| 1 | Strengthening the Road From Mangudi village Road in mangudi Panchayat. Clearing the Scrub jungle including all labour charges for burryingng and burning etc.,Clearing and grubbing road land including uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut earlie and disposal of unserviceable material and stacking of serviceable materials to be used or auctioned, upto a lead of 1000m including removal and disposal of top organic soil not exceeding 150mm thickness as per technical specification clause 201. etc. comp. |
| 2 | Scarifying the existing metal road surface to a depth of 50 mm to 100 mm and disposal of scarified material with a lift upto 3 m and lead upto 1000 m as per Technical Specification including all charges etc complete |
| 3 | Providing laying and compacting U.S Gravel material on prepared sub-grade in accordance with the requirements of the specification.The materials shall be laid in one or more layers as sub-base as necessary according to lines. grades and cross sections hown inthe drawing or as directed by the Engineer. Gravelling for Hard Shoulders. |
| 4 | Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete. |
| 5 | Applying TACK COAT over Primed WBM surface at 2.5Kg of RS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Comp. |
| 6 | Applying PRIMECOAT over WMB/ WMM surface at 7.00Kg of SS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Comp. |
| 7 | BITUMINOUS CONCRETE 25/30/40 MM THICK USING cmp (Grade-II) Providing and laying Bituminous Concrete to 25/30/40mm thick using 0.13 cum of 19.00- 9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 50.30kgs of VG30 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including fuel and all other incidental charges etc., complete asper specification using CMP as per clause 507 of MORTH Rev-5 |
| 8 | Provision of HM Stones (SOR Pg .no :26) |
| 9 | Provision for Name board etc., Complete |
| 10 | GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column \"BB\" for all works in this package} Please Enable Macros to View BoQ information |