| 1 | based on Ruidp 2023 |
| 2 | Carriage of Materials by mechanical transport including loading, unloading and stacking ::Stone, boulders, gravelly material |
| 3 | Earth work in excavation in foundation, trenches etc. including dressing of sides and ramming of bottoms, including getting out the excavated material, refilling after laying pipe/ foundation and disposal of surplus excavated material at a lead upto 50m suitable site as per direction of Engineer for following depths, below natural ground / Road top level.Depth upto 1.5 m |
| 4 | Providing and laying un-reinforced, plain cement concrete mix in pavement over a prepared sub base with 43 grade cement, coarse and fine aggregate conforming to IS: 383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a batching and mixing plant, transported to site, laid spread, compacted and finished in a continuous operation including provision of contraction, expansion, admixtures as approved, curing compound, finishing to lines and grades complete as per drawing and as per clause 602, 112 of MoRT&H specification including all material, labour, machinery, lighting, guarding and maintenance of diversion for road restoration under sewer line and manhole work including allowances for any additional road restoration beyond the drawings (measurement for payment to be as per standard drawings) to complete the task.cement concrete 1:4:8 |
| 5 | Providing and laying un-reinforced, plain cement concrete mix with Concrete Mixer & vibrator pavement over a prepared sub base with 43 grade cement , coarse and fine aggregate conforming to IS: 383, maximum size of coarse aggregate not exceeding 25 mm, mixed as per approved mix design, laid, spread, compacted and finished in a continuous operation including provision of contraction, expansion, construction and longitudinal joints etc including all material, labour, machinery, lighting, guarding and maintenance of diversion.PCC M-20 |
| 6 | Random rubble stone masonry work in cement mortar with mechanical mixer in foundation (at any level) complete as per drawing and technical specification and as per clause 1000 and 1400 of MoRT&H specification including all scaffolding material, labour, machinery but excluding pointing and plastering.In cement mortar 1:4 (1 cement : 4 coarse sand) |
| 7 | Brick masonry work in cement mortar with mechanical mixer with First class bricks (min. 10.5 Mpa) in foundation (at any level) complete as per drawing and technical specification and as per clause 1000 & 1300 of MoRT&H specification including all scaffolding material, labour, machinery but excluding pointing and plastering.In cement mortar 1:4 (1 cement : 4 coarse sand) |
| 8 | Cement plastering including T&P, scaffolding, material and complete labour, including cost of water, curing, racking of joints etc. with 12 mm cement plaster of mix : including Providing /mixing of synthetic fibers compulsorily complying with IS 16481:2022 of 06 mm/12 mm length to be mixed @ 0.25% by weight of Cement i.e. 125 gms per 50 kg Cement up to 900 gms per cum of Concrete/ mortar1:6 (1 cement : 6 fine/ coarse sand) |
| 9 | Structural steel work riveted, bolted or welded in built up sections, trusses and framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete: Please Enable Macros to View BoQ information |