| 1 | Earth work in cutting or in embankment in ordinary soil excavation to be the form of regular pits not exceeding ½ meter (20”) in depth and earth work in enbankment to be in 20cm (8”) layers, including ramming and dressing the surface to required levels and slopes and also including 1.5m (5”) lift and 30m (100’) lead. The earth form cutting to be used in making embankent or to be deposited as spoil banks within 30m (100’) distance as directed by the E/I. (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 2 | Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density,complete as per Technical Specification clause 405. (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 3 | Providing, laying, spreading and compacting of sukrut stone stone aggregates of specific sizes(45-63mm) to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with smooth wheel roller 80-100 kN in stages to proper grade and camber,applying and brooming ,binding materials to fill-up the interstices of coars aggrigate,watering and compacting to the required density Grading-2 as per Technical Specification clause 405 (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 4 | Providing, laying, spreading and compacting of sukrut stone stone aggregates of specific sizes(22.4-53mm) to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with smooth wheel roller 80-100 kN in stages to proper grade and camber,applying and brooming ,binding materials to fill-up the interstices of coars aggrigate,watering and compacting to the required density Grading-3 as per Technical Specification clause 405. (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 5 | Brick edging on both side of road with first class brick 8 cm wide and 12 cm deep laid with mud mortar including all materials, labour T&P etc. complete. (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 6 | Providing and applying primer coat with bitumen emulsion (SS-II) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.70 kg per sqm using mechanical means as per Technical Specification Clause 502. (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 7 | Providing and applying tack coat with Bitumen (VG-10) using bitumen distributor at the rate of 0.30 kg per sqm on the prepared bituminous surface cleaned with Air compresser as per Technical Specification Clause 503 (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 8 | Providing, laying and rolling of open-graded premix carpet of 20 mm thickness composed of 13.2 mm -11.2 mm aggregates using penetration grade bitumen VG-10 to required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant,laying and rolling with three wheel static roller 80-100 KN capacity ,finished to required level and grades to be follwed by seal coat of Type -C as per Technical Specification Clause 508. (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 9 | Providing and laying seal coat sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall using Type C as per Technical Specification Clause 510 (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 10 | Earth work in cutting or in embankment in ordinary soil excavation to be the form of regular pits not exceeding ½ meter (20”) in depth and earth work in enbankment to be in 20cm (8”) layers, including ramming and dressing the surface to required levels and slopes and also including 1.5m (5”) lift and 30m (100’) lead. The earth form cutting to be used in making embankent or to be deposited as spoil banks within 30m (100’) distance as directed by the E/I. for Pateri (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 11 | Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000m (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 12 | Construction of granular Sub-base by providing well graded material , spreading in uniform layers with motor grader on prepared surface mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as perTechincal Specification clause 401 (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 13 | Sand Filling in Foundation Trenches as per Drawing & Technical Specification as per Ref. to MORD Spec 305.3.9 (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 14 | Plain cement concrete 1:3:6 mix with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days. (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 15 | RCC Grade M 25 Furnishing and Placing Reinforced/ Prestressed cement concrete in sup-structure as per drawing and Technical Specification (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 16 | Supplying, fitting and placing HYSD bar reinforcement in sub-structure complete as per drawing and technical specifications (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 17 | RCC Grade M-25 Furnishing and Placing Reinforced/ Prestressed cement concrete in super-structure as per drawing and Technical Specification (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 18 | Supplying, fitting and placing HYSD bar reinforcement in super-structure complete as per drawing and technical specifications (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 19 | Providing and laying filter media with granular crushed aggregates as per specification to a thickness of not less than 600 mm with smaller size towards the soil and bigger size towards the wall and providing over the entire surface behind abutment, wing wall, return wall to the full height, compacted to firm condition complete as per drawing and technical specification Clause 1204.3.8 (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 20 | Providing and fixing of drainage spout as per drawing and Technical Specifications Claause 2705 (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 21 | Providing weep holes in brick masonry/ stone masonry plain/ reinforced concrete abutment, wing wall, return wall with 100mm dia AC pipe extending through the full width of the structure slope of 1(V) 20(H) towards drawing face complete as per drawing and technical specification clauses 614, 709, 1204.3.7 (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 22 | Running of 5HP pump for dewatering including arrangement of pump suction and delivery pipes and other accessories at site including cost of POL (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 23 | Cement concrete with 4 cm gauge brick ballast coarse sand and cement in the proportion 8:4:1 including cost of all material, labour etc. complete. SI No-275 (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 24 | Brick work with cement and fine sand mortar in proportion 1:4 including cost of all material, labour etc. complete SI No-305 (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 25 | Struck cement pointing with 1:2 cement and fine sand mortar on both visibule face of end wall in parapet. SI No-574 (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 26 | Providing and laying 350 mm dia N.P-3 H.P. jointing with coller in proper position including cost of cement , jute etc. required for proper completion of work. but excluding cost of collor (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 27 | Providing and laying 6000 mm dia N.P-3 H.P. jointing with coller in proper position including cost of cement , jute etc. required for proper completion of work. but excluding cost of collor (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 28 | C.C. 1:2:4 on parapet as SI No-279b (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 29 | Colour washing two coat as SI No-675 (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 30 | PART BMaintainance cost :- Maintainance cost will be paid year wise as per Government order No. 17/2024/SA.-113/23-1-2024-23-1099/113/2023 Date 16.01.2024 and HQ UPPWD,Lucknow order No. 36890C/RMC/Mul-23-24 Date 17.02.2024 . Maintainance cost will adjusted as per final cost of construction and will be paid accordingly. |
| 31 | 1st year - maintainance cost 0% (including labour material T&P etc. complete as per direction of E/I & also including all taxes Labour cess but excluding GST. |
| 32 | 2nd year - maintainance cost 0.75% (including labour material T&P etc. complete as per direction of E/I & also including all taxes Labour cess but excluding GST. |
| 33 | 3rd year - maintainance cost 1.50% (including labour material T&P etc. complete as per direction of E/I & also including all taxes Labour cess but excluding GST. |
| 34 | 4th year - maintainance cost 2.25% (including labour material T&P etc. complete as per direction of E/I & also including all taxes Labour cess but excluding GST. |
| 35 | 5th year - maintainance cost 3.00% (including labour material T&P etc. complete as per direction of E/I & also including all taxes Labour cess but excluding GST. Please Enable Macros to View BoQ information |