| 1 | All in all comprehensive maintenanceof 11/0.415 KV or 33/0.415 KV Distribution sub station including 11 KV circuit Breaker , Transformerand its complete accessories , Auto transfer switch ,repairing of LT/HT cables with terminations, LT panel with complete accessories , APFC panel , Sub station Earthingsetc with maintaining of Log Books complete in all respect but excluding of transformer oil as and when required. |
| 2 | Up to 500 KVA sub stationjob per KVA/month 500x02 nos for 12 month |
| 3 | Repairing Serviceing,& Reinstallation of 315 KVA 11/0.433 KV Delta Star Connected Copper wound Transformer ( Make PRAKASH ) as per original winding Charecteristics (Old material shall be retain by the contractor) etc. as required complete in all respect |
| 4 | Replacement of existing transformer Oil (Old oil shall be retained by Contractor) |
| 5 | Replacement of packing Seal / Gasket of 315 KVA copper wound Transformer complete as required |
| 6 | Replacement of HV side Bushing brass Stand (Metal parts) of 315 KVA copper wound Transformer complete etc as required. |
| 7 | Replacement of Temp Meter of 315 KVA copper wound Transformer complete etc as required. |
| 8 | Replacement of Breather of 315 KVA copper wound Transformer complete etc as required. |
| 9 | Replacement of LT Expoxy Insulatators of 315 KVA copper wound Transformer complete etc as required. |
| 10 | Labour charges, painting charges, Ovening charges, Testing Charges, Tank Fabrication Charges for opening of top cover draining of oil De Tanking Coil Assembling covering and Retanking of core replacement of nuts bolts etc. |
| 11 | Loading, unloading and transportation of Transformer site to factory and factory to side back complete with help of crain as required. |
| 12 | All in all comprehensive maintenance including servicing , replacement of fuel - filter, coolant ,lubricating oil etc of Diesel Generating set including auto mains failure(AMF) panel , change over switch , earthing etc as per OEM guidelines and maintenance manual complete in all respet. (Excluding replacement of only batteries as and when required.) |
| 13 | Up to 62.0 kvaDG set per kva.month 25 kvax01 no for 12 month |
| 14 | above 62.5 kva DG set add @20/ per kva month (250+200) = 450 kva for 12 month |
| 15 | All in all comprehensive maintenance of Automatic power factor correctionpanel includingrepair / replacement of defective componenets to maintain the power factor as per Discom\"s permissible limit and without any penalty or surcharge. |
| 16 | Up to 125 KVAR capacity APFC panel job per kvar per month 100 kvar for 12 month |
| 17 | above 100 kvar capacity APFC panel add @24/ per kvarjob per kvar per month 150 kvar for 12 month |
| 18 | Supply, Installation, Testing & Commissioning of 150Ah 12 V Tublar Lead Acid Battery Conforms to IS 13396-1992, High capacity plates ensure higher cranking ration works in temp. renge - 18 degree to 55 degree C, strudy PPCP (Polyopropylene coploymer) contains for durabilitty, Non spill vent plug with flame arrestor ceramic disc, heavy duty pillar & termination to withstand heavy currents, making duly connection. All as per approved by Enginner in charge. For additional technocal parameters of products /work rerer annexure \" A\" atteched with PWD Electrical BSR 2022 |