| 1 | Dismantling stone slab flooring laid in cement mortar including stacking of serviceable material and disposal of unserviceable material within 50 metres lead, complete all as specified and as directed. |
| 2 | Taking out existing CC interlocking paver blocks from footpath/ central verge, including removal of rubbish etc., disposal of unserviceable material to the dumping ground, for which payment shall be made separatelyand stacking of serviceable material within 50 metre lead,complete all as specified and as directed. |
| 3 | Taking out existing kerb stones of all types from footpath/ central verge, including removal of mortar etc., disposal of unserviceable material to the dumping ground, for which payment shall be made separately andstacking of serviceable material within 50 metre lead, complete all as specified and as directed. |
| 4 | Earth work in surface excavation not exceeding 30 cm in depth but exceeding 1.5 m in width as well as 10 sqm on plan including getting out and disposal of excavated earth upto 50m and lift upto 1.5 m, for all kinds ofsoil, complete all as specified and as directed. |
| 5 | Supplying and laying for100mm thick broken boulders hardcore of gauge n exc. 63 mm, deposited, spread and levelled in layers n exc. 15 cm thick, watered and rammed to a true surface, complete all as specified and as directed. |
| 6 | Material and Labour for providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - for all work1:3:6 (1 Cement : 3 manufactured sand derived from Recycled Concrete Aggregate (RCA): 6 graded stone aggregate 40 mm nominal size Recycled Aggregate (RA), complete all as specified and as directed. |
| 7 | Material and Labour for centering and shuttering including strutting, propping etc. and removal of form for sub base concrete complete all as specified and as directed. |
| 8 | Material and Labour for chequered precast cement concrete tiles 22 mm thick in footpath & courtyard, jointed with neat cement slurry mixed with pigment to match the shade of tiles, including rubbing and cleaning etc. complete, on 20 mm thick bed of cement mortar 1:4 (1 cement: 4 coarse sand) finished with dark shade pigment using ordinary cement, complete all as specified and as directed. |
| 9 | Supply and Fix factory made chamfered edge 80 mm thick C.C. paver block of M-40 grade with approved colour design and patternin footpath, parks, lawns, drive ways or light traffic parking etc, of required strength, thickness & size / shape, made by table vibratory method using PU mould, laid in required colour & pattern over 50mm thick compacted bed ofsand, compacting and proper embedding / laying of inter locking paver blocks into the sand bedding layer through vibratory compaction by using plate vibrator, filling the joints with sand and cutting of paver blocks as per required size and pattern, finishing and sweeping extra sand, complete all as specified and as directed. |
| 10 | Material and Labour for providing and laying at or near ground level factory made kerb stone of M-25 grade cement concrete in position to the required line, level and curvature, jointed with cement mortar 1:3 (1 cement: 3 coarse sand),including making joints with or without grooves (thickness of joints except at sharp curve shall not to more than 5mm), including making drainage opening wherever required complete etc. all as specified and as directed.Note : length of finished kerb edging shall be measured for payment. Precast C.C. kerb stone shall be approved by Engineer-in-charge. |
| 11 | Supply and Fix Reinforced concrete pipes of dia 200 mm dia, class NP2, laid and jointed complete with collars, completeall as specified and as directed. |
| 12 | Material and Labour for preparation of new concrete surfaces and applying two coats of synthetic enamel paint over a coat of primer of approved brand and manufacture of required colour to give an even shade, complete all as specified and as directed. |
| 13 | Disposal of moorum/building rubbish/ malba/ similar unserviceable, dismantled or waste material by mechanical transport including loading, transporting, unloading to outside MoD land for all lifts, complete as per directions of Engineer-in-charge. Note - item to be applicable in urban areas having directions for restricted hours for movement/ plying of load carrying motor vehicle of 3.5 cum or more. |
| 14 | Excavating holes in any type of soil more than 0.10 cum & upto 0.5 cum including getting out the excavated soil, then returning the soil as required in layers not exceeding 20cm in depth, including consolidating each deposited layer by ramming, watering etc, disposing of surplus excavated soil, as directed within a lead of 50 m and lift upto 1.5 m, complete all as specified and as directed. |
| 15 | Material and Labour for providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :1:2:4 (1 cement : 2 coarse sand (zone-III)including manufactured sand derived from Recycled Concrete Aggregate(RCA) upto 25% : 4 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 25%), complete all as specified and as directed. |
| 16 | Supply and Fix stainless steel ( Grade 304) railing made of Hollow tubes, channels, plates etc., including welding, grinding, buffing, polishing and making curvature (wherever required) and fitting the same with necessary stainless steel nuts and bolts complete, including fixing the railing with necessary accessories & stainless steel dash fasteners , stainless steel bolts etc., of required size, on the top of the floor or the side of waist slab with suitable arrangement as per approval of Engineer-in-charge, (for payment purpose only weight of stainless steel members shall be considered excluding fixing accessories such as nuts, bolts, fasteners etc.), complete all as specified and as directed. |
| 17 | Material and Labour for steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required in gratings, frames, guard bars, ladder, railings, gates and similar works. in gratings, frames, guard bars , conforming to Fe.290. Gde-E-165 etc., complete all as specified and as directed. |
| 18 | Dismantling of existingroad sign boards with all fittingsto dochequered tiles/paver block work as per the scope on any level or in any position and refixing the same sign boardson the same location after completion ofwork including necessary welding and providing holdfast wherever required.The quoted rate includes demolition of post hole concrete and redo the same after positioning grill post.Note: Dismantled signboards to be stored in thelocation as directedby Engn-In-Charge upto completion of repair work of compound wall without any hindrance to the Users. |
| 19 | Material and Labour for forming 12mm thick expansion joints filled with pre-formed bituminous fillerand top 30mm primed andsealed with sealing com pound, Grade ‘A’ for concrete thickness upto 100mm, complete all as specified and as directed. |
| 20 | Dismantlingand stacking within 50 metres lead, in base of T\" or \"L\" iron or pipe fencing posts or struts including all earth work and dismantling of concrete etc., complete all as specified and as directed. |
| 21 | Dismantling barbed wire or flexible wire rope or chain link fencingin fencing including making rolls and stacking within 50 metres lead, complete all as specified and as directed. |
| 22 | Material and Labour for making hole up to 20cm x 20cm for embedding pipes up to 150 mm diameter in any type of masonry and filling with cement concrete 1:3:6 (1 cement : 3 coarse sand: 6 graded stone aggregate 20 mm nominal size) including disposal of malba, complete all as specified and as directed. |
| 23 | Demolishing stone rubble masonrybuilt in cement mortar manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead, complete all as specified and as directed. |
| 24 | Desilting and cleaning of blocked storm water drain/nallah/culvert etc by removal of mud, soil, aggregate and other similar waste material for smooth flowing/functioningof storm water complete all as specified and directed. |
| 25 | Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m for all kinds of soil, complete all as specified and as directed. |
| 26 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - for all work1:4:8 (1 cement : 4 manufactured sand derived from Recycled Concreteggregate (RCA) : 8 graded stone aggregate 40 mm nominal size Recycled Aggregate (RA) aggregate as in foundation filling, etc., complete all as pecified and as directed. |
| 27 | Material and Labour for providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - for all work1:3:6 (1 Cement : 3 manufactured sand derived from Recycled Concrete AggregateRCA)) : 6 graded stone aggregate 20 mm nominal size derived from Recycled Concrete Aggregate (RCA)) as in foundation filling, etc., complete all as specified and as directed. |
| 28 | Material and Labour for providing and laying factory made Precast concrete solid blocks of 200 mm thickness of grade M10 made of C&D waste from approved manufacturer in superstructure above plinth level up to floor V level inCement mortar 1:6 (1 cement : 6 coarse sand), complete all as specified and as directed. |
| 29 | Material and Labour for 15 mm cement plaster on rough side of single or half brick wall finished with a floating coat of neat cement of mix 1:4 (1 cement: 4 fine sand) complete alll as specified and as directed. |
| 30 | Material and Labour for steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level, Thermo-Mechanically Treated bars of grade Fe-500D or more complete all asspecified and as directed. |
| 31 | Material andLabour for providing and fixing up to floor five level precast cement concrete string or lacing courses, cover slab,copings, bed plates, anchor blocks, plain window sills, shelves, louvers, steps, stair cases, etc., including hoisting and setting inposition with cement mortar 1:3 (1 Cement : 3 coarse sand), cost of required Centering in 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) including manufactured sand derived from Recycled Concrete Aggregate (RCA)upto 25% : 3 graded stone aggregate 20mm nominal size Recycled Concrete Aggregate (RCA) upto 25%)) complete all as specified and as directed. |
| 32 | Material and Labour for providing at or near ground level precast cement concrete of 1:1.5:3 (1 Cement: 1.5 coarse sand (zone-III) including manufactured sand derived from Recycled Concrete Aggregate(RCA) upto 25% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 25%)) in kerbs, edgings, cover slab etc. as per approved pattern and setting in position with cement mortar 1:3 (1 Cement : 3 coarse sand), including the cost of required centering, shuttering, complete all as specified and as directed. |
| 33 | Labour only for, Walling of Random Rubble stone masonry, using Bangalore type stone obtained from demolition, un-coursed, well bonded, bedded and solidly hearted, built in CM(1:6), complete all as specified and as directed.Note : Serviceable stones obtained from demolition shall be re-used under this item. |