|
| 1 | Dismantling Of old RCC coverd slab/ Ramp including stacking of all materialat site |
| 2 | Dismantling of old damaged cement concrete Interlocking paver Tiles road incloding stacking of all material at site |
| 3 | Dismantling Of old damaged Brick work in cement mortar |
| 4 | Excavation work for Drain/Nala in foul condition of Soil including, lift upto 1.50 M and lead Upto 30m |
| 5 | Providing and laying cement concrete in 1:6:12 (1 cement : 6 Fine sand : 12 Brick ballast 40 mm gauge) |
| 6 | M-150 First class B/w in 1:4 Cement C\"sand mortor in Sub Structure including supply of all meterial labour t&P etc required for proper completion of work |
| 7 | 12 mm thick plaster in 1:4 cement & Coarse sand mortor over brick work minimume thickness not less then 10 mm including all supply of meterial , Labour T&P etc S.I.No. 584(i) |
| 8 | Providing and laying cement concrete with 1:2:4 (1cement 2 coarse sand and 4 graded stone ballast 20 mm nominal size) and curing complete, supply of all materials, curing, labour and T&P etc. required for proper completion of work as per direction of E/I) As per SI. No.279(a) |
| 9 | Supply,Laying and Consolidation of 22.40-53 mm gauge stone Ballast |
| 10 | Construction of un-reinforced plain cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade cement or any other type as per Clause 1501.2.2 M 30(Grade), coarse and fine aggregates conforming to IS:383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a concrete mixer of not less than 0.2 cum capacity and appropriate weigh batcher using approved mix design, laid in approved fixed side formwork (steel channel, laying and fixing of 125 micron thick polythene film, wedges, steel plates including levelling the formwork as per drawing), spreading the concrete with shovels, rakes, compacted using needle, screed and plate vibrators and finished in continuous operation including provision of contraction and construction joints, applying debonding strips, primer, sealant, near approaches to bridge/culvert and construction joints, admixtures as approved, curing of concrete slabs for 14-days,using curing compound (where specified) and water finishing to lines and grade as per drawing and finished with Power Trowel Cum Floter-Trimix Flooring Machine.Technical Specification Clause 1501. |
| 11 | M.S. or iron work of small sizes and section such as holding down bolts, hold fast, tie rods grating etc. wrought to required from including supply of steel bolts, nuts wastage etc. and their fixing required for proper completion of the work |
| 12 | Cartage for Disposal of all malba surpluse earth etc upto 5.00 Km |
| 13 | RCC Work with cement, approved coarse sand and 2 cm gauge approved stone grit in proportions of 1:1.5:3 in Slab |
| 14 | Supply, Fitting and placing HYSD bar reinforcement in sub-structure complete as per drawing and technical specifications including supply of all material, labour, Tools & Plants etc. required for proper completion of work |
| 15 | Supply and fixing of inoguration black granite stone padestal i/c grooving matter, b/w, plaster, painting etc all complete work |
| 16 | Deduct cost of old brick bats |
| 17 | Deduct cost of old Interlocking Paver Tiles |
| 18 | GST 18 % Please Enable Macros to View BoQ information |