| 1 | Earth work excavation for foundation in all soils and sub soils and full depth as may be directed except in rock requiring blasting but inclusive of shoring, strutting,and baling out water wherever necessary and refilling in sides of foundation with excavated more than 15cm thick |
| 2 | Collection and supply of sand and filling in to the basement including cost and including cost and conveyance of all materials to site and labour charges etc complete |
| 3 | Cement conceret 1:4:8 mix using 40mm ISS gauge hand broken hard granite stone jelly for foundation including dewatering if found necessary and laid in layers morethan 15cm thick |
| 4 | Supply and errecting sheet centering of size 90 cm x 60cm 10 G sheet laid over silver oak joist and supported by casurina post of size 10 cm x 13 cm dia spaced at 75 cm center to center etc. complete |
| 5 | Supplying, fabricating and placing in position inild steel or ribbed tor steel and all reinforced cement Concrete works as per the design given including cost of steel and binding wire in all floors etc complete |
| 6 | Reinforced Cement Concrete in 1:1.5:3 mix using 20mm metal including cost and conveyance of all materials to site and labour charges etc complete |
| 7 | Brick work in following Cement Mortar using best quality Fly ash bricks of size 23x11x7cm for foundation and basement including curing etc.,complete complying with standard specification. |
| 8 | Plastering in CM 1:5, 12mm thick including cost and conveyance charges etc., |
| 9 | Painting two coats over NEW Plastered surface using Approved Quality of Exterior Emulsion Paint including cost and all Labour charges etc., complete |
| 10 | Paver block Sub estimate |
| 11 | Earth work excavation and depositing on banks with initial lead and lift in gravelly soil stiff clay, hard stiff clay, murram, boulders mixed with gravel as per SS 20-B for foundation. |
| 12 | Cement conceret 1:4:8 mix using 40mm ISS gauge hand broken hard granite stone jelly for foundation including dewatering if found necessary and laid in layers morethan 15cm thick |
| 13 | Supply and errecting sheet centering of size 90 cm x 60cm 10 G sheet laid over silver oak joist and supported by casurina post of size 10 cm x 13 cm dia spaced at 75 cm center to center etc. complete |
| 14 | Plain Cement Concrete 1:2:4 mix using 20mm ISS HBG metal including cost and conveyance of all materials and labour charges etc. complete |
| 15 | Construction of Granular Sub base by providing well graded material (25 mm to 4.75 mm IRC HBG metal @ 65 %,4.75 to 2.36mm IRC HBG metal @20%&2.36 mm below IRC HBG metal @15%)& (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 25 & 6% repectively) spreading in uniform layers with motor grader on prepared surface mixing by mix in place method with rotovator at OMC and compacting with three wheel 80-100 KN capacity and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix -in - place method) |
| 16 | Providing and laying interlocking paver block of 80mm thick including all other labour charges etc |
| 17 | Provision For Name Board |
| 18 | GST Amount for providing Service to Government Contract Works for the above Construction Works. {GST Amount is the Total GST Amount for total overall quoted amount above this row in column \"BB\" for all works in this package} Please Enable Macros to View BoQ information |