| 1 | Earth work in correcting internal section of dy/mr. from u/s and d/s from the proposed vrb. |
| 2 | E/W in road diversion including all lead & lift with mannual compaction and dressing etc. As per direction of Engg. In charge. |
| 3 | Earth work back filling including all lead & lift including strengthening bank and compaction required for proper completion of work. Work shall be carried out as drawing provided and as per direction of Engineer-in-charge. |
| 4 | Earth work in excavtion in foundation in ordinary soil including 30m lead & 1.5m lift with back filling and As per direction of Engg. In charge. |
| 5 | Providing & laying C.C. 1:3:6 in foundation with cement coarse sand stone ballast 20-40mm gauge i/c proper curing and compaction etc. And i/c cost of all material, labour and T&P etc. For proper completion of work. |
| 6 | Providing & laying C.C. 1:1:2 in Box cell Structure with cement, coarse sand, stone ballast 20 mm gauge. i/c proper curing and compaction etc. And i/c cost of all material, labour and T&P etc. For proper completion of work. |
| 7 | Centering & shuttering for CC& R.C.C. i/c cost of all material, labour and T&P etc. For completion of work. |
| 8 | Providing & laying R.C.C. 1:1.5:3 with cement, coarse sand & stone grit 20mm gauge i/c proper curing and compaction etc. And i/c cost of all material, labour and T&P etc. For proper completion of work. |
| 9 | Providing Steel reinforcement including cutting, bending, binding & placing in position. i/c cost of all material, labour and T&P etc. For proper completion of work.16 mm dia |
| 10 | Providing Steel reinforcement including cutting, bending, binding & placing in position. i/c cost of all material, labour and T&P etc. For proper completion of work.12 mm dia |
| 11 | Providing Steel reinforcement including cutting, bending, binding & placing in position. i/c cost of all material, labour and T&P etc. For proper completion of work.10 mm dia |
| 12 | Providing & fixing 110 mm dia PVC pipe in drainage spout i/c cost of all material, labour and T&P etc. For proper completion of work as per direction of Engg. In charge. |
| 13 | Laying compacted local sand i/c mannual compaction and cost of all material, labour and T&P etc. For proper completion of work. |
| 14 | Earth work in Making sub grade in pitching work including watering compection and prepration of surface where ever applicable for escape of above 30 Cumecs discharge including hard clay, charri bajri upto 5% lead upto 30 meters, lift upto 1.5 meters excluding Mechanical compaction but inclusive of manual compaction and dressing to profiles. |
| 15 | Laying 300 GSM Geo textile as filter above sub grade for boulder pitching including cost of all material, labour and T&P etc required for proper completion of the work. |
| 16 | Providing and laying boulder 20 to 40 kg. with single layer on slope & Bed including cost of all material, labour and T&P etc required for proper completion of the work |
| 17 | Dry Brick on edge Soiling including preparation of sub grade and filling joints with local earth including cost of all labour & materials T&P etc. required for proper completion of the work. |
| 18 | Supply , Fabrication and fixing of mild steel /iron work in Head Regulator Gate including cutting, drilling, welding/ riveting and hinges where necessary and fixing in position including cost of material, labour T&P etc. required for proper completion of work with one coat of red oxide primer (Overall) |
| 19 | cement plaster 1:4 cement and coarse sand including all labour and material T&P etc. |
| 20 | Providing & Fixing of PVC pipe 160 mm dia in 6 kg pressure ISI Mark including cost of all Labour & Materials T&P etc. required for proper completion of the work./Rm. |
| 21 | Providing & Fixing of PVC pipe 110 mm dia 6 kg pressure ISI Mark including cost of all Labour & Materials T&P etc. required for proper completion of the work./Rm. |
| 22 | M-150 class brick work in 1:4 cement mortar with cement coarse sand and brick including cost of all labour & materials T&P etc. required for proper completion of the work |
| 23 | Cement concrete in 1:2:4 in top of Fall with course sand and stone ballast 12-20 mm gauge including cost of all labour & materials T&P etc. required for proper completion of the work |
| 24 | Cement Pointing 1:2 CM with Coarse sand including all Labour & Materials , T&P etc. required for proper completion of work . |
| 25 | Earth work in restoration of canal internal section and bank in all type soil mixed chhary and kanker with in 30 m lead andEarth work in restoration of canal internal section and bank in all type soil mixed chhary and kanker with in 30 m lead and1.50 m lift including refiling of excavated earth, dressing and manual compaction etc. required for proper completion of work as per direction of Engineer-in-charge. |
| 26 | M-150 class brick work on End pitching 1.50 m lift including refiling of excavated earth, dressing and manual compaction etc. required for proper completion of work as per direction of Engineer-in-charge. |
| 27 | Finishing wall with water proof cement paint of approved make and quality paint on new work with two coats to give an even shade. |
| 28 | Painting letters above 8 cm and upto 15cm size complete including supply of all material labour and T&P |
| 29 | Brick on edge lining with 1:3 cement morter laid with 4 mm thick base plaster . |
| 30 | Supply & laying of 200 micron L.D.P.E film over plaster work required for proper completion of work including cost of all materials, labour, T&P etc. |
| 31 | steel reinforcement including cost binding wire, and bending,cutting,binding and placing in position including T&P Please Enable Macros to View BoQ information |