| 1 | Construction of 30000 litre capacity OHT with 12.00m Staging Height @ for Thatchampatti Village in Kodukkampatti Panchayat at Kottampatti Block under JJM 2025-26 R 17.91 Lacs |
| 2 | Earth work excavation in all soils such as red earth ,hard stiff clay soil, stiff black cotton soil, hard redearth,shales, murrams, gravel,hard rock not requiring blasting ete complete.,SS 20 B |
| 3 | First depth of 2m |
| 4 | Second Depth 2m to 3m |
| 5 | Sand filling with clear M sand including cost of sand watering, ramming and consolidation etc. complete as directed by TWAD Board officers |
| 6 | Cement concrete 1:4:8 using 40mm HBGS for leveling course including the cost of mixing concrete, ramming, curing etc. complete as directed by TWAD Board officers (Beyond 1.50 m to 4.50 m) |
| 7 | Refilling in foundation and basement with excavated earth in layer of not more than 15cm thick |
| 8 | RCC M30 using 20mm HBGS excluding cost of reinforcement, centering, shuttering strutting, but including cost of mixing concrete, placing, vibrating with mechanical vibrator, finishing, curing etc. complete as directed by TWAD Board officers |
| 9 | Below 1.5m from GL |
| 10 | Items 0 to 1.5m below GL |
| 11 | 0m to 4.50m above GL |
| 12 | Above 4.50m & upto 7.32m from GL |
| 13 | Above 7.32m & upto 10.98m from GL |
| 14 | Above 10.98m & upto 14.64m from GL |
| 15 | Above 14.64m & upto 18.30m from GL |
| 16 | Supplying and erecting steel centering for sides and soffits including necessary supports and shuttering to the required height for RCC items using MS sheets or suitable size of BG 10 stiffened with welded MS angles of size 25mm x 25mm x 3mm of boarding, laid over Silver Oak joists of size 10cm X 6.5cm space at 10cm c/c and supported by Casurino Props 10cm - 13cm spaced at 75cm c/c etc., complete and as directed by TWAD Board Officers. |
| 17 | Below G.L. items |
| 18 | 0-3.30m Below G.L. |
| 19 | 5.31 m to 6.30mabove G.L. |
| 20 | 8.31 m to 9.30mabove G.L. |
| 21 | 11.30 m to 12.30mabove G.L.(Plane) |
| 22 | Square columns |
| 23 | Square Column Below GL |
| 24 | 0 to 3.30m above G.L. |
| 25 | 3.31 to 4.30m above G.L. |
| 26 | 4.31 to 5.30m above G.L. |
| 27 | 5.31 to 6.30m above G.L. |
| 28 | 6.31 to 7.30m above G.L. |
| 29 | 7.31 to 8.30m above G.L. |
| 30 | 8.31 to 9.30m above G.L. |
| 31 | 9.31 to 10.30m above G.L. |
| 32 | 10.31 to11.30m above G.L. |
| 33 | 11.30to 11.40 m above GL |
| 34 | Curved Surface - upto 3.30m ht |
| 35 | Painting two coats with approved Plastic Emulsion Paint of First quality of approved colour over a Priming Coat |
| 36 | Supplying fabricating and placing in position of HSD steel rods for reinforcement including the cost of steel and binding wire etc. complete and as directed by TWAD Board officers. |
| 37 | Fabrication, supply, delivery and fixing of outside MS ladder . |
| 38 | Providing Hand rails over the Roof slab by using 32 mm GI Pipe with 40mm x 6mm MS Flat and fixied with 12mm dia Fastner Bolt 75mm long and as directed by TWAD Bd officers |
| 39 | Providing and fixing of RCC inner access ladder in M30 . |
| 40 | Providing manhole cover of size 0.60 x 0.60M in RCC 1:1.5:3 with suitable reinforcement and 50x50x6mm MS angle fixed along edges and as directed by TWAD Board officers |
| 41 | Supply,delivery and fixing of pipes and specials for OHT connections |
| 42 | 65 mm GI Pipe |
| 43 | 65mm Coupling |
| 44 | 65mm Elbow |
| 45 | 65mm Gate valve |
| 46 | Laying and joining of GI Pipe including cost and conveyence etc., complete |
| 47 | Earth work excavation of all classes of Soil including cost and conveyence etc., complete (0.60x0.90) |
| 48 | 63 mm dia PVC Pipe |
| 49 | 63 mm dia PVC Elbow |
| 50 | 50mm dia GI Pipe |
| 51 | 50mm dia GI Coupling |
| 52 | 50mm dia GI Elbow |
| 53 | 50mm dia GI Union |
| 54 | 50mm dia GI Gate Valve |
| 55 | 50mm dia GI Flange Set |
| 56 | 50mm dia GI Hex Nipple |
| 57 | Laying and joining of GI Pipe including cost and conveyence etc., complete |
| 58 | Laying and joining of PVC Pipe including cost and conveyence etc., complete (63mm PVC) |
| 59 | Refilling of excavated earth including labour charges etc., complete (0.60x0.90) |
| 60 | GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column \"BB\" for all works in this package} Please Enable Macros to View BoQ information |