| 1 | (BASED ON RATE ANALYSIS ISOR 2023) |
| 2 | Earth work in excavation for roadway, including trimming bottom and side slopes in accordance with requirement of line, grades and cross sections, including disposal of surplus material with all lift and lead upto 1000 metre as per MoRT&H specification clause 301.In all type of soil |
| 3 | Carriage of Materials by mechanical transport including loading, unloading and stacking ::Earth upto 3 km. |
| 4 | Providing, laying, spreading and compacting of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per MoRT&H specification clause - 401 including all material, labour, machinery, lighting, guarding and maintenance of diversion.Grading - III Material |
| 5 | Providing and applying tack coat on the prepared surface with bitumen emulsion as per IS: 8887 and approved quality @ 0.2 kg/sqm with the help of spray set fitted on bitumen Container (boiler) after cleaning the surface with brooms or soft brushes and finally dusting with old gunny bags and compressed air to receive bituminous treatment complete as per clause 502 of MoRT&H specification including all material, labour, machinery, lighting, guarding and maintenance of diversion. |
| 6 | Providing and laying bituminous macadam in 50/75 mm compacted thickness on prepared surface with specified graded crushed stone aggregates as per Table 500-4, Grading-II for base/ binding course, loading of aggregate with F.E. loader, heating and mixing of stone aggregate and bitumen in computerised hot mix plant, transported to site by tippers to paver, laid over a previously prepared surface with paver finisher fitted with electronic sensing device to the required grade, level and alignment and rolling with power roller and vibratory compactor as per clauses 501.6 and 501.7 to achieve the desired compaction complete as per clause 504 of MoRT&H specification and including all material, labour, machinery, lighting, guarding and maintenance of diversion but excluding cost of primer/ tack coat.With Bitumen VG-grade 30 @ 3.3% (percentage by weight of total mix) |
| 7 | Providing laying and consolidation Semi Dense Bituminous Concrete, as per Design Mix (approved by Engineer), on prepared surface with specified graded crushed aggregates as per table 500-15 for wearing coarse including loading of material with F.E. loader, hot mixing of stone aggregate, filler and bitumen (including Cost of anti-stripping compound Minimum 1% in Lime/Cement as per design wherever required) heating and mixing in in computerised hot mix plant, transporting the mixed material by tippers to paver and laying with paver finisher fitted with electronic sensor control to the required level and grade, compacting by power rollers and vibratory rollers or 150 to 250 KN pneumatic tyred roller with TP = 0.7 Mpa, to achieve the desired density (approximately 2.3 tonne/cum) complete as per clause 508 of MoRT&H specification including all material, labour, machinery, lighting, guarding and maintenance of diversion but excluding primer/tack coat. 35-40 mm compacted thickness (Grade-1) using Bitumen VG-grade 30 @ 4.5% (percent by weight of total mix) Please Enable Macros to View BoQ information |