| 1 | Earth work in surface excavation not exceeding 30 cm in depth but exceeding 1.5 m in width as well as 10 sqm on plan including getting out and disposal of excavated earth upto 50 m and lift up to 1.5 m, as directed by Engineer-in-Charge:, All kinds of soil |
| 2 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m., All kinds of soil. |
| 3 | Earth work in cutting or embankment in ordinary soil,excavation to be in the form of regular pits not exceeding 0.50m in depth and earth work in embankment to be in 20 cm layers including ramming and dressing the surface to required levels and slopes and including 1.50m lift and 30 m lead also including cartage of earth upto 8 kms,cost of earth if any,and royalty etc complete in all respect. SI No. 253 (a) |
| 4 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :, 1:4:8 (1 Cement : 4 coarse sand (zone-III) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources). |
| 5 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level :, 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) |
| 6 | Centering and shuttering including strutting, propping etc. and removal of form for :, Foundations, footings, bases of columns, etc. for mass concrete |
| 7 | Centering and shuttering including strutting, propping etc. and removal of form for :, Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc. |
| 8 | Painting with synthetic enamel paint of approved brand and manufacture of required colour to give an even shade:, Painting with synthetic enamel paint of approved brand and manufacture of required colour to give an even shade: Two or more coats on new work over an under coat of suitable shade with ordinary paint of approved brand and manufacture. |
| 9 | Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete. |
| 10 | Extra for compaction of earth work in embankment under optimum moisture conditions to give at least 95% of the maximum dry density (proctor density). |
| 11 | Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at the rate of 0.25 kg per sqm on the prepared bituminous surface cleaned with mechanical broom |
| 12 | Mild steel or iron work in plain work such as in R.C.C. or R.B. (when not included in an over all rates ) including bending for proper completion of the work and including supply of steel and its wastage , bends, hooks and authorised overlaps shall be measured up to floor two level. (SI No. 504) (Sanction Rate) |
| 13 | \"Construction of granular sub-base by providing coarse graded material, spreading in uniform layer with motor grader on perpared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratoy roller to achieve the desired density complete as per clause 401. For Grading I Material (GSB-I)\" |
| 14 | Providing, laying and spreading of graded stone aggregate (WMM) after mixing with water at OMC in mechanical mix plant carriage of mixed material by tipper to site, laying with 1% OPC cement and 3.50% Emulsion in uniform single layer on sub base/subgrade and compacting with the road roller to achieve the desire density @4160.00 |
| 15 | Providing and applying primer coat with bitumen emulsion (slowe setting) on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.60 kg/sqm using mechanical means. (Sanction Rate) |
| 16 | Providing and laying bituminous macadam (B.M.) with 100-120 TPH hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading premixed with bituminous binder @3.30%, transported to site, laid over a previously prepared surface with paver finisher to the required grade, level and alignment and rolled as per clauses 501.6 and 501.7 to achieve the desired compaction (Sanction Rate) |
| 17 | 25 mm thick Semi-Dense Bituminous Concrete (S.D.B.C.) (Using Water Plastic) providing and laying Semi-Dense Bituminous Concrete with 100-120 TPH batch type HMP producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @ 5 per cent mix to work at site as per MORTH & H specification clause No. 508 complete in all respects(Reducing Bituminous Quantity by 8% and replacing it by Plastic wastage as per IRC : SP: 98-2013) (Sanction Rate) |
| 18 | Providing and laying factory made chamfered edge Cement Concrete paver blocks In foot path, park & lawns driveway or light & traffic parking etc. of required strength, thickness & size/ shape, made by table vibratory method using PU mould, laid in required colour & pattern over 50mm thick compacted bed of course sand, compacting and proper embedding/ laying of inter locking paver blocks into the sand bedding layer through vibratory compaction by using plate vibrator, filling the joints with sand and cutting of paver blocks as per required size and pattern, finishing and sweeping extra sand, all complete as per manufacturer\"s specifications & direction of Engineer in-Charge., 80mm thick Cement concrete paver block of M-30 grade with approved colour, design & pattern. |
| 19 | Providing and applying 2.5 mm thick road marking strips (retro-reflective) of specified shade/ colour using hot thermoplastic material by fully/ semi automatic thermoplastic paint applicator machine fitted with profile shoe, glass beads dispenser, propane tank heater and profile shoe heater, driven by experienced operator on road surface including cost of material, labour, T&P, cleaning the road surface of all dirt, seals, oil, grease and foreign material etc. complete as per direction of Engineer-in-charge and accordance with applicable specifications. Please Enable Macros to View BoQ information |