| 1 | Construction of labour rest room |
| 2 | Earth work in excavation by mechanical means (Hydraulic excavator ) manual over areas (exceeding 30 cm in depth, 1.5m in width as well as 10 sqm on plan ) including disposal of excavated earth, lead upto 50m and lift upto 1.5 m disposed earth to be levelled and neatly dressed. All kinds of soil |
| 3 | Providing and laying in position cement concrete including curing, compaction etc. complete in specified grade excluding the cost of centering and shuttering - All work up to plinth level. 1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size.) |
| 4 | Random Rubble stone masonry for with hard stone in foundation and plinth in Cement Sand mortar above 30 CM thick wall in: Cement Mortar 1:6 ( 1-Cement : 6-Sand). |
| 5 | Brick work with F.P.S. bricks of class designation 75 in superstructure above plinth level upto floor V level in all shapes and sizes in : Cement mortar 1:6 (1 cement : 6 coarse sand ) |
| 6 | Plaster on new surface on walls in cement sand mortar 1:4 including racking of joints complete fine finish : 20 mm thick |
| 7 | 9.2 Structural steel work riveted, bolted or welded in built up sections, trusses and framed work, including cutting, hoisting (height upto 10 m) , fixing in position and applying a priming coat of approved steel primer all complete:pwd bsr item number 9.2 @ 81 per kg |
| 8 | 10.1 Providing corrugated G.S. sheet roofing including vertical / curved surface fixed with polymer coated J or L hooks, bolts and nuts 8 mm diameter with bitumen and G.I. limpet washers or with G.I. limpet washers filled with white lead and including a coat of approved steel primer and two coats of approved paint on overlapping of sheets complete (upto any pitch in horizontal/ vertical or curved surfaces) excluding the cost of purlins, rafters and trusses and including cutting to size and shape whenever required. 10.1.1 1.00 mm thick with zinc coating not less than 275 gm/m2 Sqm 904.00 (49.60sqm Area) |
| 9 | Bathroom Nirman |
| 10 | Earth work in excavation by mechanical means (Hydraulic excavator ) manual over areas (exceeding 30 cm in depth, 1.5m in width as well as 10 sqm on plan ) including disposal of excavated earth, lead upto 50m and lift upto 1.5 m disposed earth to be levelled and neatly dressed. All kinds of soil |
| 11 | Providing and laying in position cement concrete including curing, compaction etc. complete in specified grade excluding the cost of centering and shuttering - All work up to plinth level. 1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size.) |
| 12 | Random Rubble stone masonry for with hard stone in foundation and plinth in Cement Sand mortar above 30 CM thick wall in: Cement Mortar 1:6 ( 1-Cement : 6-Sand). |
| 13 | Providing and laying damp-proof course with cement concrete grade M-150(1:2:4) Mortar prepared with 1% solution of water-proof compound complete as per specification 75mm thick |
| 14 | Brick work with F.P.S. bricks of class designation 75 in superstructure above plinth level upto floor V level in all shapes and sizes in : Cement mortar 1:6 (1 cement : 6 coarse sand ) |
| 15 | Centering & Shuttering with plywood or steel sheets including strutting, propping bracing both ways with steel props and removal of formwork for upto floor five level for : Suspended floors, roofs, landings, staircases, balconies, girders, cantilevers, bands, coping bed plates, anchor blocks, sills, chhajjas, lintel, beam, plinth beam etc. |
| 16 | Providing and laying in position specified grade of cement concretee for RCC structural elements upto floor five level including curing, compaction, finishing with rendering in cement sand mortar 1:3 (1 cement: 3 coarse sand) and making good the joints and cost of plastizers (if required ) excluding the cost of centering, shuttering and reinforcement for Walls (any thickness) including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. M20 grade Nominal Mix / Design Mix . |
| 17 | Steel Reinforcement: Providing and fabrication reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding ( including cost of binding wire) all complete up to floor five level. (Original producers who manufacture billet directly from iron ores and rolll the bilets to produce steel conforming to IS:1786) Thermo-mechanically Treated bars (Conforming of relevent IS code ) (100 kg per cum of c.c.) |
| 18 | Plaster on new surface on walls in cement sand mortar 1:4 including racking of joints complete fine finish : 20 mm thick |
| 19 | Painting with synthetic enamel paint of approved brand and manufacture to give an even shade: Two or more coats on new work. |
| 20 | Safety Tank |
| 21 | Sanitory Work |
| 22 | Forest Guard Choki |
| 23 | Earth work in excavation by mechanical means (Hydraulic excavator ) manual over areas (exceeding 30 cm in depth, 1.5m in width as well as 10 sqm on plan ) including disposal of excavated earth, lead upto 50m and lift upto 1.5 m disposed earth to be levelled and neatly dressed. All kinds of soil |
| 24 | Providing and laying in position cement concrete including curing, compaction etc. complete in specified grade excluding the cost of centering and shuttering - All work up to plinth level. 1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size.) |
| 25 | Random Rubble stone masonry for with hard stone in foundation and plinth in Cement Sand mortar above 30 CM thick wall in: Cement Mortar 1:6 ( 1-Cement : 6-Sand). |
| 26 | Providing and laying damp-proof course with cement concrete grade M-150(1:2:4) Mortar prepared with 1% solution of water-proof compound complete as per specification 75mm thick |
| 27 | Brick work with F.P.S. bricks of class designation 75 in superstructure above plinth level upto floor V level in all shapes and sizes in : Cement mortar 1:6 (1 cement : 6 coarse sand ) |
| 28 | Centering & Shuttering with plywood or steel sheets including strutting, propping bracing both ways with steel props and removal of formwork for upto floor five level for : Suspended floors, roofs, landings, staircases, balconies, girders, cantilevers, bands, coping bed plates, anchor blocks, sills, chhajjas, lintel, beam, plinth beam etc. |
| 29 | Providing and laying in position specified grade of cement concretee for RCC structural elements upto floor five level including curing, compaction, finishing with rendering in cement sand mortar 1:3 (1 cement: 3 coarse sand) and making good the joints and cost of plastizers (if required ) excluding the cost of centering, shuttering and reinforcement for Walls (any thickness) including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. M20 grade Nominal Mix / Design Mix . |
| 30 | Steel Reinforcement: Providing and fabrication reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding ( including cost of binding wire) all complete up to floor five level. (Original producers who manufacture billet directly from iron ores and rolll the bilets to produce steel conforming to IS:1786) Thermo-mechanically Treated bars (Conforming of relevent IS code ) (100 kg per cum of c.c.) |
| 31 | Plaster on new surface on walls in cement sand mortar 1:4 including racking of joints complete fine finish : 20 mm thick |
| 32 | 6 mm thick cement plaster to celling of mix 1:3 (1 cement : 3 fine sand ) |
| 33 | Providing and applying white cement based putty over plastered surface to prepare the surface even and smooth complete. New plastered Surface (Three or more coats) |
| 34 | Distempering with dry distemper of approved brand and Shade ( two or more coats) and of required shade on new work, over and including, priming coat of whiting to give an even shade including all scaffolding. |
| 35 | Finishing wall with water proofing cement paint of approved brand and manufacture and or required shade to give an even shade including all scaffolding. New work (Two or more coats applied @3.84 kg / 10 sqm) |
| 36 | Painting with synthetic enamel paint of approved brand and manufacture to give an even shade: Two or more coats on new work. |
| 37 | Supplying and fixing stone lintels/bed plates of approved quarry rough dressed in cement mortar 1:4 Upto 15 cm thick. Window / D |
| 38 | Providing dab stone over chajjas duly fixed in cement sand mortar 1:6 complete . 50mm thick |
| 39 | Providing and fixing horizontal chajja of Red/ white sand stone 40 mm thick and upto 80 cm projection in cement mortar 1:4 (1 cement : 4 coarse sand ) including pointing in white cement mortar 1:2 ( 1 white cement : 2 stone dust ) with an admixture of pigment matching the stone shade. |
| 40 | Filling available excavated earth (excluding rock) in trenches, plinth side of foundation etc. in layers not exceeding 20 cm. in depth, consolidating each deposited layer by ramming and watering including lead up to 50 meter and with all lift. |
| 41 | Random rubble dry stone kharanja under floor. |
| 42 | Providing and laying in position cement concrete including curing, compaction etc. complete in specified grade excluding the cost of centering and shuttering - all work up to plinth level. M15 grade Nominal mix 1:2:4 ( 1 cement : 2 course sand : 4 graded stone aggregate 40 mm nominal size ). (flooring) |
| 43 | Kota stone slab flooring 25 mm thick over 20 mm (average) thick base laid over and jointed with grey cement slurry mixed with pigment to match the shade of the slab including rubbing and polishing complete with base of cement mortar 1:4(1 cement : 4 coarse sand ) for area of each slab from 901 to 2000 sq. Cm : 864.00 |
| 44 | Providing and fixing 1st quality MAT & Glossy finished ceramic tile confirming to IS : 13755 and IS 15622 colour such as white, grey, ivory, fume red brown, light green, light blue and other light shades in floors, steps, pillars etc. laid on a bed of neat cement slurry finished with flush pointing in the white cement mixed with pigment to match the shade of the tile complete (including the cost of cement mortar bed 1:4 ) Size 250mm x 375 mm sqm 661.00 |
| 45 | Providing and fixing in cm 1:4 double paitam (rebated ) stone door window and ventilator frames of approved quarry: Size 100 x 75 mm. |
| 46 | Sanitory Work |
| 47 | Electricity fitting |
| 48 | Gate and Window fitting |
| 49 | septic tank |
| 50 | Construction of 400 RMT Boundary Pucca Wall 4 feet Height |
| 51 | Surface dressing of the ground including removing vegetation and inequalities not exceeding 15cm deep and disposal of rubbish lead up to 50 Mtr. and lift up to 1.5 Mtr. : All kinds of soil |
| 52 | Earth work in excavation by mechanical means (Hydraulic Excavator )/ manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift upto 1.5 m, including taking out the excavated soil and depositing and refilling of jhiri with watering & ramming and disposal of surplus excavated soil as directed with in a lead of 50 meter.All kinds of soils |
| 53 | Providing and laying in position cement concrete including curing, compaction etc. complete in specified grade excluding the cost of centering and shuttering - All work up to plinth level. 1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate40mm nominal size). |
| 54 | Random Rubble stone masonry for with hard stone infoundation and plinth in Cement Sand mortar above 30 CM thick wall in: Cement Mortar 1:6 ( 1-Cement : 6-Sand). |
| 55 | Random Rubble stone masonry with hard stone insuperstructure above plinth level and upto five level above 30cm. thick walls in : Cement Mortar 1:6 ( 1-Cement : 6-Sand). |
| 56 | Plaster on new surface on walls in cement sand mortar 1:6 including racking of joint etc. complete fine finish : 25 mm thick |
| 57 | Pointing on stone masonry in cement sand mortar 1:3 (1cement : 3 sand) :Flush / Ruled/ Struck or weathered pointing. Boundary Wall Face * 2 side |
| 58 | Providing & fixing precast cement concrete coping 1 : 2: 4 mix 50mm thick complete as per specification : (A) Pillar top (B) Boundary wall top |
| 59 | Construction of Vermi compost Unit |
| 60 | Clearing jungle including uprooting of rank vegitation ,grass,brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removel of rubbish up to a distance of 50m outside the periphery of the area cleared |
| 61 | Earth work in excavation by mechanical means (hydraulic excabator ) manual means over areas ( exceeding 30 cm in deapth 1.5 m in width or 10 sqm on plan) icluding excavated earth, lead upto 50m and lift upto 1.50m disposal earth to be levelled and neatly dressed ,all kinds of soil |
| 62 | Random Rubble stone masonry for foundation and plinth in Cement Sand mortar above 30 cm thick wall in : Cement Mortar 1 : 6 (1-Cement : 6-Sand). |
| 63 | Providing and laying damp proof course with cement concrete Grade M-150(1:2:4) Mortar prepared with 1 % soluition of water proof compound complete as per specification 75 mm thick |
| 64 | Brick work with F.P.S. bricks of class designation 75 in superstructure above plinth level upto floor V level in all shapes and sizes in : Cement mortar 1:6 (1 cement : 6 coarse sand ) |
| 65 | Plaster on new surface on stone masonary in cement sand mortar 1:3 including racking of joints etc. complete fine finish 25 mm thick (C) Long wall Out side (G) Long wall Top side |
| 66 | Teen Shed kary |
| 67 | Construction of Pakka Beds (20 Beds) |
| 68 | Clearing jungle including uprooting of rank vegitation ,grass,brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removel of rubbish up to a distance of 50m outside the periphery of the area cleared |
| 69 | Earth work in excavation by mechanical means (hydraulic excabator ) manual means over areas ( exceeding 30 cm in deapth 1.5 m in width or 10 sqm on plan) icluding excavated earth, lead upto 50m and lift upto 1.50m disposal earth to be levelled and neatly dressed ,all kinds of soil |
| 70 | Random Rubble stone masonry for foundation and plinth in Cement Sand mortar above 30 cm thick wall in : Cement Mortar 1 : 6 (1-Cement : 6-Sand). |
| 71 | Random Rubble stone masonry for superstructure above plinth level one storey height above 30 cm. thick walls in : Cement Mortar 1 : 6 (1-Cement : 6-Sand). |
| 72 | Plaster on new surface on stone masonary in cement sand mortar 1:3 including racking of joints etc. complete fine finish 25 mm thick |
| 73 | Providing and laying damp proof course with cement concrete Grade M-150(1:2:4) Mortar prepared with 1 % soluition of water proof compound complete as per specification 50 mm thick |
| 74 | Construction Seed Germination unit |
| 75 | Clearing jungle including uprooting of rank vegitation ,grass,brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removel of rubbish up to a distance of 50m outside the periphery of the area cleared |
| 76 | Earth work in excavation by mechanical means (hydraulic excabator ) manual means over areas ( exceeding 30 cm in deapth 1.5 m in width or 10 sqm on plan) icluding excavated earth, lead upto 50m and lift upto 1.50m disposal earth to be levelled and neatly dressed ,all kinds of soil |
| 77 | Random Rubble stone masonry for foundation and plinth in Cement Sand mortar above 30 cm thick wall in : Cement Mortar 1 : 6 (1-Cement : 6-Sand). |
| 78 | Random Rubble stone masonry for superstructure above plinth level one storey height above 30 cm. thick walls in : Cement Mortar 1 : 6 (1-Cement : 6-Sand). |
| 79 | Plaster on new surface on stone masonary in cement sand mortar 1:3 including racking of joints etc. complete fine finish 25 mm thick |
| 80 | Providing and laying damp proof course with cement concrete Grade M-150(1:2:4) Mortar prepared with 1 % soluition of water proof compound complete as per specification 50 mm thick |
| 81 | Green Net shed kary Please Enable Macros to View BoQ information |