| 1 | Dismantling of Bituminous Road & sorting out & stacking of serviceable material including supply of lab, T&P etc complete |
| 2 | Excavation of foundation in ordinary soil including supply of lab,T&P etc complete upto 1.50m |
| 3 | Concrete work 20 gauge brick blast & 1:3 cement & coarse sand mortar under floor in prop 1:05 including supply of lab, mat, T&P etc |
| 4 | Making necessary arrangement of barricading with sal ballies, red flag, lab, T&P etc complete |
| 5 | 1st class brick work with 1:3 cement & coarse sand mortar including supply of lab, mat, T&P etc complete |
| 6 | 12 mm thick plaster 1:3 cement & L.Sand mortar including supply of lab, mat, T&P etc complete |
| 7 | Providing bier to retain sewage water etc complete |
| 8 | RCC work with cement, C.sand & stone ballast 1:1.5:3 in slab including supply of lab, mat,T&P etc complete |
| 9 | Mild steel or iron work in slab including supply of lab,T&P etc complete |
| 10 | Bailing out of water with 5 HP mud pump including accessories & supply of lab,T&P etc complete |
| 11 | Cast cement concrete for seat fixing in 1:2:4 including supply of lab, mat, T&P etc complete |
| 12 | Supply & laying of RCC pipe 300 mm dia including supply of lab, mat, T&P etc complete |
| 13 | Making sewer line connection with supply of lab, mat, T&P etc complete |
| 14 | Supply of RCC frame of size 650 X 75 mm |
| 15 | Supply of RCC cover on M.H size 650 X 75 mm |
| 16 | Disposal of surplus earth & dismantled malva of excavated earth etc complete |
| 17 | Unforeseen work as cartage of pipe including loading/unloading etc complete Please Enable Macros to View BoQ information |