| 1 | Supplying, laying Jointing of 1000 mm dia NP-3 hume pipe (S&S type) including complete as per directiobn of EI |
| 2 | Construction of embankment with approved material obtained from borrow pits with a lift upto 1.5 m, transporting to site, spreading, grading to required slope and compacting to meet requirement of Tables 300.1 and 300.2 with a lead upto 1000 m as per Technical Specification Clause 301.5 |
| 3 | Laying brick soling layer on prepared sub-grade with brick on end edging according to lines, graded and cross-section shown on the drawing filling joints with sand and earth, spreading 25 mm thick layer of earth over brick soling, watering and rolliing the same with three wheel road roller 80-100 kN as per Technical Specification Clause 412 |
| 4 | Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 m as per Technical Specification Clause 202. |
| 5 | Dismantling of existing structures like culverts, bridges, retaining walls and other structures comprising of brick masonry, including unserviceable material and stacking the serviceable material with all lead and lift of 1000 m as per Technical Specification Clause 202. |
| 6 | Removal of unserviceable soil including excavation,loading and disposal up to 1000 meters lead but excluding replacement by sutiable soil which ahall be paid separately as per clause 305 |
| 7 | Excavation in foundation in ordinary soil (Loam, clay or sand) including lift upto 1.50 m and lead upto 30 M and including filling watering and ramming of excavated earth into the trenches and removal and disposal of surplus earth as directed by the Engineer in Charge up to distance 30m. SI No. 251(a) |
| 8 | Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface., mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, as per MORD specification 401(including,labour cess but excluding G.S.T) |
| 9 | Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications.(M-10)(P.C.C) |
| 10 | Providing and laying reinforced cement concrete in superstructure as per drawing and technical specifications Clauses 800, 1205.4 and 1205.5(M-30) |
| 11 | Supplying, fitting and placing TMT bar reinforcement (Fe 415) in substructrue complete as per drawings and technical specification Clauses 1002, 1005, 1010 & 1202 |
| 12 | Supply & Fixing of 100 mm dia Drainage Spouts of MS with gratings as per drawing including cost of all materials, labour, T & P etc. required for proper completion of the work as per drawing and Technical specification. |
| 13 | Back filling behind abutment, wing wall and return wall complete as per drawing and Technical Specification. |
| 14 | Providing weep holes in Brick masonry/Plain/ Reinforced concrete abutment, wing wall/ return wall with 80 mm dia PVC pipe, extending through the full width of the structure with slope of 1V :20H towards drawing foce. Complete as per drawing and Technical Specifications |
| 15 | Providing pressure relief pipes 100 mm dia in bottom slab of box cell on a filter media base of 500 mm x 500 mm as per drawing and technical specification Clause 1205.5.7 |
| 16 | Providing and laying boulders apron on river bed for protection against scour with stone boulders weighing not less than 40 kg each complete as per drawing and Technical specification. |
| 17 | Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with 3 wheeled steel/ vibratory roller 8-10 tonnes in stages to proper grade and camber, applying and brooming requisite type of screening/ binding Materials to fill up the interstices of coarse aggregate, watering and compacting to the required density (.For Grading-II ) |
| 18 | Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with 3 wheeled steel/ vibratory roller 8-10 tonnes in stages to proper grade and camber, applying and brooming requisite type of screening/ binding Materials to fill up the interstices of coarse aggregate, watering and compacting to the required density (For Grading-III) |
| 19 | Providing and applying primer coat with bitumen emulsion (SS-1) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.70-1.0 kg/sqm using mechanical means as per Technical Specification Clause 502 |
| 20 | Providing and applying tack coat with bitumen VG-10 grade using bitumen pressure distributor at the rate of 0.30 kg per sqm on the prepared granular surface treated with primer & cleaned with hydraulic broom as per Technical Specification Clause 503 |
| 21 | Providing and laying and rolling of open graded premix carpet by Manual Means of 20 mm thickness composed of 13.2 mm to 5.6 mm agregates using V.G.-10 grade bitumen bitumen to required line grade and level to serve as wearing course on previously prepared base by manual MORD specific ations 508 (excluding cost of labour cess & GST) |
| 22 | Providing and laying seal coat by manual means with 80/100 grade bitumen sealing the voids in bitumens surface laid to the specified levels grade and cross fall using type C as per Technical Specification Clause 510 (excluding cost of labour cess & GST) Please Enable Macros to View BoQ information |