| 1 | Earthwork in excavation by mechanical means (Hydraulic excavator)/manual means in foundation trenchs or drains(Exceeding 30Cm in depth 1.5m in width as well as 10 Sq.M on Plan) including dressing of sides and ramming of bottoms including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50Mtr. (All kinds of Soil) |
| 2 | Clearing jungle including uprooting of rank vegetation , Grass brush wood ,trees and sapling of girth upto 30Cm measured at a height of 1 Mtr above the ground leveland removal of rubbish upto a distance of 50M outside te periphery of the area cleared |
| 3 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. in layers not exceeding 20Cm in depth, consolidating each deposited layer by ramming and watering, lead upto 50M and lift upto 1.5M |
| 4 | Brick work with F.P.S bricks of class designation 75 in foundation and plinth in cement mortar 1:6 (1cement: 6 Sand) complete in all respect as per direction of Engineer in charge |
| 5 | 12mm cement plaster of mix 1:6 (1 cement: 6 Sand) |
| 6 | Supplying and filling in plinth with riversand under floors including watering ramming consolidating and dressing complete. |
| 7 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering. Cement concrete in 1:4:8 (1 Cement : 4 sand:8 Coarse Aggregate 40mm Down) |
| 8 | Providing and laying in position Reinforced cement concrete of specified grade excluding the cost of centering and shuttering. Cement concrete in 1:2:4 (1 Cement : 2 sand:4 Coarse Aggregate 20mm Down) complete in all respect as per direction of Engineer in charge Upto plinth level |
| 9 | Providing and laying Reinforced cement concrete in vertical and horizontal fins individually forming box louvers facias and eaves boardupto v th floor level excluding cost of centering shuttering finishing and reinforcement with CC 1:1½:3 complete in all respect as per directionof Engineer in charge above plinth level CC 1:1½:3 (1 Cement:1½ Coarse Sand:3 Coarse Aggregate 20mm Down) |
| 10 | Providing and placing reinforcement for R.C.C. work including straightining cutting bending placing in position and binding allcomplete. Upto plinth level and above plinth level Thermo Mechanically Treated Bars |
| 11 | SHUTTERING & CENTERING, Centering and shuttering including struting propping etc and removal of forms for: Foundations footing bases of column etc for mass concrete |
| 12 | SHUTTERING & CENTERING, Centering and shuttering including struting propping etc and removal of forms for: Lintels beams plinth beams girders bressumers and cantilevers. |
| 13 | SHUTTERING & CENTERING, Centering and shuttering including struting propping etc and removal of forms for: Columns Pillars piers Abutment Posts and strutts |
| 14 | Finishing wall with acrylic smooth exterior paint of required shade: New work (two or more coat applied @1.67kg/10 Sq.M) on existing cement paint |
| 15 | Applying one coat of cement primer of approved brand and manufactureron wall surface. Cement primer |
| 16 | Steel work welded in built upsection/ framed work including cutting hoisting fixing in position and applying a priming coat of approved steel primer using structural steel etc as required below in grating frames guard bar ladder railings brackets gates and similar works. in grating , frames guard bar railing brackets gates and similar works |
| 17 | Demolishing cement concrete manually/ by mechanical means including disposal of materials with in 50mtr lead as per direction of Engineer inCharge. Cement concrete 1:3:6 or richer Mix |
| 18 | Demolishing brickwork manually/ by mechanical means including stacking of servicable materials and disposal of unservicable materials with in 50mtr lead as per direction of Engineer in Charge |
| 19 | Painting with synthetic enamel paint of approved brand and manufacture to give an even shade: Two or more coats on new work |