| 1 | Supply, Installation, Testing & Commissioning ofAir Cooled type outdoor units ofVRF system having hermetically sealed inverter scroll/twin rotary compressor, condenser coil fabricated from Seamless Copper tube & Plate type Al. Fins of Multi Row, Axial Flow, top discharge throw condenser fan, Condenser fan - motor unit, all system controls-safety. The system should have flexibility to handle total 280 Rmt of ref. piping. ODU shall be placed on structure with heavy duty anti vibrational pad to protect the system from any kind of unwanted vibration.The system shall have minmum COP of 3.7 at ARI condition as per CPWD guidelines. Each Outdoor units with High Pressure switch, Fan driver overload protector, Over current relay, Inverter Overload Protector & Fusible Plug. The unit shall be suitable for 415 ± 10 % volts, 50 Hz, 3 phase AC supply, and IP protection will be suitable for outdoor installation. The VRF System shall have green ref. gas only- R410A/ R407 |
| 2 | 10 HP |
| 3 | Indoor Units Supply, Installation, Testing & Commissioning of Indoor units address setting and capacity as mentioned below. Multi speedmotor,coil sectionwith DXcoil, outer cabinet, drain pan mechanism insulation, pipe connections, clamp metal, washer fixing plate, sealing pads, screws, clamps, washer for hanging bracket & insulation for fitting, fresh air intake connector for cassettesetc. of various capacities as per specifications. Power cabling (3mtr from unit) with conduit from power socket & plug top to indoor is inclusive of price. |
| 4 | Hi-Wall Type Indoor Unit- Capacity - 1.5 TR |
| 5 | VRF Y JOINTS FOR BRANCH DISTRIBUTION REFRIGERENT PIPE JOINTS WITH PRECAST INSULATION |
| 6 | Supply, installation, testing & commissioning of Y shape Branch Distribution Joints for VRF system. ( The quantity shown here is indicative - in case the quantity requirement is differ based on the system selection for the specific product the revised quantity is required to quoted here) |
| 7 | REMOTE CONTROLLER |
| 8 | Supply, installation, testing & commissioning of Cordlesss remotes for VRF indoor units |
| 9 | SITC of VRF Refrigerant Piping: Supply, installation, testing & commissioning of Seamless heavy gauge Copper piping of following size duly insulated with 13 mm/ 19mm thk. Nitrile Rubber Insulation covered with aluminium foil ( As per Specified with K Value of 0.027-0.029 K Cal/Hr.M Deg C at 0-16 Deg C) . Refrigeration piping will have to be taken in the piping rack / Support individually connecting to all indoor units for the respective floors. Even necessary supports, fittings, valves & ref. joints where ever required will be included. The exposed refrigerent insulated piping shall be covered with UV Resistance canvass coating. |
| 10 | 25.4 mm O.D..(with 19 mm insulation ) |
| 11 | 22.2 mm O.D..(with 19 mm insulation ) |
| 12 | 19.05 mm O.D..(with 19 mm insulation ) |
| 13 | 15.88 mm O.D..(with 19 mm insulation ) |
| 14 | 12.7 mm O.D..(with 19 mm insulation ) |
| 15 | 19.1 mm O.D..(with 13 mm insulation ) |
| 16 | 15.9 mm O.D..(with 13 mm insulation ) |
| 17 | 12.7 mm O.D.(with 13mm insulation ) |
| 18 | 9.52 mm O.D.(with 13mm insulation ) |
| 19 | 6.35 mm O.D.(with 13mm insulation ) |
| 20 | Supply, Installation and Testing of rigid UPVC Drain Piping complete with fittings, supports as per specifications and duly insulated with 6 mm thick closed cell nitrile rubber insulation. |
| 21 | 32 mm dia |
| 22 | 25 mm dia |
| 23 | SITC of GI perforated Cable Tray for the refrigerant pipe hanging & Covering |
| 24 | 300 x 50 x 2 mm |
| 25 | 150 x 50 x 1.6 mm |
| 26 | Supply & fixing of control cum transmission wiring of Copper conductor Shielded cable along with PVC conduit / casingfor looping between indoor & outdoor VRF system. |
| 27 | 2 C X 1.5 Sq. mm (Communication cable) |
| 28 | 3 C X 1.5 Sq. mm - PVC insulated & PVC sheathed cable for IDU power connection |
| 29 | Supply, installation, testing & commissioning of require size copper conductor steel armoured power cable with termination to individual Outdoor units.(From Power Panel to VRF ODU) |
| 30 | Civil foundation of VRF ODU |
| 31 | Making wall opening for passage in the wall/glass for ref & drain pipes andcables and making good of the same for all the indoor/ outdoor units. |
| 32 | Decorative Pelmets of required size for fixing of IDUs on wallwith 16 mm thich anti termite laminated board. |
| 33 | Comprehensive AMC of the VRF system for four years after DLP. |
| 34 | Comprehensive AMC 1st Year after DLP |
| 35 | Comprehensive AMC 2ndYear after DLP |
| 36 | Comprehensive AMC 3rd Year after DLP |
| 37 | Comprehensive AMC 4thYear after DLP |