conducting SPT/UDS/DS at every 1.0m intervals alternatively as follows: |
| 6 | (aa) Gravel Soils |
| 7 | (ab) Soft disintegrated rock |
| 8 | (ac) Hard rock |
| 9 | (iv) Carrying out various laboratory tests of UDS/SPT/DS samples at alternate depths (which ever applicable) |
| 10 | (aa) Sieve analysis |
| 11 | (ab) Atterberg\"s limits |
| 12 | (ac) FMC |
| 13 | (ad) Bulk density |
| 14 | (ae) Specific gravity |
| 15 | (af) Shear test for cohesion and angle of shearing resistance. |
| 16 | (ag) Water absorption of rock |
| 17 | (ah) Compressive strength of rock |
| 18 | (c) Submitting of sub soil investigation report in triplicate giving site plan showing test points sub soil profile, results of field investigations, safe bearing capacity, recommendationsand precautions regarding type of foundations |
| 19 | (d) Electrical Resistance Test : Conductingelectrical conductivity testat 2 (Two) locations&submisson of report. The survey will be gotdone byreputed& specified agency as approved by Departmentagency only |
| 20 | (e) Chemical Properties of soil Sample |
| 21 | CONSULTANCY SERVICES (To be Quoted inPercentage (%) |
| 22 | Preparation of DPR as perpara 3 (a)forScope of Work 2.1 (a)of Annexure - II of Tender Documents. |
| 23 | Building including internal services |
| 24 | Consultancy Services for detailed planning, designing and detailed engineering including preparation of detailed architectural, structural and service drawings, preparation of BOQ, cost estimates, Rate analysis, etc., for the proposed buildings/ structure including internal services as per the following and all as per detailed scope of work mentioned in scope of consultancy at para 2.1 (a) of (1-22), in Annexure IIof Tenderdocuments, including proof checking for structural design from approved third party. |
| 25 | Consultancy Services for detailed planning, designing and detailed engineering, preparation of BOQ, cost estimates, Rate analysis, for special items of work as per the following and all as per the detailed scope of workmentioned in scope of consultancy at para 2.1 (a) of 23 in Annexure IIof Tenderdocuments. |
| 26 | (i) Air Conditioning |
| 27 | (ii) Power Wiring |
| 28 | (iii) Shop Electrics |
| 29 | (iv) UPS Wiring |
| 30 | (v)Lightning protection |
| 31 | (vi) Special Earthing & Equipment |
| 32 | (vii) Telephone& LANconduiting |
| 33 | (viii) Fire alarm |
| 34 | (ix) Fire Fighting |
| 35 | (x) EOT Cranes |
| 36 | (xi) RO Plantand Water Coolers |
| 37 | (xii)Gas suppression system |
| 38 | (xiii) Lift |
| 39 | (xiv) DG Sets |
| 40 | (xv) Flame prooffixtures |
| 41 | (xvi) MotorisedSteelgates |
| 42 | Consultancy Services for detailed planning, designing and detailed engineering,preparation of BOQ, cost estimates, Rate analysis,for external services as per the following and all as perdetailscope of work mentioned in scope of consultancy at para2.1 (a) of 24 in Annexure IIof Tenderdocuments. |
| 43 | (i) Roads, Hardstandingfoot path, Culverts |
| 44 | (ii) External Electrification |
| 45 | (iii) Water Supply System |
| 46 | (iv) External Lighting |
| 47 | (v) Sewage disposal |
| 48 | (vi) Area Drainage & Rain Water Harvesting |
| 49 | (vii) Arboriculture/Land Scaping |
| 50 | (viii) Furniture |
| 51 | STATION : MANDURU |
| 52 | SOIL INVESTIGATION (MANDURU) |
| 53 | (i) Mobilization of tools and equipment from laboratory to site and back for conducting soil investigation work at site. |
| 54 | (ii) Shifting of machine from one bore hole to another including clearing and removing of all vegetation, obstructions, bushes, shrubs etc |
| 55 | (iii) Making 100mm dia bore in any soil strata upto 8m depth or refusal whichever is met earlier, collecting / conducting SPT/UDS/DS at every 1.0m intervals alternatively as follows: |
| 56 | (aa) Gravel Soils |
| 57 | (ab) Soft disintegrated rock |
| 58 | (ac) Hard rock |
| 59 | (iv) Carrying out various laboratory tests of UDS/SPT/DS samples at alternate depths (which ever applicable) |
| 60 | (aa) Sieve analysis |
| 61 | (ab) Atterberg\"s limits |
| 62 | (ac) FMC |
| 63 | (ad) Bulk density |
| 64 | (ae) Specific gravity |
| 65 | (af) Shear test for cohesion and angle of shearing resistance. |
| 66 | (ag) Water absorption of rock |
| 67 | (ah) Compressive strength of rock |
| 68 | (c) Submitting of sub soil investigation report in triplicate giving site plan showing test points sub soil profile, results of field investigations, safe bearing capacity, recommendationsand precautions regarding type of foundations |
| 69 | (d) Electrical Resistance Test : Conductingelectrical conductivity testat 2 (Two) locations&submisson of report. The survey will be gotdone byreputed& specified agency as approved by Departmentagency only |
| 70 | (e) Chemical Properties of soil Sample |
| 71 | CONSULTANCY SERVICES (To be Quoted inPercentage (%) |
| 72 | Preparation of DPR as perpara 3 (a)forScope of Work2.1(b)of Annexure - II of Tender Documents. |
| 73 | Building including internal services |
| 74 | Consultancy Services for detailed planning, designing and detailed engineering including preparation of detailed architectural, structural and service drawings, preparation of BOQ, cost estimates, Rate analysis, etc., for the proposed buildings/ structure including internal services as per the following and all as per detailed scope of work mentioned in scope of consultancy at para 2.1 (b) of (1-14), in Annexure IIof Tenderdocuments, including proof checking for structural design from approved third party. |
| 75 | Consultancy Services for detailed planning, designing and detailed engineering, preparation of BOQ, cost estimates, Rate analysis, for special items of work as per the following and all as per the detailed scope of workmentioned in scope of consultancy at para2.1 (b) of 15 in Annexure IIof Tenderdocuments. |
| 76 | (i) Air Conditioning |
| 77 | (ii) Power Wiring |
| 78 | (iii) Shop Electrics |
| 79 | (iv) UPSwiring |
| 80 | (v)Lightning protection |
| 81 | (vi) Special Earthing & Equipment Earthing |
| 82 | (vii) Telephone& LANconduiting |
| 83 | (viii) Fire alarm |
| 84 | (ix) Fire Fighting |
| 85 | (x) EOT Cranes |
| 86 | (xi) RO Plantand Water Coolers |
| 87 | (xii)Gas suppression system |
| 88 | (xiii) Lift |
| 89 | (xiv) DG Sets |
| 90 | (xv) Flame prooffixtures |
| 91 | (xvi) MotorisedSteelgates |
| 92 | Consultancy Services for detailed planning, designing and detailed engineering,preparation of BOQ, cost estimates, Rate analysis,for external services as per the following and all as perdetailscope of work mentioned in scope of consultancy at para2.1 (b) of 16 in Annexure IIof Tenderdocuments. |
| 93 | (i) Roads, Hardstandingfoot path, Culverts |
| 94 | (ii) External Electrification |
| 95 | (iii) Water Supply System |
| 96 | (iv) External Lighting |
| 97 | (v) Sewage disposal |
| 98 | (vi) Area Drainage & Rain Water Harvesting |
| 99 | (vii) Arboriculture/Land Scaping |
| 100 | (viii) Furniture |