| 1 | Construction of granular sub-base by providing close graded material, mixing in a mechanical mix plant at OMC, carriage of mixed material to work site, spreading in uniform layer with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401 of MoRTH specification, 4th Revision - by plant mix method - for grading II material. |
| 2 | Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the material with water at OMC in mechanical mix plant carriage of mixed material by tipper to site, laying in uniform layers with paver in sub-base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density - Using vibratory roller. (As per MoRTH specification, 4th Revision) |
| 3 | Providing and applying primer coat with bitumen emulsion on prepared surface of granular base including clearing of road surface and spraying primer at the rate of 0.60 kg/sqm using mechanical means. (As per MoRTH specification, 4th Revision) |
| 4 | Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at the rate of 0.20 kg. per sqm. on the prepared bituminous / granular surface cleaned with mechanical broom. (As per MoRTH specification, 4th Revision) |
| 5 | Providing and laying bituminous macadam with hot mix plant of capacity not less than 40 -60 TPH using crushed aggregates of specified grading premixed with bituminous binder, transported to site, laid over a previously prepared surface with paver finisher to the required grade, level and alignment and rolled as per clauses 501.6 and 507.7 of MoRTH specification, 4th Revision, to achieve the desired compaction. - using grade II metal and bitumen - VG30 |
| 6 | Providing and laying bituminous concrete with HMP of capacity not less than 40 to 60 TPH using crushed aggregates of specified grading, premixed with bituminous binder @ 5.4 to 5.6 percent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per clause 509 of MoRTH specification, 4th Revision, complete in all respects - Using grade-II material.-Bitumen -VG30 |
| 7 | Providing, hoisting and fixing upto plinth level precast reinforced cement concrete for drain cover slab of length varying upto 1.50m of various thickness including the cost of required centering, shuttering and finishing smooth with 6mm cement plaster 1:3 (One cement : 3 fine sand) on all faces of the slab but excluding the cost of reinforcement with 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate of 20mm nominal size) |
| 8 | Steel reinforcement for R.C.C.work including straightening , cutting , bending , placing in position and binding all complete upto plinth level - Thermo -Mechanically treated bars Fe - 500D or more |
| 9 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - all work upto plith level - 1:2:4 (1 cement : 2 fine aggregate : 4 graded stone aggregate 20mm nominal size) |
| 10 | Centring and shuttering including strutting , propping etc. and removal of form work for - retaining walls, return walls, walls (any thickness) including attached pilasters, buttresses, plinth and string courses fillets, kerbs and steps etc. |
| 11 | 6mm cement plaster of mix 1:3 (1 cement : 3 fine aggregate) |