| 1 | Earth work excavation and depositing on bank with in initial lead of 10 m and initial lift of 2m in hard stiff clay, stiff black cotton soil, hard red earth,earth mixed with small sized boulders and hard gravelly soil as per SS 20B etc |
| 2 | Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for Levelling course |
| 3 | Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for Foundation |
| 4 | Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for Superstructure |
| 5 | Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for bed blocks |
| 6 | Reinforced cement concrete 1:1.5:3 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying, and curing etc complete for Deckslab |
| 7 | Supplying and erecting centering shuttering including necessary supports for plane surface in foundation and superstructure for Abutment /pier using mild steel sheets of size 90 x 60 cm and 10 guage stiffened, welded with mild steel angles of size 25mmx25mmx3mm for boarding laid over silver oak (country wood) scantlings of size 10cm x 6.5cm spaced of about 90cm centre to centre and supported by casurina props of 10cm to 13cm dia spaced at 75cm centre to centre complete complying with standard specifications and as directed by departmental officers etc. |
| 8 | Above Sill Level |
| 9 | Supplying and fabrication of steel including cost and conveyance of steel to site and all labour charges for straightening, cutting to length,bending to shape and tying in position and forming grills for all R.C.C works |
| 10 | Providing and fixing 20mm Bitumen felt for expansion joint Between Dirtwall &Deck slab |
| 11 | Providing and fixing Tar Paper for bearing Between Bed Block & Deck slab |
| 12 | Providing weepholes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing |
| 13 | Collection and supply of US gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for filling etc.complete, |
| 14 | GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column \"BB\" for all works in this package} Please Enable Macros to View BoQ information |