| 1 | Safe carriage of following material from Store Centre to site/JE store with loading & unloading at both ends respectively distance with in 40 Kms. |
| 2 | 09/11/13 Mtr. Long ST Poles |
| 3 | 8.5 Mtr. PCC Pole |
| 4 | 33KV/11 KV XLPE Cable 3x70/120mm2/185/300/400 |
| 5 | 11/0.4 10 KVA Transformers |
| 6 | 11/0.4 25 KVA Transformers |
| 7 | 11/0.4 63 KVA Transformers |
| 8 | 11/0.4 100 KVA Transformers |
| 9 | ACSR Weasel/Rabbit/Dog Conductor |
| 10 | 33KV/11 KV CT/PT unit with all its related accessories. |
| 11 | 33KV/11 KV Pilfer resistant metering Cubical. |
| 12 | L.T. ABC Cable off Different Sizes. |
| 13 | L.T. Alu. Cable Size 3.5x70mm. |
| 14 | 11 KV line material Such as Cross-Arms, Pin Insulators, Guarding Angles, G.I. Wire, Disc Insulators, Stay Rod, Stay Wire & Cable Jointing Kits etc |
| 15 | Digging of pits, Erection of 13/11 Mtr. Long ST/PCC Pole including fixing of all required accessories by providing M.S. Clamps Nut & Bolts. |
| 16 | Digging of pits, Erection of 13/11 Mtr. Long ST Double poles including fixing of all required accessories by providing M.S. Clamps Nut & Bolts. |
| 17 | Digging of pits, Erection of 8.5/9 Mtr. Long PCC pole including fixing of all required accessories by providing M.S. Clamps Nut & Bolts. |
| 18 | Digging of pits, Erection of 13/11 Mtr. Long ST Single Section Pole including fixing of all required accessories by providing M.S. Clamps Nut & Bolts. |
| 19 | Fabrication and fixing of T/F Angle seat on Double pole for Mounting and safe placement of T/F on Double pole by providing M.S. Clamps Nut & Bolts. |
| 20 | Grounding of earth rods for making earthing of poles and T/F by M.S clamps, nut and Bolts. |
| 21 | Grouting of Stay rods (20x1800mm.) including all works of excavation, cement concrete in size of (0.60x0.60x0.30) M in the atio of 1:4:6 (cement, sand and 40mm. brick ballast) including back filling of soil and proper ramming etc. |
| 22 | Fixing, tightening and nozelling of stay wire with stay rod and stay insulators, with pole of required tension by providing stay clamps, nuts, bolts etc. |
| 23 | Fabrication and fixing of guarding angles on poles by M.S clamps, nut & bolts, laying and sagging of G.I wire, Fixing and binding of cross lesses for making jaal under 11KV line. |
| 24 | Fabrication of M.S channel/Angle/33 KV/11 KV Cross Arm including its cutting, Drilling making holes etc. |
| 25 | Fabrication of M.S. Channel/angle and mounting of 33 KV/ 11 KV CT/PT unit on Double pole and fixing & fitting of all related accessories by providing m.S. clamps, Nuts & Bolts for Double metering. |
| 26 | Installation of 33 KV/11 KV pilfer resistant metering cubical in meter room Including fixing of cable Boxes and Making Connections Complete Work. |
| 27 | Laying and sagging of ACSR weasel/Rabbit/Dog conductor in 33KV/11KV line including its binding on Insulators ets complete work. |
| 28 | Filling and fixing of 33KV/11KV cable jointing kits after laying of XLPE cable. |
| 29 | Laying, jointing & binding of 33 KV/ 11 KV XLPE cable on pole and other end in meter room. |
| 30 | Grouting of ST pole and making plinth all around the pole with cement, sand and stone Ballast in ratio 1:4:6 |
| 31 | Fabrication and fixing of T-off channels on poles by providing M.S clamps, Nut and Bolts. |
| 32 | Mounting and fixing of 10 KVA transformers on Single pole including making proper connections. |
| 33 | Mounting and fixing of 25 KVA transformers on double pole including making proper connections. |
| 34 | Mounting and fixing of 63 KVA transformers on double pole including making proper connections. |
| 35 | Mounting and fixing of 100 KVA transformers on double pole including making proper connections. |
| 36 | Providing & fixing of danger board at each location as per specification of the drawing. |
| 37 | Laying and mounting of LT PVC Cable 3.5x70mm2 on Poles . |
| 38 | Laying, lifting and sagging of ABC Cable on poles by fixing all type of clamps, its binding on shackle insulators etc. Complete work. |
| 39 | Fixing of Distribution Boxes on ST Poles by providing MS Clamps including making connections of consumer’s cable connections by providing locks on Distribution Boxes. |
| 40 | Trimming of Tree branches crossing in the route of different spans of 33 KV/11KV/LT Lines. |
| 41 | Providing Wrapping of barbed wire on SP-55 Poles 1 Kg. per Pole. |
| 42 | Providing and fixing of Number Plate with clamp, nut and bolts. |
| 43 | Back Cartage of Old used Damaged 10/25/63/100 T/F from work Site to Bijnor Store including its loading and unloading. |
| 44 | Back Cartage of Old used Damaged CT/PT unit and 33KV/11 KV Pilfer Resistant Unit from work Site to Bijnor Store including its loading and unloading. Please Enable Macros to View BoQ information |