| 1 | Single under reamed pile foundation with RCC M20 using 12mm size black hard granite(Crusher broken) stone chips including cost of boring but excluding cost of MS/ Tor steel and labour charges for cutting, bending and binding of steel |
| 2 | Earth work in hard soil or gravelly soil within 50m. Initial lead and 1.5m. Initial lift icluding rough dressing and bracking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m. in depth and as per the direction of the EIC |
| 3 | Filling in foundatin and plinth with sand watered and rammed including all cost of materials, labour, conveyance, royalty, cess etc. complete |
| 4 | Providing,laying, spreading and compacting graded stone aggregates to Wet mix macadam specification including premixing the material with water at OMC in machanical mix plant,carriage of mixed material by tripper to site,laying in uniform layers with paver in sub-base/base course on well prepared surface and compacting with 3 wheeled steel roller 8-10 tonnesto achieve the desired density as per Clause 406 of MoSRT&H Specification for Road & Bridge works (4th Revision) including cost and conveyance of materials T&P etc (See Page no-166,Item no 42 of AoR-06) |
| 5 | Cement Concrete (1:3:6) with 40 mm size hand broken granite metal ( HB ) including all cost of materials, labour, conveyance, royalty, Tools and Plants water for curing etc.all complete,as per OPWD. specification required for the work to finished items of work |
| 6 | Cement Concrete (1:2:4) with 12mm size crusher broken hard granite chips including hosting and laying all cost of materials, labour, conveyance, royalty, Tools and Plants water for curing etc.all complete,as per O.P.W.D. specification required for the work to finished items of work. (See Page no-44,Item no 7 of AoR-06) |
| 7 | R.C.C. work of M20 grade with 20 mm and down grade crusher broken hard granite chips including hosting and laying all cost of materials, labour, conveyance, royalty, Tools and Plants water for curing etc. all complete, as per O.P.W.D. specification required for the work to finished items of work |
| 8 | Supplying ,fitting and placing uncoated HYSD bar reinforcement complete as per drawing and technical specification |
| 9 | RCC foundation, plinth band and footings bases of columns mass concrete, Drain walls & pre-cast slabs etc |
| 10 | Earth work in oridinary soil transporting from borrow area within 5 km initial lead and 1.5m initial lift including rough dressing and breaking clods to maximum 5cm to 7cm and laying in layers not exceeding 0.3m in depth and as per direction of the Engineer-in-charge |
| 11 | Add for other unforeseen Item such as Display Board & Photography etc Please Enable Macros to View BoQ information |