| 1 | Clearing and grubbing road land including uprooting wild vegetation, grass, bushes, shrubs, saplings and tress, girth up to 300mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, up to a lead of 1000m including removal and disposal of top organic soil not exceeding 150mm in thickness. as per Technical Specification Clause 201.1 |
| 2 | Construction of embankment with approved material obtained from borrow pits with a lift up to 1.5 meter transporting to sites spreading grading to require slope and compaction to meet requirement of table 300.1 & 300.2 with a lead up to 50 meter as per MORD technical specification cause 301.5 MORD specification 301.5(I) S.No. 3.4 |
| 3 | Laying and spreading available soil in the subgrade on a prepared surface ,pulverising,mixingthe spread soil in place with rotavator with 2 percent slaked lime having minimum 70 percent of contents of Cao, grading with motor grader and compacting with smooth whteeled road roller at omc to the desired density to form a layer of improved Sub grade as per technical Specification Clause 403. |
| 4 | Construction of Granular sub-base by providing well graded material, spreading in uniform layers on prepared surface, mixing by mix in place method by Tractor With Rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per Technical Soecification Clause 401 as per Data Book item No. 4.1 (A)-IFor Grading I Material (A mix of 50% 22.4-53 mm hand broken stone ballast, 20% well graded 6.7mm stone grit & 30% Moorum) |
| 5 | Providing, laying, spreading and compacting stone aggregates of specific sizes to Water bound macadam WBM Grading 2 specification including spreading in uniform thickness, hand packing, rolling with three wheel 80-100 kN static roller in stages to proper grade and camber, applying and brooming, crushable screening to fillup the interstices of course aggregate , watering and compacting to the reqiured density as per Technical Specification Clause 405. as per Data Book item No. 4.8-2(A) |
| 6 | Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam Base WBM 3 specification including spreading in uniform thickness, hand packing, rolling with three wheel 80-100 kN static roller in stages to proper grade and camber, applying and brooming, crushable screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 3 as per Technical Specification Clause 405. as per Data Book item No. 4.7-3(A) |
| 7 | Laying Brick Edging layer on prepared sub grade with brick on end edging according to lines, graded and cross section shown on the drawing filling joints with sand and earth, spreading 25mm thick layer of earth over brick soling, watering and rolling the same with 3 wheeled road roller 80-100 kN as per MORD specification clause 412 and as per Data Book item No. 4.18 |
| 8 | Providing and applying primer coat with bitumen emulsion (SS-1) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.70 kg/sqm using mechanical means as per Technical Specification Clause 502. as per Data Book item No. 5.1-(I ) Low porosity |
| 9 | Providing and applying tack coat with RS-1 bitumen using bitumen pressure distributor @ 0.25 to 0.3 kg. per sqm. on the prepared bituminous surface cleaned with Hydraulic broom as per Technical Specification Clause 503. Case (ii) |
| 10 | Providing laying & rolling of open graded premix carpet of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates either using penetration grade bitumen or emulsion to required line ,grade and level to serve as wearing course on a previously prepared base including mixing in a suitable plant ,laying and rolling with a three wheel 80-100 KN static roller capacity finished to required level and grades to be followed by seal coat . Clause 508 |
| 11 | Providing and laying seal coat Type-C sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall using As per Technical Specification Clause 510 |
| 12 | Providing and fixing 350 mm dia hume pipe for crossing including all(chapter 1of si73 and chapter 26 new item a |
| 13 | Earth work in excavation for foundation of structures up to 3m depth as per drawing and technical specification clause 305. 1 including setting out construction of shoring and bracing removal of stumps and other deleterious materials and disposal up to a lead of 50m. dressing of sides and bottom and backfilling in trenches with excavated suitable material as per MORD Specification No. 300 as Per Data Book item No. 9.1 |
| 14 | Sand filling in plinth including supply of necessary quantity of sand from a distance not exceeding 8km (5 miles) from the side of work & including watering ,dressing etc. Rate to include cost of all materials,labour and tools & plants,etc. required for proper completion of work |
| 15 | Cement concrete with 4cm (1/2\"\") gauge approved stone ballast, approved coarse sand. cement in the proportion 8:4:1 including supply of all materials, labour and tools and plants etc. required for proper completion of the work. |
| 16 | Class-150 brick work in 1:4 cement & fine sand mortar in foundation and plinth I/c all complete as chapter 6 as S.I. No. 305 |
| 17 | R.C.C. work in 1:1½:3 cement, coarse sand and 20mm gauge stone grit including all complete for but for slab |
| 18 | M.S. or iron work (Tor or plain bar) in plain work such as R.C.C. /R.B. work I/c all complete as directed by engineer in charge as chapter 10 as SI No. 504 |
| 19 | Plaster 12mm thick with cement, fine sand mortar in proportion of 1:4 in fair side of wall I/c all complete as directed by engineer in charge etc. (chapter 13 as SI no 17.58 (ii)) |
| 20 | P.C.C. work in 1:2:4 cement, coarse sand and 20mm gauge stone grit including all complete work etc as chapter 5 as S.I. No. new item -A |
| 21 | Providing & fixing 100 mm dia P.V.C. soil or vent pipe I/C digging and filling trenches and supply of clamps ,the pipe shall either be fixed parallel to the wall with M.S. clamps or laid in ground to proper slopes I/c all complete as per Sanitary S.I. NO. Chapter no. 19 new item no.-3 Please Enable Macros to View BoQ information |