| 1 | work detial |
| 2 | Earth work in foundation excavation up to 1.5m, ramming bottom, dressing sides,back filling and disposal of surplus soil with in a lead of 50m.In hard soil. |
| 3 | Cement concrete in foundation and plinth with stone ballast size 40mm including curing and compaction etc in 1:4:8 mix |
| 4 | Brick work in foundation and plinth using bricks of class designation-75 in CM 1:6 |
| 5 | Brick work in super structure using bricks of class designation-75 in CM 1:6 |
| 6 | S & F Stone lintels |
| 7 | P & L First class stone slab roof in CM 1:4 |
| 8 | P & L brick bats on roof |
| 9 | S & F mosaic tiles on roof |
| 10 | 20mm thick plaster on new work including curing and racking of joints in CM 1:6 |
| 11 | S & F Glaze tiles on wall |
| 12 | Providing and applying white cement based putty over plastered surface to prepare the surface even and smooth complete (PWD BSR-2022 - Less-10%) |
| 13 | Finishing walls with Acrylic Smooth exterior paint of required shade including all scaffolding.New work ( Two or more coat incuding base coat of water proofingcement paint) -(PWD BSR -2022 Less- 10%) |
| 14 | Wall painting with plastic emulsion paint of required shade including all scaffolding.New work ( Two or more coatincuding base coat of water proofing cement paint) -(PWD BSR-2022 Les-10%) |
| 15 | S & F iron door |
| 16 | Enamel painting on door and window |
| 17 | Wiring for fan/light point in PVC condutpipe as per specification |
| 18 | Wiring for light/Power point in PVC condutpipe as per specification |
| 19 | Wiring for circuit/submain as perspecification- 2x1.5Sqmm |
| 20 | S & F Water cooler |
| 21 | S & F Wate Filter |
| 22 | S & F Electric motor pump |
| 23 | S & F PVC water storage tank |
| 24 | S & F Bib cock |
| 25 | Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes (IS 15778 : 2007 code) having thermal stability for hot & cold water supply including all CPVCplain & brass threaded fittings i/c fixing the pipe with clamps at 1 metre spacing. This includes jointing of pipes& fittings with one step CPVC solvent cement and testing of joints complete as per direction of Engineer in Charge.(Internal work Exposed on wall) ( PWD20mm nominal size |
| 26 | S & F Full way valve-20mm |
| 27 | Earth work in foundation excavation up to 1.5m, ramming bottom, dressing sides,back filling and disposal of surplus soil with in a lead of 50m. |
| 28 | Cement concrete in foundation and plinth with stone ballast size 40mm including curing and compaction etc in 1:4:8 mix |
| 29 | Brick work in foundation and plinth using bricks of class designation-75 in CM 1:6 |
| 30 | DPC - Reinforced cement concrete workincluding curing compaction, finishing withrendering in cement sand mortar 1:3 andmaking good and joints excluding cost ofcentering, shuttering and reinforcement in1:1.5:3 (1cement: 1.5course sand: 3-graded stone aggregate 20mm nominalsize) |
| 31 | Brick work in super structure using bricks of class designation-75 in CM 1:6 |
| 32 | Reinforced cement concrete workincluding curing compaction, finishing withrendering in cement sand mortar 1:3 andmaking good and joints excluding cost ofcentering, shuttering and reinforcement in1:1.5:3 (1cement: 1.5course sand: 3-graded stone aggregate 20mm nominalsize) |
| 33 | Providing and fabricating reinforcementfor RCC work including straightening,cutting, bending, placing in position andbinding (including cost of binding wire) infoundation and super structure up to 4.5mheight above plinth level hot rolleddeformed (IS: 1139) cold twisted (IS:1786) bars |
| 34 | Centering and shuttering with plywood orsteel sheets including strutting, propping,bracing both ways with wooden membersand removal of from work |
| 35 | S & F steel girder including cutting,hoisting and fixing in position 300x140 |
| 36 | S & F stone sriwan in CM 1:6 |
| 37 | P & L First class stone slab roof in CM 1:4 |
| 38 | P & L brick bats on roof in CM 1:4 |
| 39 | S & F Mosaic tiles on roof |
| 40 | 20mm thick plaster on new work includingcuring and racking of joints in CM 1:6 |
| 41 | Providing and applying white cementbased putty over plastered surface toprepare the surface even and smoothcomplete |
| 42 | Finishing walls with Acrylic Smoothexterior paint of required shade includingall scaffolding.New work ( Two or morecoat incuding base coat of water proofing cement paint) -PWD BSR -2022 - Less10% |
| 43 | Wall painting with plastic emulsion paint ofrequired shade including allscaffolding.New work ( Two or more coatincuding base coat of water proofingcement paint) -PWD BSR-2022 - Less10% |
| 44 | S & F iron door |
| 45 | Providing and fixing steel glazed doorswindows and ventilator shutters of standardrolled steel section (IS 1038-1983) joints mitredand welded with steel lugs 13x3mm, 10cm. longembedded in cement concrete block15x10x10cm. of 1:3:6 (1cement : 3 coarse sand: 6 graded stone aggregate 20mm nominal size) orwith wooden plugs and screws or rawl plugs andscrews with fixing clips or with bolts and nutsas required including providing and fixing of plainglass panes 4mm thick with cooper glazing clipsand special metal sash 4mm thick with cooperglazing clips and special metal sash putty ofapproved make or metal beading with screwscomplete including priming coat of approval steelprimer, excluding the cost of metal beading andother fitting except necessary hinges of pivots |
| 46 | S & F wire mesh on Section window |
| 47 | S & F Iron bars on Section window |
| 48 | Enamel painting on door and window |
| 49 | Earth work in filling with ordinary soil |
| 50 | Carriage of earth-lead One KM |
| 51 | Cement concrete in floor with stoneballast size 40mm including curing andcompaction etc in 1:6:12 mix |
| 52 | S & F Polished Kota stone flooring |
| 53 | Wiring for fan/light point in PVC condutpipe as per specification |
| 54 | Wiring for circuit/submain as perspecification- 2x1.5Sqmm |
| 55 | Yojna board & Contingency charges Please Enable Macros to View BoQ information |